697DCK-24-Q-00048.pdf

PDF 289 KB Posted

Attached to
Carpet Replacement/Installation - Louisville KY
Solicitation number
697DCK-24-Q-00048
Issued by

About this file

This document is a Request for Quotations (RFQ) for a carpet replacement/installation project at the Louisville Airport Air Traffic Control Tower Base Building (SDF TRACON) in Louisville, KY for the Federal Aviation Administration (FAA).

The contractor must furnish all labor, supervision, supplies, material, tools, equipment, transportation, insurance, and engineering required for carpet replacement in the TRACON, tower, first floor hallways, and offices. The project has an estimated value under $100,000 and is set aside for small business concerns. A site visit is scheduled for April 17, 2024, and proposals are due by April 29, 2024. The period of performance is from October 1, 2023 to September 30, 2024. The FAA will make a single award, and the contractor must perform at least 25% of the work on-site using their own organization. Federal clauses, including Davis-Bacon Act labor requirements, are incorporated by reference.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

697DCK-24-Q-00048

1. REQUEST NO.

4a. ISSUED BY

NAME

a. NAME

c. STREET ADDRESS

d. CITY

9. PLEASE FURNISH QUOTATIONS TO

THE ISSUING OFFICE IN BLOCK 4a ON

OR BEFORE CLOSE OF BUSINESS (Date)

2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NO.

5. DELIVERY BY (Date)

6. DELIVERY

8. DESTINATION

a. NAME OF CONSIGNEE

b. STREET ADDRESS

PAGE OF PAGES

4b. FOR INFORMATION CALL: (No collect calls)

TELEPHONE NUMBER

AREA CODE NUMBER

7. TO:

b. COMPANY

e. STATE f. ZIP CODE

c. CITY

d. STATE e. ZIP CODE

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 4a. This request does not commit the Contract Authority to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter.

10. SCHEDULE (Include applicable Federal, State and local taxes)

THIS RFQ

REQUEST FOR QUOTATIONS

(THIS IS NOT AN ORDER)

IS IS NOT A SMALL BUSINESS SET ASIDEX

CS-24-00329

1 48

AAQ-500 - REGIONAL ACQUISITIONS

10101 HILLWOOD PARKWAY

FORT WORTH TX 76177-1524

FEDERAL AVIATION ADMINISTRATION

5 Days After Notice to Proceed

7695307F

695307 DOT FAA

SYSTEMS SUPPORT CENTER

755 GRADE LN

LOUISVILLE KY 402132600

LOUISVILLE

KY 402132600

Amber Jones

04/29/2024 1700 CD

FOB DESTINATION

OTHER

(See Schedule)X

ITEM NO.

(a)

SUPPLIES/SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e)

AMOUNT

(f)

This solicitation is competitive among small business.

NAICS Code: 238330 - Flooring Contractors

Estimated project value will be under $100,000

All submittals must be approved before issuance of Notice to Proceed.

A site visit is scheduled for 04/17/2024 at 11:00am Eastern Time.

Send attendee list with name, company, and contact information for all attendees no later than 04/16/2024 at 3:00 pm Eastern time to Continued ...

11. DISCOUNT FOR PROMPT PAYMENT

a. 10 CALENDAR DAYS (%) b. 20 CALENDAR DAYS (%) c. 30 CALENDAR DAYS (%) d. CALENDAR DAYS

NUMBER PERCENTAGE

NOTE: Additional provisions and representations

12. NAME AND ADDRESS OF QUOTER

b. STREET ADDRESS

c. COUNTY

d. CITY e. STATE f. ZIP CODE

13. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

16. SIGNER

a. NAME (Type or print)

c. TITLE (Type or print)

a. NAME OF QUOTER

AREA CODE

NUMBER

14. DATE OF QUOTATION

b. TELEPHONE are are not attached

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 48 CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

697DCK-24-Q-00048

David.A.Smith@faa.gov & CC'Amber.N.Jones@faa.gov.

All questions regarding this SIR should be submitted in writing to Amber.N.Jones@faa.gov are due by 04/18/2024 12:00 PM Central Time

Proposals are due to Amber.N.Jones@faa.gov by

04/29/2024 5:00 PM Central Time

00001 Contractor shall furnish all labor, supervision, supplies, material, tools, equipment, transportation, insurance, and any engineering required for carpet replacement in the TRACON, tower, first floor hallways, and offices at

Louisville ATCT in accordance with the attached

Scope of Work (A).

Proposed Price: $ ______________________

Electronic & IT: 03

Delivery: 5 Days After Notice to Proceed

Period of Performance: 10/01/2023 to 09/30/2024

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Section B - Supplies or Services/Prices

SA24 PRICES/COSTS FOR CONSTRUCTION

Furnish all labor, materials, equipment, transportation, insurance, notifications, licenses, permits, fees and supervision necessary for the CARPET REPLACEMENT PROJECT LOUISVILLE TRACON in accordance with the specifications, drawings, contract clauses, and wage rates.

