BKA Fuel Cargo Line SOW Revision 1.pdf
PDF 196 KB Posted
- Attached to
- Biorka Island AK - Fuel Cargo Line project Federal contract opportunity
- Solicitation number
- 697DCK-23-R-00143
About this file
This document package includes a Statement of Work (SOW) and related federal contract opportunity notice. The SOW outlines requirements for a design-build project to replace an existing fuel pipeline and electrical run on Biorka Island, Alaska. Key requirements include engineering and installing approximately 925 feet of 4-inch steel fuel pipeline and 480/277V electrical feeder in fiberglass conduit above ground. The contractor must demolish and dispose of the existing infrastructure. The notice seeks bids for the Biorka Island Fuel Cargo Line project due by April 5, 2023. This is a total small business set-aside for firms under $45 million. The Department of Transportation Federal Aviation Administration is the contracting agency. A mandatory site visit will be held on March 21, 2023 to review project details. Interested parties should RSVP in advance and plan transportation accordingly.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Contractor Walkthrough Biorka Island Fuel Cargo Line Questions Final.pdf | ||
| 697DCK-23-R-00143 Amendment 0001.pdf | ||
| 2019 Biorka Facility Response Plan Final for EPA review.pdf | ||
| TECH SPEC REFERENCE Dwg Pkg A.pdf | ||
| Biorka Island Fuel Cargo Line Specifications 3-14-23.pdf | ||
| Wage Determination AK20220001.pdf | ||
| BKA Fuel Cargo Line 697DCK-23-R-00143.pdf | ||
| BKA Fuel Cargo Line SOW - Final 3-6-23.pdf | ||
| Picture of possible route.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BKA – Sitka, AK – Fuel Cargo Line March 27, 2023
SUMMARY OF WORK
1.0 GENERAL
1.1 SCOPE
The selected Contractor shall design, engineer, and furnish all labor, products, equipment, and materials for the construction and installation of approximately 925’ of 4” steel fuel pipeline and 480/277 VAC feeder in 3” fiberglass conduit on Biorka (BKA) Island located near Sitka, Alaska. The new fuel pipeline will replace an existing line that is routed on west side of the road (hillside). The ends of the fuel line are the pig catcher located atop the existing fuel tanks and the fuel barge connection located on the dock. This new pipeline will establish a route located on the East side of the road and above the approximate shoreline. Where the pipeline crosses the road, a concrete channel with removable covers, will be provided to access the pipeline for testing, maintenance, and repair. At no point will the pipeline be direct buried.
An existing 480/277 VAC feeder connects the power house and dock utility building. The feeder conduit is mounted atop and supported by the existing fuel line and subject to damage from falling trees. This feeder will need a new routing above ground apart from where it crosses the road at each end between disconnect located at the trestle abutment and the first pull box located outside the powerhouse buildings.
“Construction and Installation” will include, but is not limited to all site preparation, vegetation clearing, culvert replacement, installation of road crossing reinforced concrete vault and cover to withstand up to 140 tons (approx. 31 feet); footings and stanchions for fuel cargo line (2 foot above ground), testing IAW API standards, installation of power run; pier supports and connections of fuel cargo line and fiberglass conduit; manual stainless steel air relief valves;
removal of existing fuel cargo line and attached feeder conduit.
The following items are a summary of the project and are provided solely for the purpose of describing the general nature of the work. The Contractor is responsible for accomplishing all items of work identified in the design/engineering, applicable drawings, specifications, and provisions of the contract:
A. General
1. Biorka (BKA) Island is an active operational facility, which runs 24 hours a day, 7 days a week.
2. BKA Island is located approximately 15 miles south of Sitka via ocean; BKA is equipped with a barge landing, pier, and floating dock for access and material handling.
3. All work shall be coordinated with the FAA and be accomplished on a “Not to interfere with FAA operations” basis.
4. Construction material shall be stored only in FAA approved areas.
5. Construction staging shall be allowed only in the FAA approved areas.
6. The Contractor shall provide all temporary services required for construction.
7. The FAA cannot guarantee housing or utilities will be available to the Contractor during construction on the island.
8. The Contractor shall clean up and restore the site grounds to its original condition after the work has been performed.
