This bid tabulation report summarizes bids received in response to Solicitation Number 6982AF20B000040 issued by the Department of Transportation Federal Highway Administration. The solicitation sought bids for construction of an entrance road and parking areas at the Rio Mora National Wildlife Refuge in New Mexico. Responsive Construction Solutions Group, LLC provided the lowest bid of $1,491,031.04. The second lowest bid was from LaForge and Budd Construction Company, Inc. at $2,121,158.75. Higher bids ranged from $2,192,517.30 to $3,022,696.00. The engineer's estimate for the work was $1,949,000.00. The bid tabulation provides unit pricing and totals for over 100 individual line items for the various construction tasks required to complete the project, including items such as roadway excavation, asphalt paving, fencing, signage and temporary traffic control. Construction is scheduled to be awarded by December 22, 2020.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tabulation of Bids Report Date: 12/21/20
1 out of 14Source Selection Information - See FAR 2.101 & 3.104
Project No: NM FTFW RIMO 10(1)
Project Name: Entrance Road and Parking Areas
Schedule: A
Schedule Type: Base
Solcitation No: 6982AF20B000040
Division: Central Federal Lands
State: NM County: Mora
Federal Land: Rio Mora National Wildlife Refuge Opened at: Lakewood
Opened by: Josephine Helms
Date: 12/02/20
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Construction Solutions Group, LLC $1,491,031.04 5512 Elk Valley Estates Dr St. Louis, MO 63128
LaForge and Budd Construction Company, Inc. $2,121,158.75 2020 North 21st Street Parsons, KS 67357
GC Works, Inc. $2,192,517.30 1820 SW 3rd Avenue Miami, FL 33129
R & M Government Services, Inc. $2,302,054.07 650 Montana Ave Las Cruces, NM 88001
Southwest General Construction, Inc. $2,422,500.95 1100 S. Main St. Suite 106 Las Cruces, NM 88005
Groundhog Excavating Inc. $2,658,079.16 792 Nikanda Rd NE Albuquerque, NM 87107
Meridian Contracting, Inc. $3,022,696.00 1615 1/2 University Blvd NE Suite A Albuquerque, NM 87102
Engineer's Estimate $1,949,000.00
Contract Specialist
12-22-2020
Non-Responsible
2 out of 14Source Selection Information - See FAR 2.101 & 3.104
Project No: NM FTFW RIMO 10(1)
Project Name: Entrance Road and Parking Areas
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0020 15101-0000 MOBILIZATION
Construction Solutions Group, LLC Lump Sum $191,900.00 LaForge and Budd Construction Company, Inc. Lump Sum $325,000.00 GC Works, Inc. Lump Sum $278,000.00 R & M Government Services, Inc. Lump Sum $80,018.00 Southwest General Construction, Inc. Lump Sum $260,587.80 Groundhog Excavating Inc. Lump Sum $182,181.38 Meridian Contracting, Inc. Lump Sum $200,000.00 Engineer's Estimate ALL LPSM Lump Sum $338,976.00
A0040 15205-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING STAKE
Construction Solutions Group, LLC Lump Sum $16,864.00 LaForge and Budd Construction Company, Inc. Lump Sum $35,000.00 GC Works, Inc. Lump Sum $35,236.00 R & M Government Services, Inc. Lump Sum $11,350.00 Southwest General Construction, Inc. Lump Sum $7,817.63 Groundhog Excavating Inc. Lump Sum $9,883.26 Meridian Contracting, Inc. Lump Sum $24,000.00 Engineer's Estimate ALL LPSM Lump Sum $30,000.00
A0060 15215-3000 SURVEY AND STAKING, DRAINAGE STRUCTURE