The offered price shall encompass all costs related to (a) direct and indirect labor, fringe benefits, overhead, G&A expenses, profit, material, equipment, other direct costs, insurance, freight, handling, transportation, inspection, testing, operation and maintenance manuals, bonds, etc., (b) federal, state, and local taxes, (c) all applicable fees permits, licenses, and (d) any miscellaneous charges.

An offeror is required to provide a price for each contract line item (CLIN). Failure to comply may result in the rejection of the subject offer. A single award shall be made. There shall be no split award. In the event that the CLIN price for any line item is materially unbalanced, the entire offer may be rejected without discussion with the offeror.

In the event of any disparity between the CLIN price and the total offered price, the CLIN price shall be deemed correct, and the total offered amount shall be revised accordingly, unless available information indicates otherwise.

Effective April 1, 1996, the Federal Aviation Administration (FAA) began operating under the new FAA Acquisition Management System. The l996 DOT Appropriation Act, Public Law 104-50, mandated that the FAA rewrite its acquisition regulations and granted legislative relief from certain laws. The Federal Acquisition Regulations (FAR), Federal Acquisition Streamlining Act of 1994, Small Business Act, and Competition in Contracting Act, are three of these laws.

(End of Clause)

Section C - Description/Specifications General Scope of Work: Carpet Replacement/Installation.

“Contractor must provide all labor, material, transportation, and supervision to Replace/Install Carpet at the Louisville Airport Air Traffic Control Tower Base Building, in Louisville, KY, in accordance with the Specifications attached in Section J.”

Section D - Packaging and Marking Packaging: All equipment units, supplies, materials, to be delivered at the project site must be clearly marked and addressed to the Contracting Officer Representative (COR). When possible, the FAA will assign a secured storage area for any deliveries that may take place before the project starts.

Marking: All designated storage and work areas must be properly marked to avoid unintended access and/or accidents. Contractor and sub-contractors must follow OSHA guidelines to avoid safety hazards accordingly.

Section E - Inspection and Acceptance

3.1-1 CLAUSES AND PROVISIONS INCORPORATED BY REFERENCE (JUL 2019)

This screening information request (SIR) or contract, as applicable, incorporates by reference the provisions or clauses listed below with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make the full text available, or offerors and contractors may obtain the full text via Internet at:

https://fast.faa.gov/contractclauses.cfm.

(End of clause)

3.10.4-1 CONTRACTOR INSPECTION REQUIREMENTS (APR 1996)

3.10.4-10 INSPECTION OF CONSTRUCTION (SEP 2009)

3.10.4-11 INSPECTION - DISMANTLING, DEMOLITION, OR REMOVAL OF IMPROVEMENTS

(APR 1996)

Section F - Deliveries or Performance

3.1-1 CLAUSES AND PROVISIONS INCORPORATED BY REFERENCE (JUL 2019)

This screening information request (SIR) or contract, as applicable, incorporates by reference the provisions or clauses listed below with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make the full text available, or offerors and contractors may obtain the full text via Internet at:

https://fast.faa.gov/contractclauses.cfm.

(End of clause)

3.10.1-24 NOTICE OF DELAY (MAR 2009)

SA13 HOLIDAYS

The following Federal holidays are observed by the Federal Aviation Administration.

New Year's Day January 1st

Martin Luther King's Birthday Third Monday in January

Presidents Day Third Monday in February

Memorial Day Last Monday in May

Juneteenth Day June 19th

Independence Day July 4th

Labor Day First Monday in September

Columbus Day Second Monday in October

Veterans Day November 11th

Thanksgiving Day Fourth Thursday in November

Christmas Day December 25th

SA35 FAA HOLIDAY MORATORIUM

No work shall be scheduled or take place during the week of and the weekend preceding the following holidays:

Thanksgiving, Christmas and New Year's Day. Only emergency work to restore critical services to the facility will be considered and a moratorium waiver must be submitted and approved. The moratorium period will not be counted against the contract construction duration for the project.

Section G - Contract Administration Data

3.10.1-23 CONTRACTING OFFICER'S REPRESENTATIVE-CONSTRUCTION CONTRACTS (APR

2012)

(a) The Contracting Officer may appoint other Government personnel to accomplish certain contract administration matters. While there shall be various titles and divisions of duties for these individuals, generically they are known as Contracting Officer's Representatives (CORs). The Contracting Officer will provide written notice of COR appointment(s), setting forth the authorities and limitations, to the Contractor within 3 calendar days prior to the notice to proceed. COR duties may include, but are not limited to:

(1) Perform as the authorized representative of the Contracting Officer for technical matters, including interpretation of specifications and drawings, and inspection and review of work performed.

(2) Perform as the authorized representative of the Contracting Officer for administrative matters, including reviewing payments, and updated delivery schedules.

