QnA 9.2.22.pdf

PDF 81 KB Posted

Attached to
ND FTNP THRO 11(10) South Unit Scenic Loop Slide Repair
Solicitation number
6982AF22B000024
Issued by

About this file

This document contains questions and answers from an advertisement for a federal transportation contract opportunity to repair a scenic loop road within a national park. The opportunity involves reconstructing 6 miles of road, including installing soldier pile walls at locations with unstable subgrade, lime stabilizing subgrade in multiple areas, replacing culverts and concrete work, and repaving the entire length. The road is currently closed to traffic and will remain so during construction. Attention to detail is required due to environmental and cultural resource constraints. The estimated price range for the work is $40-50 million. Methods, materials, and a wage determination are specified. Excess material from road reconstruction can be used as backfill on site.

View the file

Other files

File Type Posted
Bid Opening Summary.pdf PDF
A006.pdf PDF
QnA 11.10.22.pdf PDF
A005.pdf PDF
QnA 11.7.22.pdf PDF
A004 Plan Sheets.pdf PDF
A004.pdf PDF
QnA 10.24.22.pdf PDF
FINAL_ND THRO_MP 24.1 & 24.5 Rpt_20211030.pdf PDF
QnA 10.13.22.pdf PDF
A003.pdf PDF
A002.pdf PDF
QnA 9.15.22.pdf PDF
A001.pdf PDF
Final Theodore Roosevelt Pavement Design Report 04-15-22.pdf PDF
ND FTNP THRO 11(10) Plans 3 of 4.pdf.pdf PDF
ND FTNP THRO 11(10) H and H Report.pdf PDF
Final Geotech Report Theodore Roosevelt National Park 221-230_07-01-22.pdf PDF
6982AF22B000024.pdf PDF
ND FTNP THRO 11(10) Plans 1 of 4.pdf PDF
ND FTNP THRO 11(10) Plans 2 of 4.pdf PDF
ND FTNP THRO 11(10) Plans 4 of 4.pdf.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for

ND FTNP THRO 11(10) South Unit Scenic Loop Slide Repair

September 2, 2022

Questions Answers

1 Would the government allow for a different Federal wage schedule from a different state it the total fringe and wage was the same or more?

No. The successful contractor must use the wage determination included with the solicitation, to include any amendments to it. However, this does not preclude the successful contractor from paying more than the minimum rates within the wage determination.

2 Section 305.01 states that the top 4” of FDR material gets removed to accommodate the 4” of new asphalt. Does the government have an area that we can waste the excess material that does not get used for roadway aggregate or is the contractor responsible to remove the material off site?

Excess FDR material can be used as backfill per Section 302.04.

3 SCR Section 152.05(f) can the government explain the reasoning behind not allowing the AMG method? It seems that allowing for this would be a savings to the department.

Concur – Amendment A002 will address this.

4 Is an asphalt plant allowed in the Mix Pit area shown on the site map?

No