This statement of work defines the requirements for a design-build contract to replace the building automation system and relocate an HVAC distribution panel at the Bethel Air Traffic Control Tower in Bethel, Alaska. The project involves designing and installing a new BACnet-compliant building automation system to control and monitor HVAC equipment, replacing the existing legacy system. It also requires relocating an HVAC distribution panel to meet NEC clearance requirements and installing a new panel. The contractor must design the systems, submit 95% and 100% design packages for review, develop an implementation schedule, install the work per the approved design, and commission and test the new systems. The contractor must provide two years of warranty coverage and ongoing seasonal inspections and adjustments. The work must comply with FAA design standards and codes and be completed within 120 days of award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 001.pdf | ||
| As-built Feb 2021.pdf | ||
| Davis Bacon.pdf | ||
| COVID Spec language.pdf | ||
| BET ATCT SOW R1.pdf | ||
| 697DCK-21-R-00179.pdf | ||
| PPQ.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO.
PAGE OF PAGES
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
CODE
9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
Items 8 and 15, and returning is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required.)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.
E. IMPORTANT: Contractor is not, is required to sign this document and return
ORDER NO. IN ITEM 10A.
1 2
0002 04/02/2021
FEDERAL AVIATION ADMINISTRATION
AAQ-500 - REGIONAL ACQUISITIONS
2200 S. 216TH STREET
DES MOINES WA 98198-6547
AAQ530ANM-AFN
x separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ 0 x x
697DCK-21-R-00179
0 copies to the issuing office.
04/02/2021
(x)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The following is hereby added to the subject RFO:
Answer to received question, revisions to submittal schedule, due date clarification.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Darren T. Odegard
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Q. As per document 697DCK-21-R-00179, pdf page 37, a Buy American clause is mentioned. Could you please confirm that we should bid this project w/ Buy American? Is that is so, could you please also confirm under which FAR clause should we use?
A. Yes, Buy American Act is a requirement. The AMS clauses included in the subject RFO are the applicable ones. The FAA is not under the FAR.
Clarification on Due Date:
The correct Due Date for this RFO is Thursday April 29, 2021 at 2PM local Seattle time.
Project Delioverables Schedule See included Spec with revision.
Federal Aviation Administration Engineering Services
JCN: 1508626, 1703818
Statement of Work: Bethel Air Traffic Control Tower (ATCT) Controls Upgrade and HVAC Panel “M” Relocation
Rev-1
Bethel, Alaska
BET ATCT
April 13th, 2021
Design-Build Scope of Work, BET ATCT, Bethel Alaska P a g e | i
TABLE OF CONTENTS
1. Project Overview
1.1 Building Automation System (BAS) Upgrades
1.2 Relocate HVAC Distribution Panel “M”
2. Scope of Work
3. Project Objectives
4. Operational Risk Management (ORM)
5. Miscellaneous
5.1 Coordination/Permitting
5.2 Schedule
5.3 Vendor Requirements
5.4 Government Furnished Property
6. Functional Requirements
6.1 Mechanical
6.2 Electrical
7. Warranty
8. Criteria for Design and Construction
8.1. Industry Codes and Standards
8.2. FAA Design Standards
8.3. Occupational Safety and Health
9. Deliverables
8.1 Hard Copy Deliverables
8.2 System Training
10. Points Of Contact
Design-Build Scope of Work, BET ATCT, Bethel Alaska P a g e | 2
1. PROJECT OVERVIEW
This statement of work defines the requirements to design and install a replacement Building Automation System (BAS) and relocate an HVAC distribution panel for the Bethel Air Traffic Control Tower (BET ATCT). The work will be procured under a firm fixed price, design-build contract and delivered in accordance with the provided template BAS specifications and other FAA Standards referenced in this document. The period of performance for this task is 120 days from contract award.
1.1 BUILDING AUTOMATION SYSTEM (BAS) UPGRADES
Design and install a new BAS to replace the existing legacy Barber Coleman Network 8000 control system.
1.2 RELOCATE HVAC DISTRIBUTION PANEL “M”
The existing HVAC distribution panel “M”, located in the building’s fan room, does not meet the required NEC face clearance in its current location. Install new panel in a suitable location to meet NEC clearance requirements, route new conduit, and pull new wiring.
