RCAG TOWER REPLACEMENT
PITTSBURGH (PIT) RCAG
JANUARY 9, 2017
Summary of the Work
1.4 WORK AT THE RCAG SITE:
• Perform the earthwork, site grading and surfacing, associated with the construction of the antenna tower foundations, cable duct and tower grounding.
• Construct two 17.5-foot x 17.5-foot x 4-foot concrete foundations.
• The work also includes the tower cabling and facility grounding system, restoration of areas during construction, and installation of appurtenances as described herein or indicated on the drawings.
• Offload and erect two (2) 80 foot FAA furnished antenna towers. The work also includes installation of PVC conduit and GFM 7/8” heliax cables from the top of the new towers to the building.
• The towers will come completely unassembled. Grounding components will not be supplied with the towers.
• After a two (2) week period in which the FAA will make the new towers operational, remove and dispose of the old towers.
• At the end of the project submit redline drawings and other items in the specifications under contract closeout.
Summary of the Work
1.5 WORK AT THE RTR SITE:
• Perform the earthwork, site grading and surfacing, associated with the construction of the antenna tower foundations, cable duct and tower grounding.
• Construct four 17.5-foot x 17.5-foot x 4-foot concrete foundations.
• The work also includes the tower cabling and facility grounding system, restoration of areas during construction, and installation of appurtenances as described herein or indicated on the drawings.
• Offload and erect four (4) 80 foot FAA furnished antenna towers. The work also includes installation of PVC conduit and GFM 1/2” heliax cables from the top of the new towers to the building.
• The towers will come completely unassembled. Grounding components will not be supplied with the towers.
• After a two (2) week period in which the FAA will make the new towers operational, remove and dispose of the old towers.
• At the end of the project submit redline drawings and other items in the specifications under contract closeout.