9. Contractor will be responsible for a design build approach for a new fuel cargo line and one clean power cable run from the power plant to the pier and all associated components.
B. Engineering & Design
1. Contractor shall engineer and draw up all site prep, slope of fuel cargo line, proper stainless steel, manual air relief valves, stanchions and support foundations, concrete channel with removable steel cover(s) to withstand up to 140 tons, culvert replacement, and one 480/277 VAC feeder between disconnect located at the trestle abutment and the first pull box located outside the switchgear building.
2. The new fuel cargo line and its subparts must be reviewed/stamped by a licensed PE registered in the state of Alaska.
3. The contractor will be responsible for updating the Spill Prevention Countermeasure and Control (SPCC) plan/Facility Response Plan (FRP) which must be approved by the Environmental Protection Agency and US Coast Guard. The FAA will provide the contractor with the existing (SPCC) and (FRP) documents.
4. Prior to final design, once at 50% completion and another at 90% completion a review process will be conducted to address any comments/questions or changes to the project with FAA representatives. Submittal will be reviewed for proper operation and compliance with requirements detailed in this section.
5. Appendix A, BKA-D-MAREQ-G002 thru G005 and E001 provide design direction as used for dock construction. This direction and methods of design apply to this contract.
C. Demolition
1. Remove and properly dispose of all construction debris, overburden (soil, rocks, etc.,) off island. Once new fuel cargo line and new 480/277 VAC feeder run have been installed and tested, remove existing fuel cargo line and 480/277 VAC feeder run and properly dispose of off island.
2. All vegetation shall be removed along the west end of the road and burned on the island in a location approved by the FAA. Stumps may be left in place for erosion control.
D. Installation
Site Prep and Installation Spec’s
1. Grade site and excavate only as needed for new fuel cargo line, 480/277 VAC feeder run, concrete encased channel and cover, and stanchions and foundations. All construction practices must be in accordance with state and local codes and be properly designed for the associated climate zone.
2. Within the Pig Box, install a clear Lexan pig catcher between the tank line and the fill line with Victaulic fittings and stainless-steel bushings and hardware.
3. The pipe coming out of the Pig Box should sweep 90 degrees at the level of the Pig Box and continue out over the fence then sweep 90 degrees downward past the rock retaining wall.
4. Where the pipe comes into and out of the concrete vault, a static steel plate will need to be welded to the pipe holding it in place permanently on the vault.
5. The vault will need to a concrete cap on the end nearest to the rock retaining wall so that it does not turn into a drainage ditch. The vault will have a 1-degree slope towards the shoreline and be fully open on the other end to allow for drainage.
6. Where the pipe exits and comes up out of the concrete vault on the West side of the road, a manual air relief valve will need to be installed.
7. (2) 8-inch round bollards will need to be installed between the pipe and the road to protect the line from damage on each side.
8. After crossing the road, the cargo line should follow the road edge all the way out to the dock approx. 3’ off the edge.
9. The cargo line fasteners to the dock shall allow for the pipe to move on UHMW pads.
10. The cargo line run out on the dock will need to be armored near the dock cranes to prevent damage from swinging loads.
11. At the barge filling station on the end of the dock, a manual air bleeder will need to be installed inside of the filling station housing.
Pipeline Testing
1. Testing as required by US Coast Guard and Federal and State EPA will be performed by contractor and witnessed.
2. Non-destructive testing of all welds will be performed by contractor.
Electrical Installation
1. Between the power house pull box and point the electrical is integrated with the fuel pipe support stanchions, the electrical line will need to be trenched 3’ down, bedded with sand, taped, and direct buried.
2. Between the fuel pipe support stanchions at the dock end and the dock electrical pull box, the electrical line will need to be trenched 3’ down, bedded with sand, taped, and direct buried.
