Bid Tabs CA ERFO KLAMATH NF 17N11 Upper Doolittle and Mill Creek bridges.pdf

PDF 650 KB Posted

Attached to
CA ERFO KLAMATH NF 17N11(1) Upper Doolittle & Mill Creek Bridges
Solicitation number
6982AF22B000003
Issued by

About this file

This document contains a bid tabulation report for a federal construction contract opportunity to replace two bridges on the Klamath National Forest in California. The Central Federal Lands Highway Division is seeking bids to demolish the existing Upper Doolittle Creek Bridge and Mill Creek Bridge, located on Forest Routes 17N11 and 18N15 respectively, and replace them. Hooker Creek, Inc. provided the lowest bid of $2,397,777 while Hayes & Sons, Inc. bid $3,232,050. The engineer's estimate was $2,356,000. Key work includes mobilization, excavation, structural concrete, reinforcing steel, pre-fabricated steel bridges, drilled shafts, guardrails, seeding and mulching. The solicitation number is 6982AF22B000003 and bids were opened on April 11, 2022. Award has not yet been made.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tabulation of Bids Report Date: 04/13/22

1 out of 7

Project No: CA ERFO KLAMATH NF 17N11(1)

Project Name: Upper Doolittle & Mill Creek Bridges

Schedule: A

Schedule Type: Base

Solcitation No: 6982AF22B000003

Division: Central Federal Lands

State: CA County: Siskiyou

Federal Land: Klamath National Forest Opened at: Lakewood, CO

Opened by: Leslie Karsten

Date: 04/11/22

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Hooker Creek, Inc. $2,397,777.00 1015 Anderson St.

Red Bluff, CA 96080

Hayes & Sons, Inc. $3,232,050.00 2606 Kuck Road Montague, CA 96064

Engineer's Estimate $2,356,000.00

Contract Specialist April 13, 2022

2 out of 7

Project No: CA ERFO KLAMATH NF 17N11(1)

Project Name: Upper Doolittle & Mill Creek Bridges

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0100 15101-0000 MOBILIZATION

Hooker Creek, Inc. Lump Sum $233,000.00 Hayes & Sons, Inc. Lump Sum $175,000.00 Engineer's Estimate ALL LPSM Lump Sum $381,350.00

A0120 15206-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING STAKE

Hooker Creek, Inc. $5,000.00 $500.00 Hayes & Sons, Inc. $40,000.00 $4,000.00 Engineer's Estimate 0.100 MILE $60,000.00 $6,000.00

A0140 15214-1000 SURVEY AND STAKING, BRIDGE

Hooker Creek, Inc. Lump Sum $16,000.00 Hayes & Sons, Inc. Lump Sum $20,000.00 Engineer's Estimate ALL LPSM Lump Sum $14,000.00

A0160 15216-2000 SURVEY AND STAKING, GRADE FINISHING STAKES

Hooker Creek, Inc. $50,000.00 $5,000.00 Hayes & Sons, Inc. $80,000.00 $8,000.00 Engineer's Estimate 0.100 MILE $20,000.00 $2,000.00

A0180 15301-0000 CONTRACTOR QUALITY CONTROL

Hooker Creek, Inc. Lump Sum $131,677.00 Hayes & Sons, Inc. Lump Sum $150,000.00 Engineer's Estimate ALL LPSM Lump Sum $68,000.00

A0200 15401-0000 CONTRACTOR TESTING

Hooker Creek, Inc. Lump Sum $50,000.00 Hayes & Sons, Inc. Lump Sum $150,000.00 Engineer's Estimate ALL LPSM Lump Sum $58,000.00

A0220 15501-0000 CONSTRUCTION SCHEDULE

Hooker Creek, Inc. Lump Sum $1,500.00 Hayes & Sons, Inc. Lump Sum $10,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00

3 out of 7

Project No: CA ERFO KLAMATH NF 17N11(1)

Project Name: Upper Doolittle & Mill Creek Bridges

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0240 15705-0100 SOIL EROSION CONTROL, SILT FENCE