Construction Solutions Group, LLC $660.00 $5,280.00 LaForge and Budd Construction Company, Inc. $1,000.00 $8,000.00 GC Works, Inc. $6,922.00 $55,376.00 R & M Government Services, Inc. $5,675.00 $45,400.00 Southwest General Construction, Inc. $407.17 $3,257.36 Groundhog Excavating Inc. $5,929.95 $47,439.60 Meridian Contracting, Inc. $2,750.00 $22,000.00 Engineer's Estimate 8 EACH $1,000.00 $8,000.00
A0080 15236-2000 SURVEY CONTROL, GRADE FINISHING
Construction Solutions Group, LLC $5,280.00 $11,088.00 LaForge and Budd Construction Company, Inc. $8,500.00 $17,850.00 GC Works, Inc. $37,752.00 $79,279.20 R & M Government Services, Inc. $11,350.00 $23,835.00 Southwest General Construction, Inc. $1,861.34 $3,908.81 Groundhog Excavating Inc. $39,467.14 $82,880.99 Meridian Contracting, Inc. $16,000.00 $33,600.00 Engineer's Estimate 2.100 MILE $6,300.00 $13,230.00
3 out of 14Source Selection Information - See FAR 2.101 & 3.104
Project No: NM FTFW RIMO 10(1)
Project Name: Entrance Road and Parking Areas
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0100 15301-0000 CONTRACTOR QUALITY CONTROL
Construction Solutions Group, LLC Lump Sum $8,580.00 LaForge and Budd Construction Company, Inc. Lump Sum $85,000.00 GC Works, Inc. Lump Sum $81,796.00 R & M Government Services, Inc. Lump Sum $11,500.00 Southwest General Construction, Inc. Lump Sum $1,302.94 Groundhog Excavating Inc. Lump Sum $127,229.15 Meridian Contracting, Inc. Lump Sum $50,000.00 Engineer's Estimate ALL LPSM Lump Sum $35,000.00
A0120 15401-0000 CONTRACTOR TESTING
Construction Solutions Group, LLC Lump Sum $20,824.00 LaForge and Budd Construction Company, Inc. Lump Sum $50,000.00 GC Works, Inc. Lump Sum $85,000.00 R & M Government Services, Inc. Lump Sum $34,050.00 Southwest General Construction, Inc. Lump Sum $13,029.39 Groundhog Excavating Inc. Lump Sum $21,057.93 Meridian Contracting, Inc. Lump Sum $200,000.00 Engineer's Estimate ALL LPSM Lump Sum $35,000.00
A0140 15501-0000 CONSTRUCTION SCHEDULE
Construction Solutions Group, LLC Lump Sum $15,940.00 LaForge and Budd Construction Company, Inc. Lump Sum $5,000.00 GC Works, Inc. Lump Sum $12,584.00 R & M Government Services, Inc. Lump Sum $5,675.00 Southwest General Construction, Inc. Lump Sum $1,302.94 Groundhog Excavating Inc. Lump Sum $7,800.00 Meridian Contracting, Inc. Lump Sum $20,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00
A0160 15701-0000 SOIL EROSION CONTROL (TEMPORARY CONSTRUCTION CONTROLS)
Construction Solutions Group, LLC Lump Sum $13,200.00 LaForge and Budd Construction Company, Inc. Lump Sum $50,000.00 GC Works, Inc. Lump Sum $17,442.00 R & M Government Services, Inc. Lump Sum $17,025.00 Southwest General Construction, Inc. Lump Sum $6,514.70 Groundhog Excavating Inc. Lump Sum $18,185.19 Meridian Contracting, Inc. Lump Sum $75,000.00 Engineer's Estimate ALL LPSM Lump Sum $20,000.00
4 out of 14Source Selection Information - See FAR 2.101 & 3.104
Project No: NM FTFW RIMO 10(1)
Project Name: Entrance Road and Parking Areas
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0180 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
Construction Solutions Group, LLC Lump Sum $7,920.00 LaForge and Budd Construction Company, Inc. Lump Sum $20,000.00 GC Works, Inc. Lump Sum $62,920.00 R & M Government Services, Inc. Lump Sum $28,375.00 Southwest General Construction, Inc. Lump Sum $6,514.70 Groundhog Excavating Inc. Lump Sum $10,515.79 Meridian Contracting, Inc. Lump Sum $15,000.00 Engineer's Estimate ALL LPSM Lump Sum $5,000.00
