Amendment0002.pdf

PDF 219 KB Posted

Attached to
Replace five (5) A/C unit Splits at the Annex Building at the Miami ARTCC, Miami, FL
Solicitation number
697DCK-22-R-00475
Issued by

About this file

This amendment to a solicitation provides clarification on requirements for replacing five split air conditioning units at the Annex Building of the Miami Air Route Traffic Control Center. The Federal Aviation Administration is seeking offers for furnishing all labor, materials, and equipment to complete the replacement, including elevating new condensing units on beams, installing metal jacketing on exterior piping insulation, and providing a five-year compressor warranty and one-year parts and labor warranty. Offerors must be a service-disabled veteran-owned small business. The price range for the work is $500,000 to $1,000,000 and payment and performance bonds are required. The submission deadline is not provided.

View the file

Other files

File Type Posted
amendment0003.pdf PDF
amendment0001.pdf PDF
ZMA-1202196-DRAW FINAL.pdf PDF
DOLWAGERATE.pdf PDF
ZMA-1202196-SPEC FINAL.pdf PDF
RFO697DCK-22-R-00475.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO.

PAGE OF PAGES

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

CODE

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

Items 8 and 15, and returning is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required.)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.

E. IMPORTANT: Contractor is not, is required to sign this document and return

ORDER NO. IN ITEM 10A.

1 3

0002 07/29/2022

FEDERAL AVIATION ADMINISTRATION

AAQ-500 - REGIONAL ACQUISITIONS

1200 DISTRICT AVENUE

BURLINGTON MA 01803

AAQ510BOS-AFN

x

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ x x

697DCK-22-R-00475

copies to the issuing office.

07/05/2022

(x)

LIST OF CHANGES:

Amendment 0002 is issued for the following questions and answers and Specification changes:

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Susan J. Newcomb

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

697DCK-22-R- 00475

Amendment 0002

1. Is there an existing central fire panel system for which the duct detectors will be needed to integrated with? I.e. do we need proprietary detectors from a specific vendor?

No central fire panel system to integrate to.

2. Existing condensing units are mounted on small beams so that they are elevated 4”-6” from the slab. Should new units be set directly on slab or new beams provided?

New units should be elevated on new beams.

3. Existing AHU’s are mounted on beam / spring assemblies. Shall new units be mounted in similar fashion or internal isolation acceptable? Or, is the elevation of the units for the purpose of having enough height for proper condensate drainage?

New units may be internally isolated and mounted on pad.

4. Not clear on Amendment #1, answer #2 regarding controls.

a. Is intent to temporarily remove devices and reinstall or provide new devices with existing wiring. We checked the control diagrams on site, and they seem to match the same points being shown on drawing ZMA-M601 so infer that we are temporarily disconnecting and reconnecting existing devices, switches, etc.

Provide and install new devices. Existing wire may be used if no splice is required.

Splices in control wire is not acceptable, if existing wire is not long enough new wire must be installed.

5. Confirm no auxiliary drain pans required under new AHU No auxiliary drain pans required under new AHU.

6. Confirm that metal jacketing is required on exterior DX piping insulation.

Metal jacketing required on exterior DX piping insulation.

7. Each units test period of 24 hours per 1.19 is this required to be witnessed? Scheduled in advance?

Testing period should be shown on construction schedule. Coordinate any deviations from schedule with COR. COR will witness testing.

8. Submittals Section 1.5.D the $350 deduct if a submittal is rejected and must be reviewed again seems excessive. There are many reasons a submittal could be rejected and as long as a contractor is acting in good faith why is this included?

This section will be removed from the specs along with this amendment.

9. Clarify all bonding requirements for this project.

Reconnect existing grounding and bonding cables to new condensing units.

10. Clarify the warranty requirements the specifications require much longer and more costly requirements than the Solicitation Package does.

Compressor warranty for 5 years, labor and parts for 1 year. Warranty requirements of spec updated with this amendment.

11. Section L states: L.3 CLIENT PAST PERFORMANCE DOCUMENTATION is required. Can subcontractor past performance be submitted?

Answer: No, Experience must be of the prime contractor. Subcontractor experience cannot be used in lieu of prime contractor experience.

The following Specification Changes are hereby incorporated into the RFO:

Spec changes

REMOVE

01 33 00 1.5 D

Resubmittal Costs: Initial submittals requiring Government approval will be reviewed at no cost to the Contractor. The cost of reviewing resubmittals, for reason of failure of the initial submittal to meet contract requirements, shall be the responsibility of the Contractor. The COR will issue a deductive contract modification to reduce the contract price by $350.00 for each resubmittal of items requiring Government review and approval. The contract completion date will not be extended due to non-compliance with submittal requirements.

REMOVE

23 81 26 1.9 A 1

Warranty Period:

a. For Compressor: One year from date of Substantial Completion.

b. For Parts: One year from date of Substantial Completion.

c. For Labor: One year from date of Substantial Completion.

ADD

23 81 26 1.9 A 1

Warranty Period:

a. For Compressor: Five years from date of Substantial Completion.

b. For Parts: One year from date of Substantial Completion.

c. For Labor: One year from date of Substantial Completion.

697DCK-22-R-00475amend002
amendment0002