Hooker Creek, Inc. $5.00 $7,500.00 Hayes & Sons, Inc. $15.00 $22,500.00 Engineer's Estimate 1,500 LNFT $10.00 $15,000.00

A0260 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

Hooker Creek, Inc. $5.00 $3,000.00 Hayes & Sons, Inc. $25.00 $15,000.00 Engineer's Estimate 600 LNFT $10.00 $6,000.00

A0280 20101-0000 CLEARING AND GRUBBING

Hooker Creek, Inc. $50,000.00 $20,000.00 Hayes & Sons, Inc. $20,000.00 $8,000.00 Engineer's Estimate 0.400 ACRE $25,000.00 $10,000.00

A0300 20401-0000 ROADWAY EXCAVATION

Hooker Creek, Inc. $35.00 $49,000.00 Hayes & Sons, Inc. $35.00 $49,000.00 Engineer's Estimate 1,400 CUYD $150.00 $210,000.00

A0320 20441-0000 WASTE

Hooker Creek, Inc. $55.00 $40,150.00 Hayes & Sons, Inc. $65.00 $47,450.00 Engineer's Estimate 730 CUYD $30.00 $21,900.00

A0340 20801-0000 STRUCTURE EXCAVATION

Hooker Creek, Inc. $400.00 $32,000.00 Hayes & Sons, Inc. $300.00 $24,000.00 Engineer's Estimate 80 CUYD $150.00 $12,000.00

A0360 20803-0000 STRUCTURAL BACKFILL

Hooker Creek, Inc. $700.00 $35,000.00 Hayes & Sons, Inc. $350.00 $17,500.00 Engineer's Estimate 50 CUYD $175.00 $8,750.00

4 out of 7

Project No: CA ERFO KLAMATH NF 17N11(1)

Project Name: Upper Doolittle & Mill Creek Bridges

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0380 30202-2000 ROADWAY AGGREGATE, METHOD 2

Hooker Creek, Inc. $120.00 $45,600.00 Hayes & Sons, Inc. $75.00 $28,500.00 Engineer's Estimate 380 TON $85.00 $32,300.00

A0400 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1

Hooker Creek, Inc. $300.00 $60,000.00 Hayes & Sons, Inc. $400.00 $80,000.00 Engineer's Estimate 200 TON $300.00 $60,000.00

A0420 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)

Hooker Creek, Inc. $3,000.00 $183,000.00 Hayes & Sons, Inc. $5,500.00 $335,500.00 Engineer's Estimate 61 CUYD $2,000.00 $122,000.00

A0440 55401-1000 REINFORCING STEEL

Hooker Creek, Inc. $3.50 $19,950.00 Hayes & Sons, Inc. $12.00 $68,400.00 Engineer's Estimate 5,700 LB $5.00 $28,500.00

A0460 55504-0000 PRE-FABRICATED STEEL BRIDGE (16'x68')

Hooker Creek, Inc. Lump Sum $260,000.00 Hayes & Sons, Inc. Lump Sum $500,000.00 Engineer's Estimate ALL LPSM Lump Sum $275,000.00

A0480 55504-0000 PRE-FABRICATED STEEL BRIDGE (28'x58')

Hooker Creek, Inc. Lump Sum $360,000.00 Hayes & Sons, Inc. Lump Sum $500,000.00 Engineer's Estimate ALL LPSM Lump Sum $400,000.00

A0500 56501-0200 DRILLED SHAFT, 24-INCH DIAMETER

Hooker Creek, Inc. $1,550.00 $688,200.00 Hayes & Sons, Inc. $1,800.00 $799,200.00 Engineer's Estimate 444 LNFT $1,000.00 $444,000.00

5 out of 7

Project No: CA ERFO KLAMATH NF 17N11(1)

Project Name: Upper Doolittle & Mill Creek Bridges

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0520 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS

Hooker Creek, Inc. $80.00 $16,000.00 Hayes & Sons, Inc. $150.00 $30,000.00 Engineer's Estimate 200 LNFT $50.00 $10,000.00

A0540 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT

Hooker Creek, Inc. $8,000.00 $64,000.00 Hayes & Sons, Inc. $6,000.00 $48,000.00 Engineer's Estimate 8 EACH $7,000.00 $56,000.00

