Bid_Tabulation_WY_FLAP_6WX(1).pdf

PDF 604 KB Posted

Attached to
WY FLAP 6WX(1), Southfork Road Federal contract opportunity
Solicitation number
6982AF19B000004
Issued by
Department of Transportation Federal Highway Administration

View the file

Other files for this federal contract opportunity

Other files attached to WY FLAP 6WX(1), Southfork Road, newest first.
File Type Posted
Disregard_the_posting_titled_QnA_4.22.19.docx DOCX document
QnA_4.22.19.pdf PDF
QnA_4.22.19_4_WY.PFH.4.Beartooth_Highway.URS_Geotech.1999c.PDF PDF
Southfork_Bid_Summary.pdf PDF
Bid_Opening_Sign_In_Sheet.pdf PDF
Bidder_Q_A_WY6WX(1)_Southfork_3.26.2019.pdf PDF
Bidder_Q_A_WY6WX(1)_Southfork_3.25.2019.pdf PDF
Bidder_Q_A_WY6WX(1)_Southfork_3.24.2019.pdf PDF
A002_WY_6WX(1).pdf PDF
Bidder_Q_A_WY6WX(1)_Southfork_3.20.2019.pdf PDF
A001_WY_6WX(1).pdf PDF
Southfork_Final_Geotechnical_Report.pdf PDF
100_X-sheets.pdf PDF
6982AF19B000004.pdf PDF
100_-Plan-sheets.pdf PDF
WY_FLSP_6WX(1)_Pavement_Memo.pdf PDF
FP-14.pdf PDF
Hyd_6WX(1)_Final.pdf PDF
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tabulation of Bids Report Date: 04/03/19

1 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Contractor Responsive?

Engineer's Estimate

FirstMark Construction, LLC

Mountain Construction Company

Base Schedule A

$8,983,100.00

$12,126,000.00

$11,768,344.88

Option: X

$907,350.00

$1,357,000.00

$1,189,385.63

Option: Y

$300,000.00

$426,000.00

$514,895.10

Contractor Responsive?

Engineer's Estimate

FirstMark Construction, LLC

Mountain Construction Company

Total Base Schedule A and Option(s): X

$9,890,450.00

$13,483,000.00

$12,957,730.51

Total Base Schedule A and Option(s): XY

$10,190,450.00

$13,909,000.00

$13,472,625.61

Total Base Schedule A and Option(s): Y

$9,283,100.00

$12,552,000.00

$12,283,239.98

2 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: A

Schedule Type: Base

Solcitation No: 6982AF19B000004

Division: Central Federal Lands

State: WY County: Park

Federal Land: Shoshone National Forest Opened at: Lakewood, CO

Opened by: Sheri Walsh

Date: 03/29/19

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Mountain Construction Company $11,768,344.88 25 West 10th Lovell, WY 82431

FirstMark Construction, LLC $12,126,000.00 6611 Trade Center Ave Billings, MT 59101

Engineer's Estimate $8,983,100.00

3 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0020 15101-0000 MOBILIZATION

Mountain Construction Company Lump Sum $2,059,817.28 FirstMark Construction, LLC Lump Sum $1,056,693.00 Engineer's Estimate ALL LPSM Lump Sum $745,975.00

A0040 15201-0000 CONSTRUCTION SURVEY AND STAKING

Mountain Construction Company Lump Sum $130,000.00 FirstMark Construction, LLC Lump Sum $130,000.00 Engineer's Estimate ALL LPSM Lump Sum $180,000.00

A0060 15214-1000 SURVEY AND STAKING, BRIDGE

Mountain Construction Company Lump Sum $15,000.00 FirstMark Construction, LLC Lump Sum $15,000.00 Engineer's Estimate ALL LPSM Lump Sum $8,000.00

A0080 15301-0000 CONTRACTOR QUALITY CONTROL

Mountain Construction Company Lump Sum $260,935.00 FirstMark Construction, LLC Lump Sum $318,950.00 Engineer's Estimate ALL LPSM Lump Sum $250,000.00

A0100 15401-0000 CONTRACTOR TESTING

Mountain Construction Company Lump Sum $9,000.00 FirstMark Construction, LLC Lump Sum $210,000.00 Engineer's Estimate ALL LPSM Lump Sum $250,000.00

A0120 15501-0000 CONSTRUCTION SCHEDULE

Mountain Construction Company Lump Sum $18,500.00 FirstMark Construction, LLC Lump Sum $35,000.00 Engineer's Estimate ALL LPSM Lump Sum $25,000.00

A0140 15701-0000 SOIL EROSION CONTROL (EROSION CONTROL)

Mountain Construction Company Lump Sum $37,000.00 FirstMark Construction, LLC Lump Sum $70,000.00 Engineer's Estimate ALL LPSM Lump Sum $50,000.00

4 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0160 15701-0000 SOIL EROSION CONTROL (SEDIMENT CONTROL)

Mountain Construction Company Lump Sum $102,500.00 FirstMark Construction, LLC Lump Sum $250,000.00 Engineer's Estimate ALL LPSM Lump Sum $65,000.00

A0180 15701-0000 SOIL EROSION CONTROL (NON-STORM WATER CONTROL)

Mountain Construction Company Lump Sum $12,500.00 FirstMark Construction, LLC Lump Sum $60,000.00 Engineer's Estimate ALL LPSM Lump Sum $40,000.00

