Past Experience Form.pdf

PDF 84 KB Posted

Attached to
IIJA Funded - Fire Alarm Retrofit (PHL ATCT/TRACON)
Solicitation number
697DCK25R00058
Issued by

About this file

The Past Experience Form is a document for the FAA's solicitation 697DCK25R00058 for a Fire Alarm Retrofit project at the Philadelphia ATCT/TRACON facility. The form requires offerors to document three past projects, including details such as project name, location, client, scope, role (prime or subcontractor), percent completion (minimum 90%), contract amount (over $25,000), and point of contact information. This form is part of a small business set-aside procurement with an estimated construction magnitude between $50,000 and $100,000, to be awarded to the lowest-priced, responsible offeror. A mandatory site visit is scheduled for 4/2/25 at 10AM ET, and electronic offer submissions are required by the specified deadline, with all questions to be submitted in writing to the designated FAA contacts.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Past Experience Form

Please provide all the requested information below. Please note that the references/POCs included in this form may or may not be contacted to verify information at the FAA’s discretion.

Project #1

Name of Project: ________________________________________________

Location of Project: _____________________________________________

Owner/Organization/Customer/Client:____________________

General Scope of Project:

Summary of Your Role in this Project: Prime Subcontractor

Percent Complete (must be at least 90%) _______________________________

Final Contract Amount (must be over $25,000)___________________

Were You Terminated or Assessed Liquidated Damages? (if yes, explain) _________________________

Client/Customer Point of Contact Name:__________________________________

Client/Customer POC Phone Number:____________________________________

Client/Customer POC Phone Email:____________________________________

Project #2 Name of Project: ________________________________________________

Location of Project: _____________________________________________

Owner/Organization/Customer/Client:____________________

General Scope of Project:

1__________________________________________________________________________________

Summary of Your Role in this Project: Prime Subcontractor

Percent Complete (must be at least 90%) _______________________________

Final Contract Amount (must be over $25,000)___________________

Were You Terminated or Assessed Liquidated Damages? (if yes, explain) _________________________

Client/Customer Point of Contact Name:__________________________________

Project #3 Name of Project: ________________________________________________

Location of Project: _____________________________________________

Owner/Organization/Customer/Client:____________________

General Scope of Project:

Summary of Your Role in this Project: Prime Subcontractor

Percent Complete (must be at least 90%) _______________________________

Final Contract Amount (must be over $25,000)___________________

Were You Terminated or Assessed Liquidated Damages? (if yes, explain) _________________________

Client/Customer Point of Contact Name:__________________________________