(b) These representatives are authorized to act for the Contracting Officer in all specifically delegated matters pertaining to the contract, except:

(1) contract modifications that change the contract price or cost, technical requirements or time for performance, unless delegated field change order authority;

(2) suspension or termination of the Contractor's right to proceed, either for default or for convenience;

(3) final decisions on any matters subject to appeal, e.g., disputes under the "Contract Disputes" clause; and

(4) final acceptance under the contract.

(End of clause)

SA14 AUTHORITY OF THE GOVERNMENT

No one other than the Contracting Officer has the authority to authorize or make changes in the terms, conditions, change the scope of work or specifications in the contract, make any commitments or otherwise obligate the Government, or authorize any changes which affect the contract price, delivery schedule, period of performance, or other terms and conditions of the contract.

SA36 CORRESPONDENCE

The contracting officer prefers to receive written communication and documents electronically via email at Amber.N.Jones@FAA.GOV. All email correspondence to the FAA must state the contract number in the 'Subject' field. Electronic documents must be accompanied by an explanatory email and should be sent in a portable-document-format type file (file extension pdf), such as Adobe Acrobat. Vendors are required to ensure that the quality of the administrative content in electronic files represents a reasonably high business standard. The Government is not responsible for the administrative ordering or legibility of correspondence received electronically. Emailed files/documents may not be in a zipped format. If electronic file sizes (i.e., typically expressed as kilobytes or megabytes) are too large for email attachments, recommend delivery in compact disk (CD) format submitted via hard-copy mail. Any CD mailing or printed-paper, hard-copy correspondence will be sent to the contracting officer at the following address.

Amber.N.Jones@FAA.GOV.

Section H - Special Contract Requirements

3.1.9-1 ELECTRONIC COMMERCE AND SIGNATURE (JUL 2020)

(a) The Electronic Signatures in Global and National Commerce Act (E-SIGN) establishes a legal equivalence between:

(1) Contracts written on paper and contracts in electronic form;

(2) Pen-and-ink signatures and electronic signatures; and

(3) Other legally-required written records and the same information in electronic form.

(b) With the submission of an offer, the offeror acknowledges and accepts the utilization of electronic commerce as part of the requirements of this solicitation and the resultant contract.

(c) Certain documents may need to be provided or maintained in original form, such as large-scale drawings impractical to convert to electronic format or a document with a raised seal signifying authenticity. This clause does not change or affect any other requirements that a document must be in paper format to satisfy legal requirements such as for certain real estate transactions.

(d) The use of electronic signature technology is authorized under this solicitation and the resulting contract.

(e) Contractors must not digitally sign any documents with software that uses the Secure Hash Algorithm 1 (SHA- 1). All digitally signed documents and contracts sent to the FAA must use a SHA-256 or higher hash algorithm. This is based on the National Institute of Standards and Technology (NIST) Policy Statement on Hash Functions dated August 5, 2015. Further guidance on the use of SHA-256 is in NIST Special Publication (SP) 800-57 Part 1, section

5.6.2 as amended and SP 800-131A, Revision 1 dated November 6, 2015. Additional guidance on the use of SHA-3 is in NIST SP 800-185 as amended.

(f) Contractors do not have to update documents previously digitally signed using SHA-1 hash algorithms unless the document requires updating. The FAA and contractors may continue to use SHA-1 for the following applications:

Verifying old digital signatures and time stamps, generating and verifying hash-based message authentication codes (HMACs), key derivation functions (KDFs), and random bit/number generation.

(End of Clause)

SA15 INSURANCE REQUIREMENTS SCHEDULE

"(See Section I, Clause 3.4.1-10, Insurance--Work on Federal Aviation Administration Installation)

During the term of the contract, the Contractor and each subcontractor shall at their own expense, purchase and maintain the following minimum insurance requirements in companies properly licensed and satisfactory to the Contracting Officer:

Automobile and Truck Liability

$200,000 - bodily injury per person, not to exceed $500,000 per occurrence.

$100,000 - property damage per occurrence.

Comprehensive General Liability

$500,000 - Combined bodily injury and property damage per occurrence.

Workmen's Compensation

$100,000 or statutory, whichever is greater.

Umbrella or Excess Liability

$1,000,000 combined single limits bodily injury and property damage.

Insurance certificates shall contain a provision that coverages afforded under the policies will not be canceled until at least 30 days prior written notice has been given to the Contracting Officer at the following address:

Federal Aviation Administration

ATTN: David Bustamante Contracting Officer, AAQ- 5A0 david.t.bustamante@faa.gov

EMAIL ONLY

It is agreed that the Federal Aviation Administration, the property owner(s) and their representatives will be held harmless by the Contractor for any loss or damage to sheds, tools, equipment, property and materials of the Contractor, and his subcontractors, their servants and employees, it being understood that the Contractor may at his expense carry any insurance which may be required to provide the necessary protection against such loss or damage.