3. The electrical run above ground shall be installed in fiberglass conduit with all the proper angled fittings and attached to the support stanchions. At no point shall the fiberglass conduit be heated and bent for angled sweeps.
4. All electrical work and grounding shall comply with the latest revision of FAA specifications and standards, and NEC as required e.g., FAA-C-1391E and FAA-STD-
019. Note: these FAA documents are a substantive part of this contract specification. For example, these documents specify submittals, material choices, dictate additional grounding and bonding not required per National Electrical Code (NEC) or National Electrical Safety Code (NESC). .
5. All bonds shall be exothermic welds or FAA approved pressure connections IAW
FAA-STD-019.
6. Provide updated printed panel schedules to affected electrical panels.
7. Label all new equipment with Voltage, Amps, Phase, Source and Feed info, and
Breaker info. Labels shall be plastic engraved nameplates with white letters and black background. Letter size must be 1/8" for controls, 3/16" for devices on control panel covers and 3/8" for safety switches, and other equipment devices. Nameplates must be secured to equipment, cabinets and to controls with adhesive backing.
Provide and install Arc-flash labels, as required.
8. Utilize liquid-tight type flexible conduit when flexible application is required. Flex conduit shall not exceed 6’ individual length.
9. EMT Conduit with compression fittings is only allowed on the interior of FAA facilities.
10. See appendix A, drawing sheets BKA-D-MAREQ-EXXX for additional electrical requirements and methods of design.
Testing & Procedures Electrical
1. Perform megger test on new cables and hydrostatic testing of pipeline with FAA rep, provide written results to FAA rep. Provide torque values on all newly installed equipment in written format to FAA rep.
2. Perform an operational check of all newly installed equipment.
3. Provide one-line diagram and LO/TO procedures for all new electrical equipment installed in a binder.
1.2 APPLICABLE DOCUMENTS
A. Applicable Documents - All FAA, Military, Federal, and industrial codes or standards, specifications, and are applicable only to the extent they were used as a basis of this design. All references to codes, standards, specifications, and construction drawings refer to the latest editions (and any supplements) in effect on the date of the contract.
B. Applicable Publications - The publications listed below form a part of this specification to the extent referenced. The publications are referenced to in the text by basic designation only.
1. Code of Federal Regulations (CFR):
a. OSHA General Industry Safety and Health Standards (29 CFR 1910), OSHA
Construction Industry Standards (29 CFR 1926). OSHA 2202 is a condensed version of 29 CFR 1926. Each is for sale by the Superintendent of Documents, U.S. Government Printing Office, Washington DC 20402.
1.3 DEFINITIONS
A. Federal Aviation Administration (FAA) - The terms "Federal Aviation Administration" (FAA) and "government" as used herein denotes the "owner".
B. Contracting Officer (CO) - The term "Contracting Officer" (CO) as used herein denotes the person designated to act for the Government in the performance of this contract.
C. Contracting Officers Representative (COR) - The term "COR” as used herein denotes the representative of the Contracting Officer at the job site. The term is synonymous with the FAA terms "Resident Engineer" (RE).
D. Contractor and Subcontractor - The term "Contractor" as used herein denotes the firm who will perform and complete the work required by the Contract. The term "subcontractor" as used herein denotes the person or firm retained by the Contractor to perform a particular unit of work required by the Contractor. Subcontractors shall be required to meet all specifications required of the Contractor.
1.4 CONSTRUCTION CONDITIONS
A. Post Award Telcon – The Contractor shall participate in a post award telcon at the time and date specified by the COR and local FAA site Tech. Schedule, scope, design, engineering, and general construction conditions will be discussed.
B. Pre-design Conference - The Contractor shall attend a pre-design conference at the time and location specified by the COR, with FAA site Tech.
C. Submittals – Engineering and design submittals will go through the 50% and 90% review process with the Contractor/Sub-Contractor(s), COR, and other FAA representatives, as required. Prior to submitting orders, the contractor shall submit specifications for each new component of the installation for approval. During the project contractor shall provide submittals for Samples, certificates, reports, catalog cuts, letters, shop drawings, red-lines, maintenance and operations manuals, etc. as required. All documents shall be submitted to the COR and a hard copy binder to FAA site Tech.