2. SCOPE OF WORK
The scope of work for this project is as follows.
a. Review the following FAA provided information in preparation for site survey:
i. Floor plans and equipment lists.
ii. Sequence of operation.
iii. As-built control drawings of the existing BAS.
b. Conduct site survey of BET ATCT’ to collect the additional information needed to prepare BET ATCT’s 95% Design Package. During the site survey:45
i. Provide the (FAA) BET ATCT team with an overview of the effort for each scope item, schedule, and objectives. Review the site-survey activities and schedule.
ii. Walk the project areas and mark-up existing drawings as needed.
c. Prepare and submit Site Survey Meeting Minutes.
d. As part of the site survey, conduct an on-site point-to-point verification of BET ATCT’s equipment to confirm functionality of the existing BAS, and note all deficiencies identified. Provide a Technical Assessment Report detailing point-to-point deficiencies.
e. Develop and provide 95% and 100% Design Package for BET ATCT. The Design Package will include:
i. Installation drawings and specifications including system network architecture, system piping and instrumentation (P&ID) flow diagrams, panel interior drawings, controller termination details, instrumentation & control (I&C) end device details, sequences of operations, control power information, and bill of materials.
ii. Site summary drawings of facility floor plans with network route and locations.
iii. Installation drawings and specification for relocation of HVAC distribution panel “M.”
iv. Hardware and software product data, including updated floor plans, power one-line diagrams, and panel schedules.
v. Installation/phasing plan.
f. Fixed indent Review and provide written responses with comment resolution to all FAA comments on 95% and 100% Design Package. Participate in teleconferences to discuss the Design Packages, during which comments and responses will be discussed. Provide a design review document with comments, written responses and final comment resolutions along with the revised design documents following each design package submittal. If
Design-Build Scope of Work, BET ATCT, Bethel Alaska P a g e | 3 comments aren’t adequately addressed in the revised design package, additional review teleconferences maybe required.
g. Develop and provide an implementation schedule based on the 100% Design Package.
h. Participate in Pre-construction meeting with Contracting Officer and other project stakeholders.
i. Coordinate anticipated system outages with FAA Resident Engineer (RE) and Contracting Officer’s
Representative (COR).
j. Mobilize to site and install new work as outlined in approved 100% Design Package and implementation schedule.
k. Submit daily construction progress reports to FAA RE and COR in accordance with approved specifications.
l. Conduct final commissioning, testing, and balancing of system.
m. Following the system commissioning, provide a complete system demonstration and verification of the sequence of controls. This demonstration must be scheduled 1 week in advance to allow for the facility operations personnel to attend.
n. Attend Contractor Acceptance Inspection (CAI) and Joint Acceptance Inspection (JAI) with FAA COR and facility personnel.
o. Clear any exceptions or punch list items.
3. PROJECT OBJECTIVES
• Modernization of the HVAC control system with new, industry leading software and hardware.
• Replacement of the existing panel M with a new power distribution panel in a new location within the fan room that provides the necessary FAA clearance.
• Minimum planned design life of 15 years.
• Maintain operational integrity of FAA systems and service. Construction to occur within an active Air Traffic
Control Facility. Any interruption of service may result in loss of life or injuries. All work must be coordinated and planned to avoid impacts to service.
− Any activity requiring an outage of any National Airspace System (NAS) equipment must be coordinated with FAA. FAA approval is required prior to proceeding. Notification for all outages must be requested and approved a minimum of 72 hours (3 working days) in advance of anticipated outage.
− All electrical cutovers for power serving either essential or non-essential functions require an outage request and approval.
• All requirements defined in the scope of work are mandatory minimum performance requirements. Innovative, creative, and life cycle cost-effective solutions are encouraged. Any solution which expedites the completion of the project is encouraged.
4. OPERATIONAL RISK MANAGEMENT (ORM)
BET ATCT is a critical air traffic facility. The contractor must not interfere with or disrupt air traffic operations, and must not damage equipment or limit access in the facility. The work will be performed while BET ATCT is in operation and coordination will be required with the FAA Project Team to develop and implement a project plan permitting minimal support infrastructure systems downtime and impact to the mission operation.
Any activities that may have the potential to affect FAA systems will go through Operational Risk Management (ORM) meeting and reviews. These activities will include work plans and briefing meetings with FAA
Design-Build Scope of Work, BET ATCT, Bethel Alaska P a g e | 4 stakeholders. Contractors proposed schedule and planned outages will be incorporated into the project plan and will be essential to the ORM process. Lead contractor employees may be called upon to participate in ORM meetings and discussions hosted by the FAA.
5. MISCELLANEOUS
5.1 COORDINATION/PERMITTING
To ensure seamless design and construction, the contractor must coordinate all facets of the project. All design and construction activities must be coordinated with the facility to minimize disruptions. The Contractor must ensure that ATCT operations are not compromised during the course of construction.