The Contractor shall not commence work under the contract until he has obtained all the insurance required hereunder and such insurance has been approved by the Contracting Officer. Approval of the insurance by the Contracting Officer shall not relieve or decrease the liability of the Contractor.

The policy shall name "The United States of America, acting by and thought the Federal Aviation Administration" as an additional insured with respect to operations performed under this contract.

Section I - Contract Clauses

3.1-1 CLAUSES AND PROVISIONS INCORPORATED BY REFERENCE (JUL 2019)

This screening information request (SIR) or contract, as applicable, incorporates by reference the provisions or clauses listed below with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make the full text available, or offerors and contractors may obtain the full text via Internet at:

https://fast.faa.gov/contractclauses.cfm.

(End of clause)

3.1.7-2 ORGANIZATIONAL CONFLICTS OF INTEREST (JAN 2023)

3.2.2.3-33 ORDER OF PRECEDENCE (MAR 2009)

3.2.2.3-41 PERFORMING WORK (JUL 2004)

The Contractor (you) must perform, using your own organization, work equivalent to at least 25 percent of the total amount of work under the contract on the site. The CO may modify this contract to reduce this percentage if you request a reduction and the CO determines that it would be to the Government's advantage to do so.

(End of clause)

3.2.2.3-42 DIFFERING SITE CONDITIONS (JUL 2004)

3.2.2.3-43 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (JUL 2004)

3.2.2.3-45 MATERIAL AND WORKMANSHIP (JUL 2004)

3.2.2.3-46 SUPERVISING THE CONTRACT WORK (JUL 2004)

3.2.2.3-47 PERMITS AND RESPONSIBILITIES (JUL 2004)

3.2.2.3-48 OTHER CONTRACTS (MAR 2009)

3.2.2.3-49 PROTECTING EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES,

AND IMPROVEMENTS (JUL 2004)

3.2.2.3-50 PROPERTY PROTECTION (OCT 2014)

3.2.2.3-51 OPERATIONS AND STORAGE AREAS (APR 2012)

3.2.2.3-53 CLEANING UP AND ROADWAY MAINTENANCE (JUL 2004)

3.2.2.3-54 PREVENTING ACCIDENTS (JUL 2004)

3.2.2.3-55 AVAILABILITY AND USE OF UTILITY SERVICES (JUL 2004)

3.2.2.3-58 LAYOUT OF WORK (MAR 2009)

3.2.2.3-60 SPECIFICATIONS, DRAWINGS, AND MATERIAL OFFERS (MAR 2009)

3.2.2.3-62 PRECONSTRUCTION CONFERENCE (JUL 2004)

3.2.2.3-64 DISMANTLING AND DEMOLISHING OF PROPERTY (JUL 2004)

3.2.2.3-67 SPECIAL PRECAUTIONS FOR WORK AT OPERATING AIRPORTS (APR 2022)

3.2.2.3-68 SAFETY AND HEALTH (OCT 2014)

3.2.2.3-69 SUBCONTRACTS - CONSTRUCTION (JUL 2004)

3.2.2.3-71 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (OCT 2021)

3.2.2.3-83 PROHIBITION AGAINST CONTRACTING WITH INVERTED DOMESTIC

CORPORATIONS (OCT 2015)

3.2.2.7-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH

CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT (APR 2023)

3.2.2.7-8 DISCLOSURE OF TEAM ARRANGEMENTS (APR 2008)

3.2.5-1 OFFICIALS NOT TO BENEFIT (APR 2021)

3.2.5-3 GRATUITIES OR GIFTS (OCT 2019)

3.2.5-4 CONTINGENT FEES (OCT 1996)

3.2.5-5 ANTI-KICKBACK PROCEDURES (OCT 2019)

3.2.5-8 WHISTLEBLOWER PROTECTION FOR CONTRACTOR EMPLOYEES (APR 1996)

3.3.1-2 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (JUL 2018)

3.3.1-9 INTEREST (APR 2023)

3.3.1-15 ASSIGNMENT OF CLAIMS (JUL 2018)

3.3.1-19 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2021)

3.3.1-20 PROVIDING ACCELERATED PAYMENT TO SMALL BUSINESS SUBCONTRACTORS

(OCT 2012)

3.3.1-33 SYSTEM FOR AWARD MANAGEMENT (JAN 2024)

(a) Definitions. As used in this clause

"Registered in the SAM database" means that the Contractor has entered all mandatory information, including the Unique Identity Identifier (UEI) or the Electronic Funds Transfer indicator, into the SAM database.

"System for Award Management (SAM) database" means the primary Government repository for Contractor information required for the conduct of business with the Government.

"Unique Entity Identifier (UEI)" (also known as the Unique Entity ID) means a number or other identifier used to identify a specific commercial, nonprofit, or Government entity. See www.sam.gov for the designated entity for establishing unique entity identifiers.