A0200 15720-0000 STORM WATER POLLUTION PREVENTION PLAN

Mountain Construction Company Lump Sum $42,500.00 FirstMark Construction, LLC Lump Sum $28,990.00 Engineer's Estimate ALL LPSM Lump Sum $25,000.00

A0220 15802-0000 WATERING FOR DUST CONTROL

Mountain Construction Company Lump Sum $164,000.00 FirstMark Construction, LLC Lump Sum $170,000.00 Engineer's Estimate ALL LPSM Lump Sum $50,000.00

A0240 20101-0000 CLEARING AND GRUBBING

Mountain Construction Company $2,475.00 $148,500.00 FirstMark Construction, LLC $8,000.00 $480,000.00 Engineer's Estimate 60.0 ACRE $1,000.00 $60,000.00

A0260 20301-0600 REMOVAL OF CATTLE GUARD

Mountain Construction Company $2,000.00 $2,000.00 FirstMark Construction, LLC $1,200.00 $1,200.00 Engineer's Estimate 1 EACH $3,000.00 $3,000.00

A0280 20301-2400 REMOVAL OF SIGN

Mountain Construction Company $100.00 $1,500.00 FirstMark Construction, LLC $120.00 $1,800.00 Engineer's Estimate 15 EACH $100.00 $1,500.00

5 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0300 20302-0700 REMOVAL OF FENCE

Mountain Construction Company $0.47 $2,209.00 FirstMark Construction, LLC $2.50 $11,750.00 Engineer's Estimate 4,700 LNFT $5.00 $23,500.00

A0320 20302-1200 REMOVAL OF GUARDRAIL

Mountain Construction Company $3.00 $540.00 FirstMark Construction, LLC $11.00 $1,980.00 Engineer's Estimate 180 LNFT $6.00 $1,080.00

A0340 20304-2000 REMOVAL OF BRIDGE (PARTIAL SUBSTRUCTURE)

Mountain Construction Company Lump Sum $180,000.00 FirstMark Construction, LLC Lump Sum $115,000.00 Engineer's Estimate ALL LPSM Lump Sum $60,000.00

A0360 20304-4000 REMOVAL OF BRIDGE SUPERSTRUCTURE

Mountain Construction Company Lump Sum $90,000.00 FirstMark Construction, LLC Lump Sum $20,000.00 Engineer's Estimate ALL LPSM Lump Sum $125,000.00

A0380 20401-0000 ROADWAY EXCAVATION

Mountain Construction Company $20.74 $1,327,360.00 FirstMark Construction, LLC $30.00 $1,920,000.00 Engineer's Estimate 64,000 CUYD $11.00 $704,000.00

A0400 20403-0000 UNCLASSIFIED BORROW

Mountain Construction Company $20.68 $217,140.00 FirstMark Construction, LLC $20.00 $210,000.00 Engineer's Estimate 10,500 CUYD $3.00 $31,500.00

A0420 20425-1000 DITCH, EXCAVATION (STANDARD)

Mountain Construction Company $4.89 $42,543.00 FirstMark Construction, LLC $8.00 $69,600.00 Engineer's Estimate 8,700 LNFT $10.00 $87,000.00

6 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0440 20425-1000 DITCH, EXCAVATION (OVERSIZED)

Mountain Construction Company $9.17 $27,510.00 FirstMark Construction, LLC $11.00 $33,000.00 Engineer's Estimate 3,000 LNFT $13.00 $39,000.00

A0460 20801-0000 STRUCTURE EXCAVATION

Mountain Construction Company $243.98 $68,314.40 FirstMark Construction, LLC $100.00 $28,000.00 Engineer's Estimate 280 CUYD $100.00 $28,000.00

A0480 25101-0200 PLACED RIPRAP, METHOD A, CLASS 2

Mountain Construction Company $172.48 $24,147.20 FirstMark Construction, LLC $90.00 $12,600.00 Engineer's Estimate 140 CUYD $100.00 $14,000.00

A0500 25101-0300 PLACED RIPRAP, METHOD A, CLASS 3

Mountain Construction Company $170.83 $25,624.50 FirstMark Construction, LLC $105.00 $15,750.00 Engineer's Estimate 150 CUYD $100.00 $15,000.00

A0520 25101-2400 PLACED RIPRAP, METHOD B, CLASS 4

Mountain Construction Company $160.72 $72,324.00 FirstMark Construction, LLC $110.00 $49,500.00 Engineer's Estimate 450 CUYD $120.00 $54,000.00

A0540 25101-2600 PLACED RIPRAP, METHOD B, CLASS 6

Mountain Construction Company $121.72 $255,612.00 FirstMark Construction, LLC $115.00 $241,500.00 Engineer's Estimate 2,100 CUYD $175.00 $367,500.00

A0560 30112-0000 AGGREGATE SURFACE COURSE

Mountain Construction Company $46.37 $834,660.00 FirstMark Construction, LLC $71.00 $1,278,000.00 Engineer's Estimate 18,000 CUYD $50.00 $900,000.00

7 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0600 30203-2000 ROADWAY AGGREGATE, METHOD 2

Mountain Construction Company $7.05 $775,500.00 FirstMark Construction, LLC $5.40 $594,000.00 Engineer's Estimate 110,000 SQYD $7.00 $770,000.00

A0620 31213-0000 MAGNESIUM CHLORIDE

Mountain Construction Company $138.00 $38,640.00 FirstMark Construction, LLC $400.00 $112,000.00 Engineer's Estimate 280 TON $175.00 $49,000.00

