Q.
There is a conflict between the mechanical and electrical plans. The electrical plans call out for 30 AMP circuits feeding the units. This is sufficient if the I tia have hot water reheat. Since the units are electric reheat, 30 Amps is not sufficient. Please advise what size circuit and where it shall be pulled from.
A.
The following units will not have electric reheat or HW reheat per drawing m103:
AHU 1,3,4,5,6,7,8,9,10.
Only units OAH-1(SF-1) and AHU 2 have HW reheat.