"Electronic Funds Transfer indicator" means a 4-character suffix to the Unique Entity Identifier. This 4-character suffix may be assigned at the discretion of the business concern to establish additional SAM records for identifying alternative Electronic Funds Transfer (EFT) accounts for the same parent concern.

(b)(1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee must be registered in the SAM database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.

(2) The offeror must enter, in Representations, Certifications and Other Statements of Offerors Section of the solicitation, the UEI or EFT indicator that identifies the offeror's name and address exactly as stated in the offer. The UEI will be used by the Contracting Officer to verify that the offeror is registered in the SAM database.

(c) If the offeror does not have a UEI, it should contact www.sam.gov directly to obtain one.

The offeror should be prepared to provide the following information:

(1) Company legal business name.

(2) Tradestyle, doing business, or other name by which your entity is commonly recognized.

(3) Company Physical Street Address, City, State, and ZIP Code.

(4) Company Mailing Address, City, State and ZIP Code (if different from physical street address).

(5) Company Telephone Number.

(6) Date the company was started.

(7) Number of employees at your location.

(8) Chief executive officer/key manager.

(9) Line of business (industry).

(10) Company Headquarters name and address (reporting relationship within your entity).

(d) If the offeror does not become registered in the SAM database in the time prescribed by the Contracting Officer, the Contracting Officer may proceed to award to the next otherwise successful registered offeror.

(e) Processing time should be taken into consideration when registering. Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.

(f) The Contractor is responsible for the accuracy and completeness of the data within the SAM database, and for any liability resulting from the Government's reliance on inaccurate or incomplete data. To remain registered in the SAM database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the SAM database to ensure it is current, accurate and complete. Updating information in SAM does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document. If registered in SAM as a Service-Disabled Veteran- Owned Small Business (SDVOSB), by submission of an offer, the offeror acknowledges that they are certified as an SDVOSB under the Small Business Administration's Veteran Small Business Certification Program (VetCert).

(g)(1)(i) If a Contractor has legally changed its business name, "doing business as" name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in AMS Procurement Guidance, the Contractor must provide the responsible Contracting Officer a minimum of one business day's written notification of its intention to:

(A) Change the name in the SAM database;

(B) Comply with the requirements of AMS regarding novation and change-of-name agreements; and

(C) Agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide the Contracting Officer with the notification, sufficient documentation to support the legally changed name.

(ii) If the Contractor fails to comply with the requirements of paragraph (g)(1)(i) of this clause, or fails to perform the agreement at paragraph (g)(1)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the SAM information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the "Suspension of Payment" paragraph of the electronic funds transfer (EFT) clause of this contract.

(2) The Contractor must not change the name or address for EFT payments or manual payments, as appropriate, in the SAM record to reflect an assignee for the purpose of assignment of claims. Assignees must be separately registered in the SAM database. Information provided to the Contractor's SAM record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the "Suspension of payment" paragraph of the EFT clause of this contract.

(h) Offerors and Contractors may obtain information on registration and annual confirmation requirements via the internet at http://www.sam.gov.

(End of Clause)

3.3.1-34 PAYMENT BY ELECTRONIC FUNDS TRANSFER- SYSTEM FOR AWARD

MANAGEMENT (JUL 2018)

3.3.1-40 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (APR 2022)

3.3.2-1 FAA COST PRINCIPLES (OCT 2019)

(a) Federal Aviation Administration (FAA) "Contract Cost Principles" must be used for:

(1) The pricing of contracts, subcontracts, and modifications to contracts and subcontracts whenever cost analysis is performed; and

(2) The determination, negotiation, or allowance of costs when required by a contract clause.

(b) The Contracting Officer will incorporate the FAA cost principles and procedures in contracts with commercial organizations as the basis for:

(1) Determining reimbursable costs under

(i) Cost-reimbursement contracts and cost-reimbursement subcontracts under these contracts performed by commercial organizations and

(ii) The cost-reimbursement portion of time-and-materials contracts except when material is priced on a basis other than at cost;

(2) Negotiating indirect cost rates, when:

(i) FAA has division or corporate contract administration responsibilities;

(ii) Quick Close-out procedures are used; or

(iii) Indirect rate caps are negotiated in the contract.

(3) Proposing, negotiating, or determining costs under terminated contracts;

(4) Price revision of fixed-price incentive contracts;

(5) Price redetermination of price redetermination contracts; and

(6) Pricing changes and other contract modifications.

(c) When division or corporate contract administration responsibilities rest with another Government agency, the FAA will apply the cost principles of the administering agency for the determination or negotiation of indirect rates not covered by (2)(ii) or (2)(iii) above.

(d) Upon request, the Contracting Officer will provide a copy of the FAA "Contract Cost Principles."