A0660 40101-5600 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH OR 3/4-INCH NOMINAL MAXIMUM SIZE

AGGREGATE, 0.3 TO <3 MILLION ESAL

Mountain Construction Company $85.56 $1,540,080.00 FirstMark Construction, LLC $98.00 $1,764,000.00 Engineer's Estimate 18,000 TON $85.00 $1,530,000.00

A0680 40105-3000 ANTISTRIP ADDITIVE, TYPE 3

Mountain Construction Company $250.00 $45,000.00 FirstMark Construction, LLC $170.00 $30,600.00 Engineer's Estimate 180 TON $320.00 $57,600.00

A0720 40602-0000 FOG SEAL

Mountain Construction Company $0.55 $60,500.00 FirstMark Construction, LLC $0.50 $55,000.00 Engineer's Estimate 110,000 SQYD $0.35 $38,500.00

A0740 41102-1000 PRIME COAT, METHOD 1

Mountain Construction Company $1.70 $187,000.00 FirstMark Construction, LLC $1.40 $154,000.00 Engineer's Estimate 110,000 SQYD $1.50 $165,000.00

A0760 41201-0000 TACK COAT

Mountain Construction Company $803.96 $56,277.20 FirstMark Construction, LLC $650.00 $45,500.00 Engineer's Estimate 70 TON $800.00 $56,000.00

8 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0780 55101-2000 STEEL H-PILE, 14 X 102, IN PLACE

Mountain Construction Company $205.00 $102,500.00 FirstMark Construction, LLC $90.00 $45,000.00 Engineer's Estimate 500 LNFT $135.00 $67,500.00

A0800 55104-1000 DYNAMIC PILE LOAD TEST

Mountain Construction Company $15,000.00 $30,000.00 FirstMark Construction, LLC $6,000.00 $12,000.00 Engineer's Estimate 2 EACH $5,000.00 $10,000.00

A0820 55115-1000 PREBORING

Mountain Construction Company $999.00 $44,955.00 FirstMark Construction, LLC $100.00 $4,500.00 Engineer's Estimate 45 LNFT $50.00 $2,250.00

A0840 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)

Mountain Construction Company $1,500.00 $271,500.00 FirstMark Construction, LLC $2,350.00 $425,350.00 Engineer's Estimate 181 CUYD $1,200.00 $217,200.00

A0860 55401-1000 REINFORCING STEEL

Mountain Construction Company $3.00 $14,100.00 FirstMark Construction, LLC $3.00 $14,100.00 Engineer's Estimate 4,700 LB $1.75 $8,225.00

A0880 55401-2000 REINFORCING STEEL, EPOXY COATED

Mountain Construction Company $3.25 $139,425.00 FirstMark Construction, LLC $2.50 $107,250.00 Engineer's Estimate 42,900 LB $2.00 $85,800.00

A0900 55502-0000 STRUCTURAL STEEL, FURNISHED, FABRICATED, AND ERECTED

Mountain Construction Company $5.00 $897,000.00 FirstMark Construction, LLC $2.80 $502,320.00 Engineer's Estimate 179,400 LB $4.00 $717,600.00

9 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0920 55601-0900 BRIDGE RAILING, STEEL (WY DOT)

Mountain Construction Company $275.00 $94,050.00 FirstMark Construction, LLC $260.00 $88,920.00 Engineer's Estimate 342 LNFT $150.00 $51,300.00

A0940 56401-1000 BEARING DEVICE, ELASTOMERIC

Mountain Construction Company $2,000.00 $16,000.00 FirstMark Construction, LLC $250.00 $2,000.00 Engineer's Estimate 8 EACH $1,200.00 $9,600.00

A0960 60101-0000 CONCRETE

Mountain Construction Company $2,000.00 $2,000.00 FirstMark Construction, LLC $1,500.00 $1,500.00 Engineer's Estimate 1 CUYD $2,500.00 $2,500.00

A0980 60201-0600 18-INCH PIPE CULVERT

Mountain Construction Company $51.00 $31,110.00 FirstMark Construction, LLC $70.00 $42,700.00 Engineer's Estimate 610 LNFT $105.00 $64,050.00

A1000 60201-0800 24-INCH PIPE CULVERT

Mountain Construction Company $63.00 $91,350.00 FirstMark Construction, LLC $80.00 $116,000.00 Engineer's Estimate 1,450 LNFT $130.00 $188,500.00

A1020 60201-0800 24-INCH PIPE CULVERT (RCP)

Mountain Construction Company $405.00 $2,430.00 FirstMark Construction, LLC $260.00 $1,560.00 Engineer's Estimate 6 LNFT $160.00 $960.00

A1040 60201-0900 30-INCH PIPE CULVERT

Mountain Construction Company $107.00 $2,140.00 FirstMark Construction, LLC $120.00 $2,400.00 Engineer's Estimate 20 LNFT $150.00 $3,000.00

10 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1060 60201-1000 36-INCH PIPE CULVERT

Mountain Construction Company $107.00 $32,100.00 FirstMark Construction, LLC $130.00 $39,000.00 Engineer's Estimate 300 LNFT $150.00 $45,000.00

A1080 60201-1200 48-INCH PIPE CULVERT

Mountain Construction Company $145.00 $1,740.00 FirstMark Construction, LLC $206.00 $2,472.00 Engineer's Estimate 12 LNFT $300.00 $3,600.00