D. Conflict Resolution - The Contractor shall meet standards, specifications, and drawings as specified herein. The specifications and drawings shall rule in all cases.
Specifications shall govern over drawings. If any conflict should exist between site drawings (location-specific drawings) and standard drawings (drawings not referring to a particular location), the site drawings shall govern. In the event of dimensional discrepancies or omissions, the Contractor shall field verify and correct the information, and notify the RE. No work shall be done until agreement has been made with the RE
E. Inspection
1. Access for Inspection - The Contractor shall allow the RE complete access to all portions of the work. Portions of the work buried, enclosed, or disguised, shall be inspected by the RE before being obscured by the next operation of the Contractor.
In all cases, the RE shall be informed accordingly and given access to the work. Work obscured before inspection and acceptance by the RE, may, at the option of the RE be opened for inspection at no additional cost to Government.
The RE will inspect all work in progress up to completion and final Contractor’s Acceptance Inspection (CAI) including all materials, tools, and equipment. Such inspection may extend to all or a part of the work for the preparation, fabrication or manufacture of the materials to be used. The RE will notify the Contractor of any non-compliance with the contract specifications and/or drawings, and may reject workmanship or materials accordingly.
2. Contractor's Acceptance Inspection (CAI) - After substantial completion of all the Contractor's work, a CAI will be conducted between the Contractor and Government. The RE will review the contract documents and verify that the Contractor has completed all required work. If work remains to be completed, an itemized list will be prepared, and the contractor at no additional cost to the Government shall complete the remaining tasks correctly. A Joint Acceptance Inspection (JAI) requires FAA personnel to be present. It may be held concurrently with the CAI.
F. Project Coordination - The Contractor shall be required to coordinate his/her construction activities with the FAA through the COR. All work which affects the facility shall be coordinated and approved by FAA personnel through the COR at least 10 days in advance of the scheduled work. Failure to notify and obtain the necessary approval may result in a rescheduling of the work. If weather conditions or aircraft operations preclude a scheduled shutdown of an existing FAA facility, the Contractor shall reschedule the work. The Contractor will be required to coordinate all power shutdowns of existing facilities with the FAA, through the COR, 5 days in advance. Each shutdown shall be limited and off-peak hours shall be required for testing or power shutdowns, with the facility placed back in service at the end of the workday, or as stipulated by the FAA.
G. Layout of Work - The Contractor shall field verify measurements and work from the established base lines and bench marks indicated on the drawings and shall be responsible for all measurements in connection therewith. The Contractor shall furnish, at his/her own expense, all stakes, templates, platforms, equipment, tools, materials, and labor as may be required in laying out any part of the work from the base lines and bench marks previously established. The Contractor will be held responsible for the execution of the work as detailed in the plans and specifications. It shall be the responsibility of the Contractor to maintain and preserve all stakes and other marks previously established until authorized to remove them.
H. Permits, Inspection, Licenses, Certificates - The Contractor shall obtain and pay fees for permits, inspections, licenses, or certificates required by Federal, State and City/Town officials as necessary to perform the work, prior to starting construction, and in a timely manner to avoid delays in starting the job. The Contractor shall submit evidence that they have obtained all required permits, inspections, licenses, and/or certificates.
I. Compliance with Local and Other Codes - The Contractor shall comply with local and other codes and standards. Where the requirements of the specifications and drawings exceed those of the local or other codes, the Contractor shall comply with the requirements of the specifications and drawings.
J. Stop Work Orders - When the Contractor or subcontractors are notified by the COR other serious violations shall be corrected immediately. Non-serious violations shall be corrected within 24 hours of the non-compliance notice. The COR may stop the work with a “stop work order” if the Contractor fails to comply promptly with all or any part of the work being performed. When, in the opinion of the COR, satisfactory corrective action has been taken to correct the unsafe and unhealthy condition, the Contractor may resume work. The Contractor shall not be allowed any extension of time or compensation for damages by reason of or in connection with such work stoppage.