5.2 SCHEDULE
The Design-Builder understands the project is time critical. The Design-Builder’s schedule must be based on 6-day, 10–hours/day workweek and the shift start and stop times will be negotiated between the Design-Builder and the FAA COR. BET ATCT hours of operation are 0700-2200 Apr-Oct 31 & 0700-2000 Nov-Mar31. The Design-Builder acknowledges working nights, weekends, and holidays may be required to complete the project within the contract schedule parameters. Any work outside the agreed-upon shift time needs advanced approval, minimum of 48 hours (two working days) is required from the FAA COR. The Design-Builder acknowledges denial of work outside the agreed-upon shift time will not be used as justification for additional compensation of any kind. The Design-Builder acknowledges the additional cost borne by the FAA for work outside the agreed upon shift may result in a deductive contract mod for those costs. Liquidated damages in the amount of $3,300 per calendar day may be imposed by the Contracting Officer for delays in accordance with the FAA Acquisition Management System (AMS). Avoidance of liquidated damages by working excessive overtime will not be compensable for the Design-Builder.
Moratorium shutdowns will be considered non-work days for construction activities. The FAA has identified two
(2) annual construction moratoriums:
1) The week of Thanksgiving, beginning 12:00 am the Monday prior to Thanksgiving and concluding 12:00 am the Monday following Thanksgiving
2) Christmas/New Year’s weeks; beginning 12:00 am the Friday prior to Christmas and concluding at 12:00 am
Monday following New Year’s Day.
The Design-Builder will develop a Critical Path Method (CPM) design and construction schedule. Schedules are required in PDF and MS Project format with each design deliverable and request for payment. The FAA will review and approve every schedule. Payment will not be processed if schedule is inaccurate, contains false or misleading information, or does not accurately depict progress to date. Contractor will revise and resubmit before payment processing will proceed. The Design-Builder will provide FAA with native format with each submission.
5.3 VENDOR REQUIREMENTS
• The contractor will have an in-place support facility in the State of Alaska with factory certified technicians and engineers, spare parts inventory and all necessary test and diagnostic equipment for the installed system. The control contractor will have 24 hours/day, 7 days/week emergency service available with on-site support in Bethel available within two days’ notice.
Design-Build Scope of Work, BET ATCT, Bethel Alaska P a g e | 5
5.4 GOVERNMENT FURNISHED PROPERTY
FAA will provide available sequence of operation and as-built drawings for BET ATCT; floor plans and equipment lists. Contractor will be responsible for field verification.
6. FUNCTIONAL REQUIREMENTS
6.1 MECHANICAL
• Provide a BACnet based Building Automation System (BAS) to control and monitor the HVAC equipment in the facility. All existing HVAC equipment in the facility will be integrated into the new BAS control system.
BAS control system to comply with FAA A&E design manual.
• Provide all necessary hardware, software and control devices to execute the sequence of operation and comply with the HVAC Control Diagrams and BAS Point Function Schedule shown on the FAA-approved engineering design package. The Operator’s Workstation (OWS), Building Controllers (BC), Advanced Application Controllers (AAC), Application Specific Controllers (ASC) and all input/output devices will communicate using the protocols and network standards as defined by ANSI/ASHRAE Standard 135–2004, BACnet. All controllers, including unitary controllers, will be BACnet-compliant and listed by the BACnet Testing Laboratory (BTL).
• Non-BACnet-compliant or proprietary equipment or systems including gateways are not acceptable and are strictly prohibited.
• Add all the necessary equipment, wiring or programming (points) for creating an emergency HVAC shutdown into the BAS. The emergency shutdown must allow for facility personnel to immediately shut off operation of system fans and close outdoor air intakes in the event of an emergency.
• Building must have a stand-alone HVAC system. All work must be evaluated for optimizing efficiency and reliability of the respective systems.
• The contractor is expected to sequence the work to limit HVAC system outages. Contractor must maintain temperatures in the Tower Cab and the electronic equipment rooms between 65˚ and 78˚ during outages.
• Completely check out, calibrate and test connected hardware and software to insure that the system performs in accordance with the specified requirements and approved sequences of operation. Validation will be witnessed by COR.
6.2 ELECTRICAL
• New power distribution panel must be installed in a new location to meet NEC clearance requirements.
• New power distribution panel should be sized to accommodate all circuits without the use of sub panels.