A1100 60210-0600 END SECTION FOR 18-INCH PIPE CULVERT

Mountain Construction Company $172.00 $6,020.00 FirstMark Construction, LLC $300.00 $10,500.00 Engineer's Estimate 35 EACH $360.00 $12,600.00

A1120 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT

Mountain Construction Company $250.00 $15,000.00 FirstMark Construction, LLC $350.00 $21,000.00 Engineer's Estimate 60 EACH $400.00 $24,000.00

A1140 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT (RCP)

Mountain Construction Company $1,500.00 $1,500.00 FirstMark Construction, LLC $375.00 $375.00 Engineer's Estimate 1 EACH $1,500.00 $1,500.00

A1160 60210-0900 END SECTION FOR 30-INCH PIPE CULVERT

Mountain Construction Company $450.00 $2,700.00 FirstMark Construction, LLC $500.00 $3,000.00 Engineer's Estimate 6 EACH $600.00 $3,600.00

A1180 60210-1000 END SECTION FOR 36-INCH PIPE CULVERT

Mountain Construction Company $575.00 $6,900.00 FirstMark Construction, LLC $725.00 $8,700.00 Engineer's Estimate 12 EACH $800.00 $9,600.00

11 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1200 60210-1200 END SECTION FOR 48-INCH PIPE CULVERT

Mountain Construction Company $1,350.00 $1,350.00 FirstMark Construction, LLC $1,500.00 $1,500.00 Engineer's Estimate 1 EACH $2,000.00 $2,000.00

A1220 60703-0000 CLEANING CULVERTS IN PLACE

Mountain Construction Company $20.00 $6,200.00 FirstMark Construction, LLC $22.00 $6,820.00 Engineer's Estimate 310 LNFT $25.00 $7,750.00

A1240 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS

Mountain Construction Company $45.00 $4,500.00 FirstMark Construction, LLC $45.00 $4,500.00 Engineer's Estimate 100 LNFT $100.00 $10,000.00

A1260 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT

Mountain Construction Company $4,700.00 $14,100.00 FirstMark Construction, LLC $4,700.00 $14,100.00 Engineer's Estimate 3 EACH $3,600.00 $10,800.00

A1280 61702-1600 TERMINAL SECTION, TYPE MGS FLARED

Mountain Construction Company $4,800.00 $4,800.00 FirstMark Construction, LLC $4,800.00 $4,800.00 Engineer's Estimate 1 EACH $3,600.00 $3,600.00

A1300 61707-0000 STRUCTURE TRANSITION RAILING

Mountain Construction Company $150.00 $15,000.00 FirstMark Construction, LLC $150.00 $15,000.00 Engineer's Estimate 100 LNFT $125.00 $12,500.00

A1320 61901-0900 FENCE, BARBED WIRE, 4 STRAND

Mountain Construction Company $3.45 $8,625.00 FirstMark Construction, LLC $4.00 $10,000.00 Engineer's Estimate 2,500 LNFT $5.00 $12,500.00

12 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1340 61903-1100 CATTLE GUARD, 32 FEET

Mountain Construction Company $27,214.80 $27,214.80 FirstMark Construction, LLC $20,000.00 $20,000.00 Engineer's Estimate 1 EACH $25,000.00 $25,000.00

A1360 61920-2000 REMOVE AND RESET GATE

Mountain Construction Company $105.00 $105.00 FirstMark Construction, LLC $100.00 $100.00 Engineer's Estimate 1 EACH $4,000.00 $4,000.00

A1380 61921-1000 REMOVE AND RESET FENCE

Mountain Construction Company $8.55 $1,966.50 FirstMark Construction, LLC $5.00 $1,150.00 Engineer's Estimate 230 LNFT $12.00 $2,760.00

A1400 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY

Mountain Construction Company $150.00 $6,000.00 FirstMark Construction, LLC $194.00 $7,760.00 Engineer's Estimate 40 HOUR $125.00 $5,000.00

A1420 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY

Mountain Construction Company $185.00 $7,400.00 FirstMark Construction, LLC $202.00 $8,080.00 Engineer's Estimate 40 HOUR $140.00 $5,600.00

A1440 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE

Mountain Construction Company $200.00 $8,000.00 FirstMark Construction, LLC $208.00 $8,320.00 Engineer's Estimate 40 HOUR $170.00 $6,800.00

A1460 62201-3300 HYDRAULIC EXCAVATOR, 3/4 CUBIC YARD MINIMUM CAPACITY

Mountain Construction Company $185.00 $7,400.00 FirstMark Construction, LLC $225.00 $9,000.00 Engineer's Estimate 40 HOUR $135.00 $5,400.00

13 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1480 62301-0000 GENERAL LABOR

Mountain Construction Company $65.00 $2,600.00 FirstMark Construction, LLC $75.00 $3,000.00 Engineer's Estimate 40 HOUR $40.00 $1,600.00

A1500 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES

Mountain Construction Company $150.00 $3,000.00 FirstMark Construction, LLC $130.00 $2,600.00 Engineer's Estimate 20 HOUR $150.00 $3,000.00

A1520 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES

Mountain Construction Company $150.00 $3,000.00 FirstMark Construction, LLC $150.00 $3,000.00 Engineer's Estimate 20 HOUR $200.00 $4,000.00

A1540 62406-0300 PLACING CONSERVED TOPSOIL, 4-INCH DEPTH

Mountain Construction Company $4,335.00 $130,050.00 FirstMark Construction, LLC $4,000.00 $120,000.00 Engineer's Estimate 30.0 ACRE $1,400.00 $42,000.00