A0200 20101-0000 CLEARING AND GRUBBING
Construction Solutions Group, LLC $8,300.00 $33,200.00 LaForge and Budd Construction Company, Inc. $2,500.00 $10,000.00 GC Works, Inc. $8,306.00 $33,224.00 R & M Government Services, Inc. $3,972.50 $15,890.00 Southwest General Construction, Inc. $3,257.35 $13,029.40 Groundhog Excavating Inc. $14,614.04 $58,456.16 Meridian Contracting, Inc. $3,500.00 $14,000.00 Engineer's Estimate 4 ACRE $4,300.00 $17,200.00
A0220 20301-0600 REMOVAL OF CATTLE GUARD
Construction Solutions Group, LLC $1,980.00 $1,980.00 LaForge and Budd Construction Company, Inc. $2,500.00 $2,500.00 GC Works, Inc. $1,484.00 $1,484.00 R & M Government Services, Inc. $5,680.00 $5,680.00 Southwest General Construction, Inc. $1,302.94 $1,302.94 Groundhog Excavating Inc. $6,588.84 $6,588.84 Meridian Contracting, Inc. $6,446.00 $6,446.00 Engineer's Estimate 1 EACH $2,600.00 $2,600.00
A0240 20301-1100 REMOVAL OF GATE
Construction Solutions Group, LLC $264.00 $792.00 LaForge and Budd Construction Company, Inc. $500.00 $1,500.00 GC Works, Inc. $387.00 $1,161.00 R & M Government Services, Inc. $2,837.50 $8,512.50 Southwest General Construction, Inc. $325.74 $977.22 Groundhog Excavating Inc. $1,976.65 $5,929.95 Meridian Contracting, Inc. $2,400.00 $7,200.00 Engineer's Estimate 3 EACH $1,100.00 $3,300.00
5 out of 14Source Selection Information - See FAR 2.101 & 3.104
Project No: NM FTFW RIMO 10(1)
Project Name: Entrance Road and Parking Areas
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0260 20301-2400 REMOVAL OF SIGN
Construction Solutions Group, LLC $132.00 $792.00 LaForge and Budd Construction Company, Inc. $250.00 $1,500.00 GC Works, Inc. $126.00 $756.00 R & M Government Services, Inc. $113.50 $681.00 Southwest General Construction, Inc. $130.29 $781.74 Groundhog Excavating Inc. $395.33 $2,371.98 Meridian Contracting, Inc. $250.00 $1,500.00 Engineer's Estimate 6 EACH $135.00 $810.00
A0280 20302-0700 REMOVAL OF FENCE
Construction Solutions Group, LLC $2.64 $1,808.40 LaForge and Budd Construction Company, Inc. $9.00 $6,165.00 GC Works, Inc. $17.00 $11,645.00 R & M Government Services, Inc. $11.35 $7,774.75 Southwest General Construction, Inc. $1.90 $1,301.50 Groundhog Excavating Inc. $13.18 $9,028.30 Meridian Contracting, Inc. $10.00 $6,850.00 Engineer's Estimate 685 LNFT $5.00 $3,425.00
A0300 20302-2100 REMOVAL OF PIPE CULVERT
Construction Solutions Group, LLC $13.20 $752.40 LaForge and Budd Construction Company, Inc. $30.00 $1,710.00 GC Works, Inc. $277.00 $15,789.00 R & M Government Services, Inc. $28.38 $1,617.66 Southwest General Construction, Inc. $57.15 $3,257.55 Groundhog Excavating Inc. $50.08 $2,854.56 Meridian Contracting, Inc. $120.00 $6,840.00 Engineer's Estimate 57 LNFT $40.00 $2,280.00
A0320 20315-0000 SAWCUTTING PAVEMENT
Construction Solutions Group, LLC $13.20 $858.00 LaForge and Budd Construction Company, Inc. $10.00 $650.00 GC Works, Inc. $32.00 $2,080.00 R & M Government Services, Inc. $3.41 $221.65 Southwest General Construction, Inc. $20.05 $1,303.25 Groundhog Excavating Inc. $13.18 $856.70 Meridian Contracting, Inc. $15.00 $975.00 Engineer's Estimate 65 LNFT $2.00 $130.00
6 out of 14Source Selection Information - See FAR 2.101 & 3.104
Project No: NM FTFW RIMO 10(1)
Project Name: Entrance Road and Parking Areas