A0560 61707-0000 STRUCTURE TRANSITION RAILING

Hooker Creek, Inc. $300.00 $30,000.00 Hayes & Sons, Inc. $350.00 $35,000.00 Engineer's Estimate 100 LNFT $150.00 $15,000.00

A0580 62201-0200 DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY

Hooker Creek, Inc. $165.00 $3,300.00 Hayes & Sons, Inc. $175.00 $3,500.00 Engineer's Estimate 20 HOUR $220.00 $4,400.00

A0600 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH

Hooker Creek, Inc. $145.00 $2,900.00 Hayes & Sons, Inc. $160.00 $3,200.00 Engineer's Estimate 20 HOUR $250.00 $5,000.00

A0620 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY

Hooker Creek, Inc. $190.00 $3,800.00 Hayes & Sons, Inc. $250.00 $5,000.00 Engineer's Estimate 20 HOUR $225.00 $4,500.00

A0640 62201-2750 MOTOR GRADER

Hooker Creek, Inc. $200.00 $4,000.00 Hayes & Sons, Inc. $195.00 $3,900.00 Engineer's Estimate 20 HOUR $300.00 $6,000.00

6 out of 7

Project No: CA ERFO KLAMATH NF 17N11(1)

Project Name: Upper Doolittle & Mill Creek Bridges

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0660 62301-0000 GENERAL LABOR

Hooker Creek, Inc. $80.00 $1,600.00 Hayes & Sons, Inc. $80.00 $1,600.00 Engineer's Estimate 20 HOUR $115.00 $2,300.00

A0680 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES

Hooker Creek, Inc. $200.00 $4,000.00 Hayes & Sons, Inc. $400.00 $8,000.00 Engineer's Estimate 20 HOUR $200.00 $4,000.00

A0700 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES

Hooker Creek, Inc. $250.00 $5,000.00 Hayes & Sons, Inc. $280.00 $5,600.00 Engineer's Estimate 20 HOUR $220.00 $4,400.00

A0720 62511-2000 SEEDING, HYDRAULIC METHOD

Hooker Creek, Inc. $2.00 $4,000.00 Hayes & Sons, Inc. $5.00 $10,000.00 Engineer's Estimate 2,000 SQYD $6.00 $12,000.00

A0740 62516-2000 MULCHING, HYDRAULIC METHOD

Hooker Creek, Inc. $2.00 $4,000.00 Hayes & Sons, Inc. $5.00 $10,000.00 Engineer's Estimate 2,000 SQYD $7.00 $14,000.00

A0760 63301-0000 SIGN SYSTEM

Hooker Creek, Inc. $650.00 $1,300.00 Hayes & Sons, Inc. $2,000.00 $4,000.00 Engineer's Estimate 2 EACH $600.00 $1,200.00

A0780 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3

Hooker Creek, Inc. $200.00 $1,600.00 Hayes & Sons, Inc. $500.00 $4,000.00 Engineer's Estimate 8 EACH $500.00 $4,000.00

7 out of 7

Project No: CA ERFO KLAMATH NF 17N11(1)

Project Name: Upper Doolittle & Mill Creek Bridges

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0800 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B

Hooker Creek, Inc. $50.00 $200.00 Hayes & Sons, Inc. $300.00 $1,200.00 Engineer's Estimate 4 EACH $250.00 $1,000.00

A0820 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

Hooker Creek, Inc. $25.00 $1,000.00 Hayes & Sons, Inc. $300.00 $12,000.00 Engineer's Estimate 40 SQFT $60.00 $2,400.00

A0840 63701-0000 FIELD OFFICE

Hooker Creek, Inc. $10,000.00 $10,000.00 Hayes & Sons, Inc. $35,000.00 $35,000.00 Engineer's Estimate 1 EACH $25,000.00 $25,000.00

Total Schedule - All Items

Hooker Creek, Inc. $2,397,777.00 Hayes & Sons, Inc. $3,232,050.00 Engineer's Estimate $2,356,000.00