A1560 62510-2000 SEEDING, HYDRAULIC METHOD (UPLAND)

Mountain Construction Company $675.00 $18,900.00 FirstMark Construction, LLC $570.00 $15,960.00 Engineer's Estimate 28.0 ACRE $1,000.00 $28,000.00

A1580 62510-2000 SEEDING, HYDRAULIC METHOD (WETLAND)

Mountain Construction Company $1,850.00 $3,700.00 FirstMark Construction, LLC $1,855.00 $3,710.00 Engineer's Estimate 2.0 ACRE $1,000.00 $2,000.00

A1600 62515-2000 MULCHING, HYDRAULIC METHOD

Mountain Construction Company $1,100.00 $33,000.00 FirstMark Construction, LLC $1,200.00 $36,000.00 Engineer's Estimate 30.0 ACRE $1,000.00 $30,000.00

14 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1620 62520-0000 FERTILIZER

Mountain Construction Company $975.00 $29,250.00 FirstMark Construction, LLC $1,250.00 $37,500.00 Engineer's Estimate 30.0 ACRE $1,000.00 $30,000.00

A1640 63301-0000 SIGN SYSTEM

Mountain Construction Company $1,100.00 $13,200.00 FirstMark Construction, LLC $1,100.00 $13,200.00 Engineer's Estimate 12 EACH $400.00 $4,800.00

A1660 63316-1000 REMOVE AND RESET SIGN

Mountain Construction Company $450.00 $15,750.00 FirstMark Construction, LLC $450.00 $15,750.00 Engineer's Estimate 35 EACH $200.00 $7,000.00

A1680 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID

Mountain Construction Company $0.20 $37,000.00 FirstMark Construction, LLC $0.20 $37,000.00 Engineer's Estimate 185,000 LNFT $0.25 $46,250.00

A1700 63401-0400 PAVEMENT MARKINGS, TYPE B, BROKEN

Mountain Construction Company $0.15 $7,800.00 FirstMark Construction, LLC $0.15 $7,800.00 Engineer's Estimate 52,000 LNFT $0.20 $10,400.00

A1720 63501-0000 TEMPORARY TRAFFIC CONTROL

Mountain Construction Company Lump Sum $657,000.00 FirstMark Construction, LLC Lump Sum $657,000.00 Engineer's Estimate ALL LPSM Lump Sum $250,000.00

A1740 63610-2200 CONDUIT, 3-INCH, PVC

Mountain Construction Company $20.00 $7,000.00 FirstMark Construction, LLC $24.00 $8,400.00 Engineer's Estimate 350 LNFT $10.00 $3,500.00

15 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1760 63610-3200 CONDUIT, 6-INCH, PVC

Mountain Construction Company $24.00 $7,680.00 FirstMark Construction, LLC $27.00 $8,640.00 Engineer's Estimate 320 LNFT $15.00 $4,800.00

A1780 64620-0400 REMOVE AND RESET MAILBOX

Mountain Construction Company $500.00 $7,500.00 FirstMark Construction, LLC $350.00 $5,250.00 Engineer's Estimate 15 EACH $300.00 $4,500.00

Total Schedule - All Items

Mountain Construction Company $11,768,344.88 FirstMark Construction, LLC $12,126,000.00 Engineer's Estimate $8,983,100.00

16 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: X

Schedule Type: Options

Solcitation No: 6982AF19B000004

Division: Central Federal Lands

State: WY County: Park

Federal Land: Shoshone National Forest Opened at: Lakewood, CO

Opened by: Sheri Walsh

Date: 03/29/19

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Mountain Construction Company $1,189,385.63 25 West 10th Lovell, WY 82431

FirstMark Construction, LLC $1,357,000.00 6611 Trade Center Ave Billings, MT 59101

Engineer's Estimate $907,350.00

17 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: X

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

X0020 15101-0000 MOBILIZATION

Mountain Construction Company Lump Sum $108,082.83 FirstMark Construction, LLC Lump Sum $71,314.00 Engineer's Estimate ALL LPSM Lump Sum $38,525.00

X0040 15201-0000 CONSTRUCTION SURVEY AND STAKING

Mountain Construction Company Lump Sum $15,000.00 FirstMark Construction, LLC Lump Sum $15,000.00 Engineer's Estimate ALL LPSM Lump Sum $25,000.00

X0060 15301-0000 CONTRACTOR QUALITY CONTROL

Mountain Construction Company Lump Sum $55,000.00 FirstMark Construction, LLC Lump Sum $27,100.00 Engineer's Estimate ALL LPSM Lump Sum $25,000.00

X0080 15401-0000 CONTRACTOR TESTING

Mountain Construction Company Lump Sum $9,500.00 FirstMark Construction, LLC Lump Sum $25,400.00 Engineer's Estimate ALL LPSM Lump Sum $25,000.00

X0100 15501-0000 CONSTRUCTION SCHEDULE

Mountain Construction Company Lump Sum $5,000.00 FirstMark Construction, LLC Lump Sum $10,000.00 Engineer's Estimate ALL LPSM Lump Sum $2,500.00

X0120 15701-0000 SOIL EROSION CONTROL (EROSION CONTROL)

Mountain Construction Company Lump Sum $7,500.00 FirstMark Construction, LLC Lump Sum $75,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00

X0140 15701-0000 SOIL EROSION CONTROL (SEDIMENT CONTROL)

Mountain Construction Company Lump Sum $10,000.00 FirstMark Construction, LLC Lump Sum $21,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00