(End of clause)

3.4.1-7 NOTICE TO PROCEED (OCT 2019)

3.4.1-10 INSURANCE - WORK ON A GOVERNMENT INSTALLATION (OCT 2020)

3.4.2-6 TAXES - CONTRACTS PERFORMED IN U.S. POSSESSIONS OR PUERTO RICO (OCT

1996)

3.4.2-8 FEDERAL, STATE, AND LOCAL TAXES - FIXED PRICE CONTRACT (JUL 2019)

3.5-1 AUTHORIZATION AND CONSENT (APR 2023)

3.5-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT

(JAN 2009)

3.5-4 PATENT INDEMNITY - CONSTRUCTION CONTRACTS (JAN 2009)

3.6.1-1 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (OCT 2019)

(a) Definition. Small business concern, as used in this clause, means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the North American Industry Classification System (NAICS) standards in this Screening Information Request (SIR) at the time of submission of offer.

(b) General.

(1) Information and/or offers are requested only from small business concerns. Information and/or offers received from concerns that are not small business concerns will be considered nonresponsive and will be rejected.

(2) Any award resulting from this SIR will be made to a small business concern.

(c) Agreement. A manufacturer or regular dealer submitting information and/or an offer in its own name agrees to furnish, in performing the contract, only end items manufactured or produced by small business concerns in the United States or its outlying areas. However, this requirement does not apply in connection with construction or service contracts.

(End of clause)

3.6.1-15 POST-AWARD SMALL BUSINESS PROGRAM RE-REPRESENTATION (JUL 2023)

3.6.2-2 CONVICT LABOR (APR 1996)

3.6.2-9 EQUAL OPPORTUNITY (JUL 2023)

3.6.2-16 NOTICE TO THE GOVERNMENT OF LABOR DISPUTES (OCT 2018)

3.6.2-18 DAVIS BACON ACT (JUL 2023)

3.6.2-19 WITHHOLDING-LABOR VIOLATIONS (JUL 2023)

3.6.2-20 PAYROLLS AND BASIC RECORDS (JUL 2023)

3.6.2-21 APPRENTICES, TRAINEES, AND HELPERS (JUL 2023)

3.6.2-22 SUBCONTRACTS (LABOR STANDARDS) (JUL 2023)

3.6.2-23 CERTIFICATION OF ELIGIBILITY (JUL 2023)

3.6.2-24 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION (JUL

2023)

3.6.2-35 PREVENTION OF SEXUAL HARASSMENT (JUL 2023)

3.6.2-39 TRAFFICKING IN PERSONS (JUL 2023)

3.6.2-44 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS

ACT (JUL 2023)

3.6.2-46 PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 (JUL 2023)

3.6.2-47 MINIMUM WAGES FOR CONTRACTOR WORKERS UNDER EXECUTIVE ORDER 14026

(JUL 2023)

3.6.3-3 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA (OCT

2016)

(a) Hazardous material, as used in this clause, includes any material defined as hazardous under the latest version of Federal Standard No. 313 (including revisions adopted during the term of the contract).

(b) The offeror must list any hazardous material, as defined in paragraph (a) of this clause, to be delivered under this contract. The hazardous material shall be properly identified and include any applicable identification number, such as National Stock Number or Special Item Number. This information shall also be included on the Safety Data Sheet submitted under this contract.

Material (If none, insert None): __________________________________ Identification No.: __________________________________

(c) The apparently successful offeror, by acceptance of the contract, certifies that the list in paragraph (b) of this clause is complete. This list must be updated during performance of the contract whenever the Contractor determines that any other material to be delivered under this contract is hazardous.

(d) The apparently successful offeror agrees to submit, for each item as required prior to award, a Safety Data Sheet, meeting the requirements of 29 CFR 1910.1200(g) and the latest version of Federal Standard No. 313, for all hazardous material identified in paragraph (b) of this clause. Data shall be submitted in accordance with Federal Standard No. 313, whether or not the apparently successful offeror is the actual manufacturer of these items. Failure to submit the Safety Data Sheet prior to award may result in the apparently successful offeror being considered non-responsible and ineligible for award.

(e) If, after award, there is a change in the composition of the item(s) or a revision to Federal Standard No. 313, which renders incomplete or inaccurate the data submitted under paragraph (d) of this clause or the certification submitted under paragraph (c) of this clause, the Contractor shall promptly notify the Contracting Officer (CO) and resubmit the data.

(f) Neither the requirements of this clause nor any act or failure to act by the Government shall relieve the Contractor of any responsibility or liability for the safety of Government, Contractor, or subcontractor personnel or property.

(g) Nothing contained in this clause shall relieve the Contractor from complying with applicable Federal, State, and local laws, codes, ordinances, and regulations (including the obtaining of licenses and permits) in connection with hazardous material.

(h) The Government's rights in data furnished under this contract with respect to hazardous material are as follows:

(1) To use, duplicate and disclose any data to which this clause is applicable. The purposes of this right are to:

(i) Apprise personnel of the hazards to which they may be exposed in using, handling, packaging, transporting, or disposing of hazardous materials;

(ii) Obtain medical treatment for those affected by the material;

(iii) Have others use, duplicate, and disclose the data for the Government for these purposes.

