This document contains a bid opening summary for the Upper West Branch Bridge project. Four bids were received by the bid opening deadline of April 26, 2022 at 2:00pm MST. The bids ranged from $1,984,538 to $2,289,726 with Hooker Creek, Inc. providing the lowest bid of $1,984,538. The engineer's estimate for the project was $1,455,000. All bids remain subject to verification by the contracting agency, the US Department of Transportation Federal Highway Administration, which issued solicitation number 6982AF22B000015 for the CA ERFO KLAMATH NF 18N31(1) UPPER WEST BRANCH BRIDGE project.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Opening Summary

Project Name: Upper West Branch Bridge Project Number: CA ERFO KLAMATH NF 18N31(1) Bid Opening Date: 4/26/2022 Time: 2:00 p.m. MST Bid Opening Location: Lakewood, CO Bid Opening Officer: Josephine Helms

Amendments: (1)_A001 4/22/2022

Bidder’s Name Schedule A BID TOTAL 1.

Hooker Creek, Inc., Red Bluff, CA $1,984,538.00 $1,984,538.00

2.

West Contractors, Coos Bay, OR $2,120,053.00 $2,120,053.00

3.

Hays & Sons, Inc., Montague, CA $2,289,726.00 $2,289,726.00

4.

5.

6.

7.

Engineer’s Estimate $1,455,000.00 $1,455,000.00

*All bids are subject to verification.

Bid Opening Summary
Bid Opening Date: 4/26/2022 Time: 2:00 p.m. MST
*All bids are subject to verification.