18 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: X

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

X0160 15701-0000 SOIL EROSION CONTROL (NON-STORM WATER CONTROL)

Mountain Construction Company Lump Sum $7,500.00 FirstMark Construction, LLC Lump Sum $9,000.00 Engineer's Estimate ALL LPSM Lump Sum $5,000.00

X0180 15720-0000 STORM WATER POLLUTION PREVENTION PLAN

Mountain Construction Company Lump Sum $7,500.00 FirstMark Construction, LLC Lump Sum $5,000.00 Engineer's Estimate ALL LPSM Lump Sum $2,500.00

X0200 15802-0000 WATERING FOR DUST CONTROL

Mountain Construction Company Lump Sum $36,000.00 FirstMark Construction, LLC Lump Sum $13,000.00 Engineer's Estimate ALL LPSM Lump Sum $4,000.00

X0220 20101-0000 CLEARING AND GRUBBING

Mountain Construction Company $3,100.00 $37,200.00 FirstMark Construction, LLC $4,000.00 $48,000.00 Engineer's Estimate 12.0 ACRE $1,000.00 $12,000.00

X0240 20301-0600 REMOVAL OF CATTLE GUARD

Mountain Construction Company $2,000.00 $2,000.00 FirstMark Construction, LLC $1,400.00 $1,400.00 Engineer's Estimate 1 EACH $3,000.00 $3,000.00

X0260 20301-2400 REMOVAL OF SIGN

Mountain Construction Company $100.00 $700.00 FirstMark Construction, LLC $140.00 $980.00 Engineer's Estimate 7 EACH $100.00 $700.00

X0280 20302-0700 REMOVAL OF FENCE

Mountain Construction Company $0.47 $188.00 FirstMark Construction, LLC $3.50 $1,400.00 Engineer's Estimate 400 LNFT $5.00 $2,000.00

19 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: X

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

X0300 20401-0000 ROADWAY EXCAVATION

Mountain Construction Company $20.74 $186,660.00 FirstMark Construction, LLC $30.00 $270,000.00 Engineer's Estimate 9,000 CUYD $11.00 $99,000.00

X0320 20441-0000 WASTE

Mountain Construction Company $20.00 $8,000.00 FirstMark Construction, LLC $71.58 $28,632.00 Engineer's Estimate 400 CUYD $5.00 $2,000.00

X0340 25101-0200 PLACED RIPRAP, METHOD A, CLASS 2

Mountain Construction Company $172.48 $3,449.60 FirstMark Construction, LLC $93.00 $1,860.00 Engineer's Estimate 20 CUYD $100.00 $2,000.00

X0360 30203-2000 ROADWAY AGGREGATE, METHOD 2

Mountain Construction Company $7.05 $148,050.00 FirstMark Construction, LLC $6.00 $126,000.00 Engineer's Estimate 21,000 SQYD $7.00 $147,000.00

X0380 40101-5600 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH OR 3/4-INCH NOMINAL MAXIMUM SIZE

AGGREGATE, 0.3 TO <3 MILLION ESAL

Mountain Construction Company $84.52 $295,820.00 FirstMark Construction, LLC $98.00 $343,000.00 Engineer's Estimate 3,500 TON $85.00 $297,500.00

X0420 40105-3000 ANTISTRIP ADDITIVE, TYPE 3

Mountain Construction Company $250.00 $8,750.00 FirstMark Construction, LLC $170.00 $5,950.00 Engineer's Estimate 35 TON $320.00 $11,200.00

X0460 40602-0000 FOG SEAL

Mountain Construction Company $0.55 $11,000.00 FirstMark Construction, LLC $0.50 $10,000.00 Engineer's Estimate 20,000 SQYD $0.35 $7,000.00

20 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: X

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

X0480 41102-1000 PRIME COAT, METHOD 1

Mountain Construction Company $1.70 $34,000.00 FirstMark Construction, LLC $1.40 $28,000.00 Engineer's Estimate 20,000 SQYD $1.50 $30,000.00

X0500 41201-0000 TACK COAT

Mountain Construction Company $803.96 $12,059.40 FirstMark Construction, LLC $650.00 $9,750.00 Engineer's Estimate 15 TON $800.00 $12,000.00

X0520 60201-0800 24-INCH PIPE CULVERT

Mountain Construction Company $63.00 $16,065.00 FirstMark Construction, LLC $90.00 $22,950.00 Engineer's Estimate 255 LNFT $130.00 $33,150.00

X0540 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT

Mountain Construction Company $250.00 $2,500.00 FirstMark Construction, LLC $410.00 $4,100.00 Engineer's Estimate 10 EACH $400.00 $4,000.00

X0560 61901-0900 FENCE, BARBED WIRE, 4 STRAND

Mountain Construction Company $2.80 $1,106.00 FirstMark Construction, LLC $4.00 $1,580.00 Engineer's Estimate 395 LNFT $5.00 $1,975.00

X0580 61903-1100 CATTLE GUARD, 32 FEET

Mountain Construction Company $27,214.80 $27,214.80 FirstMark Construction, LLC $22,000.00 $22,000.00 Engineer's Estimate 1 EACH $25,000.00 $25,000.00

X0600 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY

Mountain Construction Company $150.00 $3,000.00 FirstMark Construction, LLC $194.00 $3,880.00 Engineer's Estimate 20 HOUR $125.00 $2,500.00

