Questions and Repsonses - Aug 24 2023.pdf

PDF 100 KB Posted

Attached to
Cab Shade IDIQ Contract Federal contract opportunity
Solicitation number
697DCK-23-R-00420
Issued by
Department of Transportation Federal Aviation Administration Southwestern Region

About this file

This document contains questions and responses regarding solicitation number 697DCK-23-R-00420 from the Department of Transportation Federal Aviation Administration Southwestern Region for a cab shade IDIQ contract. Offerors must provide an example of internal documentation demonstrating inspection of supplies such as shade material and rollers to ensure requirements are met. The responses clarify that a hard copy warranty is due once installation is complete, with an electronic copy to the Contracting Officer. An example checklist or form may satisfy the business proposal requirement to illustrate quality control processes.

View the file

Other files for this federal contract opportunity

Other files attached to Cab Shade IDIQ Contract, newest first.
File Type Posted
697DCK-23-R-00420_Final.pdf PDF
697DCK-23-R-00420_Final.pdf PDF
697DCK-23-R-00420_Final.pdf PDF
PAST PERFORMANCE QUESTIONNAIRE.pdf PDF
Attachment J-1 Statement of Work.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

697DCK-23-R-00420

QUESTIONS & RESPONSES

August 24, 2023

1. QUESTION: It mentions the following: “Provide one hard copy of the warranty to the COR and/or SSC and provide and electronic copy of the warranty to the CO.” How would you like this? Is there a mailing address? Or is this something to be provided at a later date? There will be an electronic copy included in the proposal, would you like a copy in a separate email as well?

1. RESPONSE: Per Attachment J-1 Statement of Work, a hard copy of the warranty is to be provided to the COR and/or SSC once the installation is complete and provide an electronic copy to the Contracting Officer. Furthermore, Quality Control and Risk Management under Factor 1 Management Approach requires Offerors to provide internal documentation (checklist and warranty) as an example with their proposal to be considered eligible for award.

2. QUESTION: In the business proposal, Volume II, section 3a., it states : “provide internal documentation to illustrate how supplies (shade material and rollers) are inspected to ensure they meet requirements in Attachment J-1…” We explain this process in the QC section, but does this require further explanation, or is a form/checklist more appropriate?

RESPONSE: In accordance with Quality Control and Risk Management under Factor 1 Management Approach Offerors must provide an example of internal documentation used to demonstrate the inspection of supplies that will be provided under the awarded contract. Please refer to clause 3.10.4-2 INSPECTION OF SUPPLIES - FIXED PRICE (NOV 1997) on page 6 of SIR, 697DCK-23-R-00420.