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0340 20401-0000 ROADWAY EXCAVATION
Construction Solutions Group, LLC $7.30 $36,500.00 LaForge and Budd Construction Company, Inc. $25.00 $125,000.00 GC Works, Inc. $19.00 $95,000.00 R & M Government Services, Inc. $17.03 $85,150.00 Southwest General Construction, Inc. $39.09 $195,450.00 Groundhog Excavating Inc. $25.04 $125,200.00 Meridian Contracting, Inc. $30.00 $150,000.00 Engineer's Estimate 5,000 CUYD $30.00 $150,000.00
A0360 20441-0000 WASTE
Construction Solutions Group, LLC $7.92 $16,362.72 LaForge and Budd Construction Company, Inc. $6.00 $12,396.00 GC Works, Inc. $24.00 $49,584.00 R & M Government Services, Inc. $11.36 $23,469.76 Southwest General Construction, Inc. $31.53 $65,140.98 Groundhog Excavating Inc. $26.36 $54,459.76 Meridian Contracting, Inc. $12.00 $24,792.00 Engineer's Estimate 2,066 CUYD $20.00 $41,320.00
A0380 25101-0200 PLACED RIPRAP, METHOD A, CLASS 2
Construction Solutions Group, LLC $194.21 $7,574.19 LaForge and Budd Construction Company, Inc. $300.00 $11,700.00 GC Works, Inc. $119.00 $4,641.00 R & M Government Services, Inc. $283.75 $11,066.25 Southwest General Construction, Inc. $2,672.70 $104,235.30 Groundhog Excavating Inc. $395.33 $15,417.87 Meridian Contracting, Inc. $550.00 $21,450.00 Engineer's Estimate 39 CUYD $120.00 $4,680.00
A0400 25120-0200 RIPRAP DITCH, METHOD A, CLASS 2
Construction Solutions Group, LLC $105.73 $58,151.50 LaForge and Budd Construction Company, Inc. $50.00 $27,500.00 GC Works, Inc. $131.00 $72,050.00 R & M Government Services, Inc. $85.13 $46,821.50 Southwest General Construction, Inc. $868.62 $477,741.00 Groundhog Excavating Inc. $329.44 $181,192.00 Meridian Contracting, Inc. $100.00 $55,000.00 Engineer's Estimate 550 LNFT $100.00 $55,000.00
7 out of 14Source Selection Information - See FAR 2.101 & 3.104
Project No: NM FTFW RIMO 10(1)
Project Name: Entrance Road and Parking Areas
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0420 25125-0000 BOULDER
Construction Solutions Group, LLC $264.00 $19,800.00 LaForge and Budd Construction Company, Inc. $600.00 $45,000.00 GC Works, Inc. $258.00 $19,350.00 R & M Government Services, Inc. $1,021.50 $76,612.50 Southwest General Construction, Inc. $399.57 $29,967.75 Groundhog Excavating Inc. $593.00 $44,475.00 Meridian Contracting, Inc. $500.00 $37,500.00 Engineer's Estimate 75 EACH $400.00 $30,000.00
A0440 30110-0000 AGGREGATE SURFACE COURSE
Construction Solutions Group, LLC $38.38 $498,940.00 LaForge and Budd Construction Company, Inc. $55.00 $715,000.00 GC Works, Inc. $38.00 $494,000.00 R & M Government Services, Inc. $56.75 $737,750.00 Southwest General Construction, Inc. $39.09 $508,170.00 Groundhog Excavating Inc. $63.25 $822,250.00 Meridian Contracting, Inc. $78.00 $1,014,000.00 Engineer's Estimate 13,000 TON $40.00 $520,000.00
A0480 40301-0000 ASPHALT CONCRETE PAVEMENT
Construction Solutions Group, LLC $462.00 $11,550.00 LaForge and Budd Construction Company, Inc. $300.00 $7,500.00 GC Works, Inc. $378.00 $9,450.00 R & M Government Services, Inc. $170.25 $4,256.25 Southwest General Construction, Inc. $260.59 $6,514.75 Groundhog Excavating Inc. $325.49 $8,137.25 Meridian Contracting, Inc. $650.00 $16,250.00 Engineer's Estimate 25 TON $160.00 $4,000.00
A0500 40601-0000 FOG SEAL