21 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: X

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

X0620 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY

Mountain Construction Company $185.00 $3,700.00 FirstMark Construction, LLC $202.00 $4,040.00 Engineer's Estimate 20 HOUR $140.00 $2,800.00

X0640 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE

Mountain Construction Company $200.00 $4,000.00 FirstMark Construction, LLC $208.00 $4,160.00 Engineer's Estimate 20 HOUR $170.00 $3,400.00

X0660 62201-3300 HYDRAULIC EXCAVATOR, 3/4 CUBIC YARD MINIMUM CAPACITY

Mountain Construction Company $185.00 $3,700.00 FirstMark Construction, LLC $225.00 $4,500.00 Engineer's Estimate 20 HOUR $135.00 $2,700.00

X0680 62301-0000 GENERAL LABOR

Mountain Construction Company $65.00 $650.00 FirstMark Construction, LLC $75.00 $750.00 Engineer's Estimate 10 HOUR $40.00 $400.00

X0700 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES

Mountain Construction Company $150.00 $1,500.00 FirstMark Construction, LLC $300.00 $3,000.00 Engineer's Estimate 10 HOUR $150.00 $1,500.00

X0720 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES

Mountain Construction Company $150.00 $1,500.00 FirstMark Construction, LLC $150.00 $1,500.00 Engineer's Estimate 10 HOUR $200.00 $2,000.00

X0740 62406-0300 PLACING CONSERVED TOPSOIL, 4-INCH DEPTH

Mountain Construction Company $4,335.00 $17,340.00 FirstMark Construction, LLC $4,500.00 $18,000.00 Engineer's Estimate 4.0 ACRE $1,400.00 $5,600.00

22 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: X

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

X0760 62510-2000 SEEDING, HYDRAULIC METHOD

Mountain Construction Company $675.00 $2,700.00 FirstMark Construction, LLC $1,966.00 $7,864.00 Engineer's Estimate 4.0 ACRE $1,000.00 $4,000.00

X0780 62515-2000 MULCHING, HYDRAULIC METHOD

Mountain Construction Company $1,200.00 $4,800.00 FirstMark Construction, LLC $1,250.00 $5,000.00 Engineer's Estimate 4.0 ACRE $1,000.00 $4,000.00

X0800 62520-0000 FERTILIZER

Mountain Construction Company $975.00 $3,900.00 FirstMark Construction, LLC $1,285.00 $5,140.00 Engineer's Estimate 4.0 ACRE $1,000.00 $4,000.00

X0820 63301-0000 SIGN SYSTEM

Mountain Construction Company $1,100.00 $1,100.00 FirstMark Construction, LLC $1,100.00 $1,100.00 Engineer's Estimate 1 EACH $400.00 $400.00

X0840 63316-1000 REMOVE AND RESET SIGN

Mountain Construction Company $450.00 $1,800.00 FirstMark Construction, LLC $450.00 $1,800.00 Engineer's Estimate 4 EACH $200.00 $800.00

X0860 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID

Mountain Construction Company $0.20 $7,200.00 FirstMark Construction, LLC $0.20 $7,200.00 Engineer's Estimate 36,000 LNFT $0.25 $9,000.00

X0880 63401-0400 PAVEMENT MARKINGS, TYPE B, BROKEN

Mountain Construction Company $0.15 $1,650.00 FirstMark Construction, LLC $0.15 $1,650.00 Engineer's Estimate 11,000 LNFT $0.20 $2,200.00

23 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: X

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

X0900 63501-0000 TEMPORARY TRAFFIC CONTROL

Mountain Construction Company Lump Sum $75,000.00 FirstMark Construction, LLC Lump Sum $90,000.00 Engineer's Estimate ALL LPSM Lump Sum $25,000.00

Total Schedule - All Items

Mountain Construction Company $1,189,385.63 FirstMark Construction, LLC $1,357,000.00 Engineer's Estimate $907,350.00

24 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: Y

Schedule Type: Options

Solcitation No: 6982AF19B000004

Division: Central Federal Lands

State: WY County: Park

Federal Land: Shoshone National Forest Opened at: Lakewood, CO

Opened by: Sheri Walsh

Date: 03/29/19

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

FirstMark Construction, LLC $426,000.00 6611 Trade Center Ave Billings, MT 59101

Mountain Construction Company $514,895.10 25 West 10th Lovell, WY 82431

Engineer's Estimate $300,000.00

25 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y0020 15101-0000 MOBILIZATION

FirstMark Construction, LLC Lump Sum $40,000.00 Mountain Construction Company Lump Sum $113,320.30 Engineer's Estimate ALL LPSM Lump Sum $30,810.00

Y0040 15214-1000 SURVEY AND STAKING, BRIDGE

FirstMark Construction, LLC Lump Sum $10,000.00 Mountain Construction Company Lump Sum $10,000.00 Engineer's Estimate ALL LPSM Lump Sum $3,000.00

Y0060 15301-0000 CONTRACTOR QUALITY CONTROL

FirstMark Construction, LLC Lump Sum $34,825.00 Mountain Construction Company Lump Sum $32,000.00 Engineer's Estimate ALL LPSM Lump Sum $2,500.00

Y0080 15401-0000 CONTRACTOR TESTING

FirstMark Construction, LLC Lump Sum $5,000.00 Mountain Construction Company Lump Sum $9,500.00 Engineer's Estimate ALL LPSM Lump Sum $3,500.00