• The FAA has special requirements covering Earth Electrode Systems, Power Distribution System Grounding
Compliance, and Surge Protection Device Requirements, and Bulkhead Connector Plates. These requirements are provided in Attachment 1 – FAA-STD-19f. The DBE will insert the language and figures of Attachment 1 into the construction drawings and specifications.
Design-Build Scope of Work, BET ATCT, Bethel Alaska P a g e | 6
• The FAA has special requirements interior electrical work. These requirements are provided in Attachment 2 – FAA-C-1217H. The DBE will insert the language and figures of Attachment 2 into the construction drawings and specifications.
• Attachment 1 and Attachment 2 may exceed the requirements of the latest edition of NFPA 70 National
Electrical Code (NEC) and therefore take precedence. Electrical work not explicitly covered by Attachment 1 and Attachment 2 will comply with the NEC.
7. WARRANTY
Provide two year warranty for new BAS and electrical work. Include coverage for field programmable micro-processor based units. Provide four complete site inspections per year, one in each season, to inspect, calibrate, and adjust controls as necessary to improve system performance. Submit written reports. Warranty starts on the date of FAA acceptance via a signed CAI.
8. CRITERIA FOR DESIGN AND CONSTRUCTION
The work must be designed and constructed to adhere to the documents, codes, and industry standards and handbooks referenced as follows. When a conflict exists between the requirements of this document and its referenced documents, this document must take precedence. When the requirements of FAA documents conflict with other referenced documents, FAA documents must take precedence. In the event of conflict between any of the other referenced documents, the most relevant requirements must apply as determined by the FAA. The Contractor must notify the Contracting Officer when the proposed design conflicts with local code requirements.
8.1. INDUSTRY CODES AND STANDARDS
• International Building Code
• National Electrical Code (NFPA 70)
• IMC
• IFC
• NFPA 72 (for HVAC system ties into the fire alarm system)
• American National Standards Institute/American Society of Heating, Refrigeration and Air-Conditioning
Engineers (ANSI/ASHRAE) Standard 135–2004, BACnet - Data Communication Protocol for Building Automation and Control Networks, including all published addenda
• SMACNA Duct Construction Standards (for any duct revisions)
• TAB IAW NEBB or other recognized TAB balancing standard
8.2. FAA DESIGN STANDARDS
• FAA JO 6480.7E - Air Traffic Control and Terminal Radar Approach Control Facility Design Guidelines
• FAA ATO Terminal Facilities Standard Designs – A/E Project Manual
• FAA-STD-002C - Facilities Engineering Drawing Preparation
• FAA-STD-019F - Lightning Protection, Grounding, Bonding, and Shielding Requirements for Facilities
• FAA-C-1217H - Construction Specification for Interior Electrical Work
8.3. OCCUPATIONAL SAFETY AND HEALTH
• Occupation Safety and Health Act (OSHA), PL 91-596.
Design-Build Scope of Work, BET ATCT, Bethel Alaska P a g e | 7
9. DELIVERABLES
The deliverables are identified in the following table.
Item Deliverable Due Date
Delivered to Whom Acceptance Criteria
1. Site Survey Meeting Minutes
Five (5) calendar days after completing the on-site survey of BET ATCT’s existing site conditions.
Western Service Area (WSA) Engineering Services (ES), Program Implementation Manager (PIM), BET ATCT, and Support Contractors
[Electronic format only]
The meeting minutes are delivered on-time and document key site survey discussions.
2. Technical Assessment Report
Fifteen (15) calendar days after completing the on-site point-to-point inspection
WSA ES, PIM, BET ATCT,
and Support Contractors
[Electronic format only]
The report is delivered on-time and it details all point-to-point deficiencies identified.
3. 95% Design Package
Thirty (30) calendar days after completing on-site survey of existing site conditions
See Distribution table below The Design Package must 1) be delivered on-time; 2) include all of the items identified in the Scope of Work section of this Task Statement; 3) incorporate site specific information from the on-site survey; and 4) be free of significant typos and other errors.
FAA will review and respond with review comments within fifteen (15) calendar days of receipt. At this time, the FAA will also schedule a 95% design review meeting, during which comments and responses will be discussed as needed.
Design-Build Scope of Work, BET ATCT, Bethel Alaska P a g e | 8
4. 100% Design Package
Twenty-one (21) calendar days after 95% Design Review Meeting.
See Distribution table below The Design Package must 1) be delivered on-time; 2) include all of the items identified in the Scope of Work section of this Task Statement; 3) incorporate FAA comments on the 95% package as agreed to; and 4) be free of typos and other errors.