(2) To use, duplicate, and disclose data furnished under this clause, in accordance with subparagraph (h)(1) of this clause, in precedence over any other clause of this contract providing for rights in data.

(3) The Government is not precluded from using similar or identical data acquired from other sources.

(i) Except as provided in paragraph (i)(2) the Contractor shall prepare and submit a sufficient number of Safety Data Sheets, meeting the requirements of 29 CFR 1910.1200(g) and the latest version of Federal Standard No. 313, for all hazardous materials identified in paragraph (b) of this clause.

(1) For items shipped to consignees, the Contractor shall include a copy of the Safety Data Sheets with the packing list or other suitable shipping document which accompanies each shipment. Alternatively, the Contractor is permitted to transmit Safety Data Sheets to consignees in advance of receipt of shipments by consignees, if authorized in writing by the CO.

(2) For items shipped to consignees identified by mailing address as agency depots, distribution centers or customer supply centers, the Contractor shall provide one copy of the Safety Data Sheets in or on each shipping container. If affixed to the outside of each container, the Safety Data Sheets must be placed in a weather resistant envelope.

(End of clause)

3.6.3-9 OZONE DEPLETING SUBSTANCES AND HIGH GLOBAL WARMING POTENTIAL

HYDROFLUOROCARBONS (OCT 2016)

3.6.3-12 ASBESTOS - FREE CONSTRUCTION (APR 2017)

(a) In performing this contract, the Contractor must not use asbestos or asbestos-containing building materials during construction, renovation, and/or modernization of this facility.

(b) The Contractor must provide to the Contracting Officer (CO) a signed statement WITH FINAL INOVICE indicating that no asbestos or asbestos-containing building materials were used during construction, renovation, and/or modernization of this facility. The Contractor's certification under this clause is considered to be a material requirement of the contract and the FAA may withhold payment pending submittal and receipt of an acceptable certification.

(c) The FAA retains the right to conduct sampling of contractor building materials used during construction, renovation, and/or modernization of this facility to verify that they are asbestos-free. If asbestos-containing material is found, the Contractor must bear the expense of the sampling conducted by the FAA, remove and replace the asbestos-containing material and decontaminate the site of asbestos contamination caused by the Contractor at no additional cost to the Government. In addition, the Contractor must bear the expense of all testing (bulk sampling and air sampling conducted by the contactor and the FAA) to determine that the asbestos removal and site decontamination are satisfactorily completed. The Contractor must follow all applicable federal, state, and local asbestos regulatory requirements as well as applicable FAA Orders with respect to asbestos abatement when the Contractor is required to remove asbestos materials they have installed.

(End of clause)

3.6.3-13 AFFIRMATIVE PROCUREMENT OF RECYCLED CONTENT AND PRODUCTS UNDER

SERVICE AND CONSTRUCTION CONTRACTS (JAN 2020)

3.6.3-14 USE OF ENVIRONMENTALLY PREFERABLE PRODUCTS (JAN 2020)

3.6.3-22 CONSTRUCTION WASTE MANAGEMENT (JUL 2023)

(a) In performance of this contract, the Contractor must establish a program to minimize waste generation, as well as recycle, reuse, and salvage construction and demolition (C&D) debris generated to the maximum extent possible.

Before commencing work, the Contractor must submit a Waste Management Plan to the Contracting Officer within 15 days after contract award prior to the start of construction activities. This plan must address the following:

(1) General: Provide an overall strategy for managing C&D debris associated with the project.

(2) Waste Identification: Indicate anticipated types and quantities by weight of demolition, site-clearing and construction waste generated by the Project. Include estimated quantities by weight and assumptions for estimates.

A site assessment may be necessary to estimate the types of materials that will be generated during construction and/or demolition. If a site visit is needed, the Contractor must notify the FAA of this as soon as possible, with the FAA arranging in turn for the contractor site visit to take place as soon as possible.

(3) Waste Reduction Work Plan: List each type of waste and whether it will be salvaged, recycled, or disposed of in landfill or incinerator. Include points of waste generation, estimated total weight of each type of waste, final disposition for each waste type, and handling and transportation procedures.

(4) Salvaged Materials: For each type of material that is salvaged or recycled, describe the type of material, source, estimated quantity, and receiving entity. Include names, addresses, and telephone numbers for the receiving individuals and/or organizations.

(5) Disposed Materials: Indicate how and where materials will be disposed of. Include name, address, and telephone number of each landfill and incinerator facility.

(6) Handling and Transportation Procedures: Include method that will be used for separating recyclable waste including sizes of containers, container labeling, and designated location on Project site where materials separation will be located.

(b) This plan must be found acceptable by the FAA Contracting Officer's Representative (COR) or the COR's designated representative prior to the Contractor receiving a Notice-to-Proceed. The plan's acceptability will be promptly determined by the FAA based on the knowledge of the site(s) covered under the Plan. The Contract must implement the approved Waste Management Plan during the term of the contract.