K. Protection of Existing Vegetation, Improvements and Structures - The Contractor shall take all precautions necessary to protect the existing facilities, equipment, buildings, foundations, vegetation, etc., during construction. Any areas damaged by the Contractor or any subcontractors, shall be repaired or replaced to their original conditions by the Contractor at no additional cost to the government. Repairs shall be approved by the COR and shall match to original finish. The Contractor shall provide all temporary covers, enclosures, barricades, etc., required to protect the existing facilities.
L. Schedules
1. Schedule - The Contractor shall, within ten (10) calendar days from date of award of contract, submit to the CO for approval a practical project schedule. The schedule shall show the order in which the Contractor proposes to carry out the work, the date on which he/she will start the several salient features (including procurement of materials, plant and equipment) and the contemplated dates for completing the work. The schedule shall be in the form of a progress chart of suitable scale to indicate the approximate percentage of work scheduled for completion at any time.
The Contractor shall enter on the chart the actual progress at such intervals as directed by the CO. The project schedule shall include a milestone schedule for payments. The milestones should be stated with requested reimbursement for each milestone (based upon actual costs, overhead and profit).
2. Progress Schedule - The Contractor, if requested by the CO, shall submit a progress schedule at such intervals as directed by the CO. If the Contractor fails to submit a progress schedule within three (3) business days, the CO may withhold approval of progress payment estimates until the Contractor submits the required progress schedule.
3. Hours of Work – Shall be approved by the COR. Most of the work is expected to be performed during normal working hours, however some work may be required afterhours. Work on weekends and Federal holidays shall be approved before time by the COR in writing.
M. Site Access - Access to the site will be via a pre-determined route identified and agreed upon at the pre-construction conference.
N. Special Permits - The Contractor shall obtain and submit evidence of all necessary permits for the work. The Contractor shall abide by all requirements dictated by the city, state, federal, airport authority or municipality for such permits without any additional cost to the government.
O. Waste Disposal - The Contractor shall provide on-site containers for the collection of construction waste materials, debris and rubbish and their daily removal from the site.
Any spillage on access and haul routes shall be cleaned up immediately. All spoil, waste and debris removed from the work site and not specified for reuse or identified as salvageable items, or identified as contaminated contents shall be disposed of off-island in areas authorized by the applicable County, State and/or Local agencies and in accordance with current rules and regulations governing the disposal of such waste.
The Contractor, at no additional cost to the government, shall pay disposal fees and miscellaneous charges. Copies of all documentation of the disposal of any fuel or hazardous wastes will be submitted to the COR.
P. Cleanup - The work site shall be kept clean and orderly during the progress of work.
After final inspection, but before final acceptance of the work, all exterior surfaces of the equipment shall be cleaned of dirt, mud, or oil accumulations. All debris shall be removed from the general site area.
Q. O & M - Upon completion of the facility modifications, the Contractor shall provide operation and maintenance instructions for all new equipment. This information will then be retained by the COR (and the FAA) and used to reflect the as-constructed conditions.
R. Warranties - Documentation for the warranties shall be provided to the government upon completion of the project.
1.5 SAFETY
OSHA and FAA safety standards will be enforced. In keeping with such standards, the Contractor shall, at a minimum, provide:
A. Safety Plan - The Contractor shall have and submit a Safety Plan with the purpose of maintaining a safe working environment for construction workers employed on site.
The safety plan shall require a statement that the current Occupation Safety and Health Act (OSHA) regulations on safety in the construction industry, OSHA Title 29, Part 1910 and Part 1926, as well as FAA safety regulations are followed. The plan will be used by the COR to insure that the work is accomplished in accordance with accepted safety practices.
B. Trained Personnel - Personnel shall be properly trained in the usage of all equipment for which they will be required to use during the Contract. The COR may request documentation or other evidence of training at any time. Personnel without adequate training will be prohibited from using such equipment.