Y0100 15501-0000 CONSTRUCTION SCHEDULE

FirstMark Construction, LLC Lump Sum $5,000.00 Mountain Construction Company Lump Sum $1,500.00 Engineer's Estimate ALL LPSM Lump Sum $1,500.00

Y0120 15701-0000 SOIL EROSION CONTROL (EROSTION CONTROL)

FirstMark Construction, LLC Lump Sum $60,000.00 Mountain Construction Company Lump Sum $5,500.00 Engineer's Estimate ALL LPSM Lump Sum $2,000.00

Y0140 15701-0000 SOIL EROSION CONTROL (SEDIMENT CONTROL)

FirstMark Construction, LLC Lump Sum $10,000.00 Mountain Construction Company Lump Sum $7,500.00 Engineer's Estimate ALL LPSM Lump Sum $3,000.00

26 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y0160 15701-0000 SOIL EROSION CONTROL (NON-STORM WATER CONTROL)

FirstMark Construction, LLC Lump Sum $6,000.00 Mountain Construction Company Lump Sum $5,000.00 Engineer's Estimate ALL LPSM Lump Sum $3,000.00

Y0180 20304-2000 REMOVAL OF BRIDGE

FirstMark Construction, LLC Lump Sum $39,985.00 Mountain Construction Company Lump Sum $40,000.00 Engineer's Estimate ALL LPSM Lump Sum $25,000.00

Y0200 20801-0000 STRUCTURE EXCAVATION

FirstMark Construction, LLC $70.00 $16,800.00 Mountain Construction Company $243.98 $58,555.20 Engineer's Estimate 240 CUYD $50.00 $12,000.00

Y0220 20803-0000 STRUCTURAL BACKFILL

FirstMark Construction, LLC $85.00 $9,350.00 Mountain Construction Company $78.00 $8,580.00 Engineer's Estimate 110 CUYD $75.00 $8,250.00

Y0240 30112-0000 AGGREGATE SURFACE COURSE

FirstMark Construction, LLC $100.00 $8,000.00 Mountain Construction Company $46.37 $3,709.60 Engineer's Estimate 80 CUYD $50.00 $4,000.00

Y0260 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)

FirstMark Construction, LLC $1,200.00 $49,200.00 Mountain Construction Company $1,200.00 $49,200.00 Engineer's Estimate 41 CUYD $1,200.00 $49,200.00

Y0280 55401-1000 REINFORCING STEEL

FirstMark Construction, LLC $1.00 $6,800.00 Mountain Construction Company $5.25 $35,700.00 Engineer's Estimate 6,800 LB $1.75 $11,900.00

27 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y0300 55504-0000 PRE-FABRICATED STEEL BRIDGE

FirstMark Construction, LLC Lump Sum $95,500.00 Mountain Construction Company Lump Sum $86,500.00 Engineer's Estimate ALL LPSM Lump Sum $100,000.00

Y0320 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY

FirstMark Construction, LLC $194.00 $1,940.00 Mountain Construction Company $100.00 $1,000.00 Engineer's Estimate 10 HOUR $125.00 $1,250.00

Y0340 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY

FirstMark Construction, LLC $202.00 $2,020.00 Mountain Construction Company $150.00 $1,500.00 Engineer's Estimate 10 HOUR $140.00 $1,400.00

Y0360 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE

FirstMark Construction, LLC $208.00 $2,080.00 Mountain Construction Company $200.00 $2,000.00 Engineer's Estimate 10 HOUR $170.00 $1,700.00

Y0380 62201-3300 HYDRAULIC EXCAVATOR, 3/4 CUBIC YARD MINIMUM CAPACITY

FirstMark Construction, LLC $225.00 $2,250.00 Mountain Construction Company $185.00 $1,850.00 Engineer's Estimate 10 HOUR $135.00 $1,350.00

Y0400 62301-0000 GENERAL LABOR

FirstMark Construction, LLC $75.00 $750.00 Mountain Construction Company $65.00 $650.00 Engineer's Estimate 10 HOUR $40.00 $400.00

Y0420 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES

FirstMark Construction, LLC $150.00 $1,500.00 Mountain Construction Company $150.00 $1,500.00 Engineer's Estimate 10 HOUR $200.00 $2,000.00

28 out of 28Source Selection Information - See FAR 2.101 & 3.104

Project No: WY FLAP 6WX(1)

Project Name: Southfork Road

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y0440 63301-0000 SIGN SYSTEM

FirstMark Construction, LLC $1,100.00 $2,200.00 Mountain Construction Company $1,500.00 $3,000.00 Engineer's Estimate 2 EACH $400.00 $800.00

Y0460 63308-3000 OBJECT MARKER, TYPE 3

FirstMark Construction, LLC $450.00 $1,800.00 Mountain Construction Company $900.00 $3,600.00 Engineer's Estimate 4 EACH $110.00 $440.00

Y0480 63501-0000 TEMPORARY TRAFFIC CONTROL

FirstMark Construction, LLC Lump Sum $5,000.00 Mountain Construction Company Lump Sum $5,000.00 Engineer's Estimate ALL LPSM Lump Sum $5,000.00

Y0500 65001-1000 CONSTRUCT AND MAINTAIN DIVERSION

FirstMark Construction, LLC Lump Sum $10,000.00 Mountain Construction Company Lump Sum $28,230.00 Engineer's Estimate ALL LPSM Lump Sum $26,000.00

Total Schedule - All Items

FirstMark Construction, LLC $426,000.00 Mountain Construction Company $514,895.10 Engineer's Estimate $300,000.00