(c) The Contractor must document all C&D disposal and diversion efforts and submit a Construction and Demolition Debris Diversion Report to the CO and COR monthly. A copy of the report must also be submitted to the EOSH Services construction waste management address at 9-AJW-ConstructionWaste@faa.gov.

The monthly Construction and Demolition Debris Diversion Report must contain the following information:

(1) FAA facility name and address, report date and reporting period, contract number, and project name;

(2) Pick up date;

(3) Waste material type;

(4) Disposed C&D waste weight in short tons less container weight, method of waste material disposal, and reason why waste was not diverted;

(5) Recycled waste weight in short tons less container weight;

(6) Composted waste (off-site) weight in short tons less container weight;

(7) Reused materials weight in short tons less container weight; and

(8) Total weight of C&D waste (i.e., sum of disposed, recycled, composted, and reused waste) in short tons less container weight.

The Contractor must ensure that facilities used for recycling, reuse, and disposal are authorized for the intended use to the required extent by federal, state, and local regulations.

(d) If the value of this contract when awarded is less than $250,000, this clause does not take effect in this contract.

(End of Clause)

3.6.3-23 DELIVERY OF ELECTRONIC AND PAPER DOCUMENTS (JAN 2020)

3.6.3-24 ASBESTOS NESHAP COMPLIANCE (OCT 2015)

3.6.3-25 AEROSOLS (OCT 2016)

3.6.4-3 BUY AMERICAN ACT - CONSTRUCTION MATERIALS (JAN 2024)

(a)Definitions

(1)"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

(2)"Cost of components" means-

(i) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(ii) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (i) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

(3) "Domestic Construction Material" means---

(i) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(A) An unmanufactured construction material mined or produced in the United States; or

(B) A construction material manufactured in the United States, if-

(aa)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029.

Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic.

Components of unknown origin are treated as foreign; or

(bb) The construction material is a COTS item, or

(ii) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

(4) "Fastener" means a hardware device that mechanically joins or affixes two or more objects together.

Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

(5) "Foreign construction material" means construction material other than domestic construction material.

(6) "Foreign iron or steel" means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

(7) "Predominantly of iron or steel or a combination of both" means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

(8) "Steel" means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

(b) Domestic Preference

(1) This clause implements 41 U.S.C.83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. The Contractor must use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

[Contracting Officer to list applicable excepted materials or indicate "none"]

(3) The Contracting Officer may add other foreign construction material to the list in (b)(2) of this clause if the Government determines that -

(i)The cost of domestic construction material would be unreasonable.

(A)The cost of particular domestic construction material subject to the requirements of the Buy American Statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent.

(B) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A) of this clause.

(C) The procedures in paragraph (b)(3)(i)(B) of the clause will no longer apply as of January 1, 2030.

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for Determination of Inapplicability of the Buy American Statute

(1)Any Contractor request to use foreign construction material in accordance with paragraph (b) (3) of this clause must include adequate information for Government evaluation of the request, including-

(i) A description of the foreign and domestic construction materials;

(ii) Unit of measure;

(iii) Quantity;

(iv) Price;

(v) Time of delivery or availability;

(vi) Location of the construction project;

(vii) Name and address of the proposed supplier; and

(viii) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(2) A request based on unreasonable cost must include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(3) The price of construction material must include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(4) Any Contractor request for a determination submitted after contract award must explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(5) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting

Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(6) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor must include the following information and any applicable supporting data based on the survey of suppliers:

FOREIGN AND DOMESTIC MATERIAL PRICE COMPARISON

Construction Material Description Unit of Measure Quantity Price (dollars)*

Foreign construction material [ ] [ ] [ ] Item 1:

Domestic Construction material [ ] [ ] [ ] Foreign construction material [ ] [ ] [ ]

Item 2:

Domestic Construction material [ ] [ ] [ ]

(List name, address, phone number, and contact for supplier surveyed. Attach copy of response, if oral, attach summary)

*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).

(e)Non-Availability Determination Waiver Approvals - In accordance with AMS Guidance T3.6.4A.4.c (3) (b), if the construction material is not being mined, produced, or manufactured in the U.S. in sufficient and reasonably available commercial quantities or of a satisfactory quality, the use of the proposed foreign construction material must also be approved by the FAA Acquisition Executive (FAE) and reviewed by the Office of Management and Budget (OMB) Made in America Office (MIAO). If a contractor is requesting a determination on this basis, the following additional information must be submitted in support of such a request:

(1) Country(ies) of origin and U.S. content (if any), of foreign end item or materials intended for purchase, if known;

(2) The estimated value of the procurement (or portion of the procurement) covered by the waiver; and

(3) As part of the justification provided under (c) (1) (viii) above, fully describe the market research activities and methods used to identify domestically manufactured items or materials capable of satisfying the requirement, including the timing of the research and conclusions reached on the availability of sources .

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .