QnA_8.28.2019.pdf

PDF 90 KB Posted

Attached to
CA ERFO ANGELES NF 3N17(2) Santa Clara Divide Road
Solicitation number
6982AF19B000012
Issued by

View the file

Other files

File Type Posted
Bid_Tabulation_-__Santa_Clara.pdf PDF
Bid_Opening_Summary_CA_ERFO_ANGELES_NF_3N17(2)_Santa_Clara_Divide_Road.pdf PDF
QnA_09.09.2019.pdf PDF
QnA_09.04.2019.pdf PDF
Amendment_A001.pdf PDF
FINAL_Geotechnical_Memorandum_CA_ERFO_3N17(2).pdf PDF
fp14.pdf PDF
CA_ERFO_3N17(2)_Plans.pdf PDF
6982AF19B000012.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for

CA ERFO ANGELES NF 3N17(2) SANTA CLARA DIVIDE

August 28, 2019

Questions Answers 1 Per section 108.1 it states contract completion date is 12/17/19.

With 60 days for the FHWA to accept proposals and issue a contact that leaves 30 days to perform the project including administrative submittals and onsite work. How many days do we have from issue of Notice to Proceed to complete the contract?

Please refer to Amendment A001 posted on FBO on 08/29/19.

FAR Clause 52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)-

The completion date is based on the assumption that the successful offeror will receive the notice to proceed by October 3, 2019. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

2 I noticed there is no organized site walk scheduled. What steps need to be taken in order to schedule a time for my team to view the site? Is this something we will have open access to? Will there be someone onsite to guide through the site?

The project site is open to the public. The contractor is encouraged to view the site prior to preparing their bid. No organized site visit will be held, and no one will be onsite to guide the contractor through the site.

3 It has come to my attention that the bid bond form provided in the 6982AF19B000012 RFP package is expired. Does the FHWA have an updated form or do you want us to use the provided form?

Please refer to Amendment A001 posted on FBO on 08/29/19 for updated bid bond forms.

File details come from the government source that posted it.