FAA will review and respond with review comments within fifteen (15) calendar days of receipt. At this time, the FAA will also schedule a 100% design review meeting, during which comments and responses will be discussed as needed.
After the 100% design review meeting, a revised 100% Design Package will be provided if necessary.
5. Construction Schedule
Ten (10) calendar days after FAA acceptance of 100% Design Package
WSA ES, PIM, BET ATCT,
and Support Contractors
[Electronic format only]
The Installation Cost Proposal and Implementation Schedule are delivered on-time.
6. Construction Submittals
Submitted with Design Package.
WSA ES, PIM, BET ATCT,
and Support Contractors
[Electronic format only]
Construction submittals are submitted on time. Submittals are complete, submitted with cover sheets, and with options/accessories clearly annotated.
7. Final Commissioning and TAB Reports
Fifteen (15) calendar days after final commissioning is completed.
point-to-point inspection
WSA ES, PIM, BET ATCT,
and Support Contractors
[Electronic format only]
The report is delivered on-time.
Design-Build Scope of Work, BET ATCT, Bethel Alaska P a g e | 9
8. Operation & Maintenance Manuals
Submitted at project close out.
See distribution table below. Submitted on time.
O&M manuals are complete, and organized into binders.
Manuals contain, for each system component, submittals, manufacturers Operation & Maintenance data, warranties, and spare parts lists. Manuals also must contained complete updated controls drawings, to include old and new drawings.
9. Revised BAS System Training
First training session due at project close out. Subsequent sessions to be coordinated with
FAA.
BET ATCT Facility Technicians
Provide 35 hours of trainings over a 3 month period that adequately prepares facility personnel for operation of BAS.
8.1 HARD COPY DELIVERABLES
The table below identifies hard copy deliverable recipients and quantities. In addition, one copy of the deliverables in the table below is to be provided electronically to each of the recipients identified. Drawings are to be provided electronically in both AutoCAD and Adobe PDF formats, and all other deliverables are to be in Adobe PDF format (and available in Microsoft Word upon request). Half size drawings are “ANSI B” size, and Full size drawings are “ANSI D” size. O&M’s of equipment, balance report, final complete control drawing package which includes all existing and new sensors, controls etc for complete controls drawing package which can be used for system review (etc) without reference to any previous project’s control system drawings.
95% Design Package 100% Design Package Final Construction Closeout
Full Size Half Size Full Size Half Size As-builts / O&M
WSA ES 0 1 0 1 1 / 1
WSA PIM 0 1 0 1 0
BET ATCT 2 2 2 4 3 / 3
Design-Build Scope of Work, BET ATCT, Bethel Alaska P a g e | 10
8.2 SYSTEM TRAINING
Provide service engineer to instruct Government in operation of systems plant and equipment. Provide at least 35 hours of system training to a minimum of 3 FAA employees. The training will include a complete initial training at project closeout and 2 follow up training sessions, scheduled over a 3 month period as follows:
1. Initial Training – 3 students, 3 days, 5 hour sessions.
2. Follow Up Training #1 – 3 students, 2 days, 5 hour sessions.
3. Follow Up Training #2 – 3 students, 2 days, 5 hour sessions.
10. POINTS OF CONTACT
FAA Contracting Officer Darren Odegard, AMQ-530 206.231.3022 Darren.odegard@faa.gov FAA Project Engineer Wilson Platt, AJW-W12A 907.271.5541 wilson.platt@faa.gov
| BET ATCT SOW - JCN 1508626 & 1703818 - REV 1.pdf |
| 1. Project Overview |
| 1.1 Building Automation System (BAS) Upgrades |
| 1.2 Relocate HVAC Distribution Panel “M” |
| 2. Scope of Work |
| 3. Project Objectives |
| 4. Operational Risk Management (ORM) |
| 5. Miscellaneous |
| 5.1 Coordination/Permitting |
| 5.2 sCHEDULE |
| 5.3 Vendor REquirements |
| 4 |
| 5 |
| 5.4 Government Furnished Property |
| 6. Functional Requirements |
| 6.1 Mechanical |
| 6.2 Electrical |
| 7. Warranty |
| 8. Criteria for Design and Construction |
| 8.1. Industry Codes and Standards |
| 8.2. FAA Design Standards |
| 8.3. Occupational Safety and Health |
| 9. Deliverables |
| 8.1 Hard Copy Deliverables |
| 8.2 System Training |
10. Points Of Contact