C. Lock Out / Tag Out – The Contractor shall employ and detail lock-out / tag-out procedures to employees working with and around electrical systems. When accessing an electrical panel, a FAA technician must be present prior to interrupting and energizing the breakers.
D. Material Safety Data Sheets - The Contractor shall have Material Safety Data Sheets
(MSDS) conforming to Federal Standard 313A, written by the manufacturer, for all materials containing chemicals or other substances which may pose a hazard. One (1) copy of each MSDS shall be submitted to the COR and one (1) copy of each MSDS shall be kept on file at the job site at all times. The Contractor and subcontractors will be prohibited from handling any material which does not have an applicable MSDS on file at the site until such MSDS arrives on site.
E. Safety Equipment - The Contractor shall provide safety equipment including, but not limited to, a Red Cross approved First-Aid kit and the appropriate number of annually inspected, charged fire extinguishers with the proper NFPA rating.
F. HAZCOM Program - The Contractor shall have a hazard communications (HAZCOM) program. The Contractor and each subcontractor shall submit a copy of their HAZCOM program as well as a copy of their current OSHA 200 form, if requested.
G. Work Practices - Although OSHA regulations and the Contractor's Safety Plan will usually apply, the COR may consider certain work practices to be unsafe in accordance with Public Law 91-596, Part 5a and 5b. The COR may stop any operation which is in violation of the OSHA standards or fails to comply with the safety plan or other safe work practices.
H. Designated Foreman - When any construction activity is conducted at the site, the presence of a designated, competent contractor’s foreman is required at the job site.
The foreman must be qualified and capable of organizing and coordinating all activities of the Contractor and his subcontractors, and keeping a safe job site.
I. Work Force - The Contractor shall at all times, when construction activities are conducted, have a substantial number of workers for each task to proceed expeditiously and without generating delay, for lack of man-power.
2.0 CONTRACTOR-FURNISHED MATERIAL AND EQUIPMENT
2.1 MATERIAL DELIVERIES
All material deliveries made under this contract shall be arranged for delivery to the Contractor's material staging area. This area shall be located as determined at the pre-construction conference.
2.2 STORAGE AND PROTECTION
The Contractor, through the COR, shall secure from FAA all necessary clearances for storage areas on site, including any time limitations upon the use of such areas. The storage and protection of Contractor material shall be the sole responsibility of the Contractor. The Contractor shall provide at his/her own expense all fencing, shelters and security personnel as may be necessary for the protection of the material and equipment.
2.3 PERTINENT INFORMATION
Any pertinent information listed about the contractor-furnished material and equipment shall be submitted to the COR.
3.0 EXECUTION
3.1 WORK SEQUENCE
General: Biorka (BKA) Island is an active operational facility, which runs 24 hours a day, 7 days a week; therefore, all work shall be coordinated and accomplished on a “Not to interfere with FAA operations” basis. Some of the work performed may have to be accomplished after hours to accommodate Air Traffic Operations.
3.2 CONTRACTOR USE OF PREMISES
A. Use of the Site - Do not disturb portions of the site beyond the areas in which work is required.
B. Driveways and Entrances: Keep driveways and entrances serving the premises clear and available to the Government, the Government’s employees, and emergency vehicles at all time. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
C. Use of the Existing Building - Maintain the existing building in a watertight condition throughout the construction period. Repair damage caused by construction operations.
Take all precautions necessary to protect the building during the construction period.
END OF SECTION
| B. Engineering & Design |
| D. Installation |
| 1.2 APPLICABLE DOCUMENTS |
| A. Applicable Documents - All FAA, Military, Federal, and industrial codes or standards, specifications, and are applicable only to the extent they were used as a basis of this design. All references to codes, standards, specifications, and construc... |
| B. Applicable Publications - The publications listed below form a part of this specification to the extent referenced. The publications are referenced to in the text by basic designation only. |
| 1.3 DEFINITIONS |
| 1.4 CONSTRUCTION CONDITIONS |