Construction Solutions Group, LLC $19,800.00 $1,980.00 LaForge and Budd Construction Company, Inc. $10,000.00 $1,000.00 GC Works, Inc. $3,146.00 $314.60 R & M Government Services, Inc. $11,350.00 $1,135.00 Southwest General Construction, Inc. $6,514.70 $651.47 Groundhog Excavating Inc. $6,588.84 $658.88 Meridian Contracting, Inc. $25,500.00 $2,550.00 Engineer's Estimate 0.10 TON $10,000.00 $1,000.00
8 out of 14Source Selection Information - See FAR 2.101 & 3.104
Project No: NM FTFW RIMO 10(1)
Project Name: Entrance Road and Parking Areas
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0520 41101-1000 PRIME COAT, METHOD 1
Construction Solutions Group, LLC $16,500.00 $3,300.00 LaForge and Budd Construction Company, Inc. $2,500.00 $500.00 GC Works, Inc. $3,146.00 $629.20 R & M Government Services, Inc. $8,512.50 $1,702.50 Southwest General Construction, Inc. $6,514.70 $1,302.94 Groundhog Excavating Inc. $6,588.84 $1,317.77 Meridian Contracting, Inc. $12,000.00 $2,400.00 Engineer's Estimate 0.20 TON $3,300.00 $660.00
A0540 41105-0000 BLOTTER
Construction Solutions Group, LLC $9,900.00 $1,980.00 LaForge and Budd Construction Company, Inc. $2,500.00 $500.00 GC Works, Inc. $3,146.00 $629.20 R & M Government Services, Inc. $4,540.00 $908.00 Southwest General Construction, Inc. $6,514.70 $1,302.94 Groundhog Excavating Inc. $1,976.65 $395.33 Meridian Contracting, Inc. $7,500.00 $1,500.00 Engineer's Estimate 0.2 TON $900.00 $180.00
A0560 41201-0000 TACK COAT
Construction Solutions Group, LLC $10,560.00 $1,056.00 LaForge and Budd Construction Company, Inc. $5,000.00 $500.00 GC Works, Inc. $3,146.00 $314.60 R & M Government Services, Inc. $11,370.00 $1,137.00 Southwest General Construction, Inc. $13,029.40 $1,302.94 Groundhog Excavating Inc. $1,976.65 $197.67 Meridian Contracting, Inc. $15,000.00 $1,500.00 Engineer's Estimate 0.10 TON $1,600.00 $160.00
A0580 50101-2600 MINOR CONCRETE PAVEMENT, PLAIN, 6-INCH DEPTH
Construction Solutions Group, LLC $66.00 $5,874.00 LaForge and Budd Construction Company, Inc. $100.00 $8,900.00 GC Works, Inc. $145.00 $12,905.00 R & M Government Services, Inc. $143.58 $12,778.62 Southwest General Construction, Inc. $146.40 $13,029.60 Groundhog Excavating Inc. $36.90 $3,284.10 Meridian Contracting, Inc. $180.00 $16,020.00 Engineer's Estimate 89 SQYD $200.00 $17,800.00
9 out of 14Source Selection Information - See FAR 2.101 & 3.104
Project No: NM FTFW RIMO 10(1)
Project Name: Entrance Road and Parking Areas
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0600 60201-0800 24-INCH PIPE CULVERT
Construction Solutions Group, LLC $72.60 $20,328.00 LaForge and Budd Construction Company, Inc. $125.00 $35,000.00 GC Works, Inc. $90.00 $25,200.00 R & M Government Services, Inc. $113.50 $31,780.00 Southwest General Construction, Inc. $195.44 $54,723.20 Groundhog Excavating Inc. $121.23 $33,944.40 Meridian Contracting, Inc. $230.00 $64,400.00 Engineer's Estimate 280 LNFT $145.00 $40,600.00
A0620 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT
Construction Solutions Group, LLC $330.00 $2,310.00 LaForge and Budd Construction Company, Inc. $750.00 $5,250.00 GC Works, Inc. $2,058.00 $14,406.00 R & M Government Services, Inc. $851.25 $5,958.75 Southwest General Construction, Inc. $1,302.94 $9,120.58 Groundhog Excavating Inc. $206.89 $1,448.23 Meridian Contracting, Inc. $750.00 $5,250.00 Engineer's Estimate 7 EACH $1,000.00 $7,000.00
A0640 60915-1000 WHEELSTOP, CONCRETE
Construction Solutions Group, LLC $330.00 $660.00 LaForge and Budd Construction Company, Inc. $500.00 $1,000.00 GC Works, Inc. $189.00 $378.00 R & M Government Services, Inc. $170.25 $340.50 Southwest General Construction, Inc. $130.30 $260.60 Groundhog Excavating Inc. $1,317.77 $2,635.54 Meridian Contracting, Inc. $900.00 $1,800.00 Engineer's Estimate 2 EACH $180.00 $360.00
A0660 61701-5150 GUARDRAIL SYSTEM MGS, TYPE 4, CLASS B WOOD POSTS
Construction Solutions Group, LLC $13.86 $29,452.50 LaForge and Budd Construction Company, Inc. $39.43 $83,788.75 GC Works, Inc. $66.00 $140,250.00 R & M Government Services, Inc. $73.78 $156,782.50 Southwest General Construction, Inc. $76.64 $162,860.00 Groundhog Excavating Inc. $42.70 $90,737.50 Meridian Contracting, Inc. $40.00 $85,000.00 Engineer's Estimate 2,125 LNFT $35.00 $74,375.00
10 out of 14Source Selection Information - See FAR 2.101 & 3.104
Project No: NM FTFW RIMO 10(1)
Project Name: Entrance Road and Parking Areas
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0680 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT
Construction Solutions Group, LLC $3,960.00 $7,920.00 LaForge and Budd Construction Company, Inc. $3,525.00 $7,050.00 GC Works, Inc. $6,418.00 $12,836.00 R & M Government Services, Inc. $3,405.00 $6,810.00 Southwest General Construction, Inc. $6,514.70 $13,029.40 Groundhog Excavating Inc. $4,941.63 $9,883.26 Meridian Contracting, Inc. $4,500.00 $9,000.00 Engineer's Estimate 2 EACH $3,500.00 $7,000.00
A0700 61901-1000 FENCE, BARBED WIRE, 5 STRAND
Construction Solutions Group, LLC $26.40 $12,276.00 LaForge and Budd Construction Company, Inc. $15.00 $6,975.00 GC Works, Inc. $5.00 $2,325.00 R & M Government Services, Inc. $13.11 $6,096.15 Southwest General Construction, Inc. $11.21 $5,212.65 Groundhog Excavating Inc. $32.94 $15,317.10 Meridian Contracting, Inc. $60.00 $27,900.00 Engineer's Estimate 465 LNFT $5.00 $2,325.00
A0720 61902-0900 GATE, METAL
Construction Solutions Group, LLC $1,056.00 $1,056.00 LaForge and Budd Construction Company, Inc. $15,475.00 $15,475.00 GC Works, Inc. $20,000.00 $20,000.00 R & M Government Services, Inc. $3,972.50 $3,972.50 Southwest General Construction, Inc. $651.47 $651.47 Groundhog Excavating Inc. $5,271.07 $5,271.07 Meridian Contracting, Inc. $10,000.00 $10,000.00 Engineer's Estimate 1 EACH $20,000.00 $20,000.00
A0740 61902-1800 GATE, METAL, 24 FEET WIDTH (AUTOMATIC)
Construction Solutions Group, LLC $19,140.00 $19,140.00 LaForge and Budd Construction Company, Inc. $100,000.00 $100,000.00 GC Works, Inc. $35,000.00 $35,000.00 R & M Government Services, Inc. $28,375.00 $28,375.00 Southwest General Construction, Inc. $19,544.09 $19,544.09 Groundhog Excavating Inc. $37,855.51 $37,855.51 Meridian Contracting, Inc. $224,000.00 $224,000.00 Engineer's Estimate 1 EACH $25,000.00 $25,000.00
11 out of 14Source Selection Information - See FAR 2.101 & 3.104
Project No: NM FTFW RIMO 10(1)
Project Name: Entrance Road and Parking Areas
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0760 61903-0700 CATTLE GUARD, 24 FEET BISON GATE
Construction Solutions Group, LLC $13,860.00 $55,440.00 LaForge and Budd Construction Company, Inc. $40,000.00 $160,000.00 GC Works, Inc. $22,000.00 $88,000.00 R & M Government Services, Inc. $28,375.00 $113,500.00 Southwest General Construction, Inc. $8,143.37 $32,573.48 Groundhog Excavating Inc. $17,921.64 $71,686.56 Meridian Contracting, Inc. $38,000.00 $152,000.00 Engineer's Estimate 4 EACH $23,000.00 $92,000.00
A0780 62406-0300 PLACING CONSERVED TOPSOIL, 4-INCH DEPTH
Construction Solutions Group, LLC $26,400.00 $118,800.00 LaForge and Budd Construction Company, Inc. $7,500.00 $33,750.00 GC Works, Inc. $11,955.00 $53,797.50 R & M Government Services, Inc. $2,837.50 $12,768.75 Southwest General Construction, Inc. $23,163.36 $104,235.12 Groundhog Excavating Inc. $7,906.61 $35,579.75 Meridian Contracting, Inc. $7,500.00 $33,750.00 Engineer's Estimate 4.50 ACRE $5,000.00 $22,500.00
A0800 62510-2000 SEEDING, HYDRAULIC METHOD
Construction Solutions Group, LLC $3,960.00 $17,820.00 LaForge and Budd Construction Company, Inc. $1,467.00 $6,601.50 GC Works, Inc. $10,068.00 $45,306.00 R & M Government Services, Inc. $5,675.00 $25,537.50 Southwest General Construction, Inc. $7,238.55 $32,573.48 Groundhog Excavating Inc. $6,259.40 $28,167.30 Meridian Contracting, Inc. $2,500.00 $11,250.00 Engineer's Estimate 4.50 ACRE $3,000.00 $13,500.00
A0820 62515-2000 MULCHING, HYDRAULIC METHOD
Construction Solutions Group, LLC $3,960.00 $17,820.00 LaForge and Budd Construction Company, Inc. $1,280.00 $5,760.00 GC Works, Inc. $10,068.00 $45,306.00 R & M Government Services, Inc. $7,377.50 $33,198.75 Southwest General Construction, Inc. $5,790.84 $26,058.78 Groundhog Excavating Inc. $6,259.40 $28,167.30 Meridian Contracting, Inc. $2,200.00 $9,900.00 Engineer's Estimate 4.50 ACRE $3,000.00 $13,500.00
12 out of 14Source Selection Information - See FAR 2.101 & 3.104
Project No: NM FTFW RIMO 10(1)
Project Name: Entrance Road and Parking Areas
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0840 63301-0000 SIGN SYSTEM
Construction Solutions Group, LLC $330.00 $3,630.00 LaForge and Budd Construction Company, Inc. $400.00 $4,400.00 GC Works, Inc. $265.00 $2,915.00 R & M Government Services, Inc. $567.50 $6,242.50 Southwest General Construction, Inc. $355.35 $3,908.85 Groundhog Excavating Inc. $658.88 $7,247.68 Meridian Contracting, Inc. $600.00 $6,600.00 Engineer's Estimate 11 EACH $350.00 $3,850.00
A0860 63309-0200 DELINEATOR, TYPE 2
Construction Solutions Group, LLC $132.00 $10,560.00 LaForge and Budd Construction Company, Inc. $50.00 $4,000.00 GC Works, Inc. $63.00 $5,040.00 R & M Government Services, Inc. $170.25 $13,620.00 Southwest General Construction, Inc. $48.86 $3,908.80 Groundhog Excavating Inc. $65.89 $5,271.20 Meridian Contracting, Inc. $50.00 $4,000.00 Engineer's Estimate 80 EACH $90.00 $7,200.00
A0880 63401-0000 PAVEMENT MARKINGS
Construction Solutions Group, LLC $13.20 $3,669.60 LaForge and Budd Construction Company, Inc. $11.00 $3,058.00 GC Works, Inc. $13.00 $3,614.00 R & M Government Services, Inc. $2.27 $631.06 Southwest General Construction, Inc. $7.03 $1,954.34 Groundhog Excavating Inc. $3.56 $989.68 Meridian Contracting, Inc. $3.00 $834.00 Engineer's Estimate 278 LNFT $3.00 $834.00
A0900 63405-0850 PAVEMENT MARKINGS, TYPE B, ACCESSIBILITY SYMBOL
Construction Solutions Group, LLC $264.00 $528.00 LaForge and Budd Construction Company, Inc. $250.00 $500.00 GC Works, Inc. $969.00 $1,938.00 R & M Government Services, Inc. $510.75 $1,021.50 Southwest General Construction, Inc. $325.74 $651.48 Groundhog Excavating Inc. $445.41 $890.82 Meridian Contracting, Inc. $500.00 $1,000.00 Engineer's Estimate 2 EACH $460.00 $920.00
13 out of 14Source Selection Information - See FAR 2.101 & 3.104
Project No: NM FTFW RIMO 10(1)
Project Name: Entrance Road and Parking Areas
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0920 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
Construction Solutions Group, LLC $26.40 $5,280.00 LaForge and Budd Construction Company, Inc. $35.00 $7,000.00 GC Works, Inc. $126.00 $25,200.00 R & M Government Services, Inc. $56.75 $11,350.00 Southwest General Construction, Inc. $104.24 $20,848.00 Groundhog Excavating Inc. $131.78 $26,356.00 Meridian Contracting, Inc. $200.00 $40,000.00 Engineer's Estimate 200 EACH $87.00 $17,400.00
A0940 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
Construction Solutions Group, LLC $66.00 $8,250.00 LaForge and Budd Construction Company, Inc. $20.00 $2,500.00 GC Works, Inc. $70.00 $8,750.00 R & M Government Services, Inc. $28.38 $3,547.50 Southwest General Construction, Inc. $104.24 $13,030.00 Groundhog Excavating Inc. $13.18 $1,647.50 Meridian Contracting, Inc. $160.00 $20,000.00 Engineer's Estimate 125 SQFT $19.00 $2,375.00
A0960 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
Construction Solutions Group, LLC $33.00 $2,640.00 LaForge and Budd Construction Company, Inc. $40.00 $3,200.00 GC Works, Inc. $18.00 $1,440.00 R & M Government Services, Inc. $39.73 $3,178.40 Southwest General Construction, Inc. $32.57 $2,605.60 Groundhog Excavating Inc. $197.67 $15,813.60 Meridian Contracting, Inc. $40.00 $3,200.00 Engineer's Estimate 80 HOUR $36.00 $2,880.00
A0980 63610-1600 CONDUIT, 2-INCH, PVC
Construction Solutions Group, LLC $3.96 $47,405.16 LaForge and Budd Construction Company, Inc. $3.00 $35,913.00 GC Works, Inc. $5.00 $59,855.00 R & M Government Services, Inc. $28.38 $339,736.98 Southwest General Construction, Inc. $10.45 $125,096.95 Groundhog Excavating Inc. $18.71 $223,977.41 Meridian Contracting, Inc. $7.00 $83,797.00 Engineer's Estimate 11,971 LNFT $5.00 $59,855.00
14 out of 14Source Selection Information - See FAR 2.101 & 3.104
Project No: NM FTFW RIMO 10(1)
Project Name: Entrance Road and Parking Areas
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1000 63621-1000 UTILITY BOX, PULLBOX
Construction Solutions Group, LLC $924.00 $20,328.00 LaForge and Budd Construction Company, Inc. $700.00 $15,400.00 GC Works, Inc. $50.00 $1,100.00 R & M Government Services, Inc. $1,078.25 $23,721.50 Southwest General Construction, Inc. $888.37 $19,544.14 Groundhog Excavating Inc. $1,619.89 $35,637.58 Meridian Contracting, Inc. $3,100.00 $68,200.00 Engineer's Estimate 22 EACH $1,500.00 $33,000.00
A1020 63622-0000 UTILITY TRENCH
Construction Solutions Group, LLC $14.87 $90,870.57 LaForge and Budd Construction Company, Inc. $1.50 $9,166.50 GC Works, Inc. $11.00 $67,221.00 R & M Government Services, Inc. $28.39 $173,491.29 Southwest General Construction, Inc. $6.40 $39,110.40 Groundhog Excavating Inc. $21.16 $129,308.76 Meridian Contracting, Inc. $22.00 $134,442.00 Engineer's Estimate 6,111 LNFT $25.00 $152,775.00
Total Schedule - All Items
Construction Solutions Group, LLC $1,491,031.04 LaForge and Budd Construction Company, Inc. $2,121,158.75 GC Works, Inc. $2,192,517.30 R & M Government Services, Inc. $2,302,054.07 Southwest General Construction, Inc. $2,422,500.95 Groundhog Excavating Inc. $2,658,079.16 Meridian Contracting, Inc. $3,022,696.00 Engineer's Estimate $1,949,000.00
| 2020-12-22T12:11:42-0700 | |