This document contains a draft CLIN structure for geotechnical surveying services in Douglas, Arizona. The solicitation is being conducted by the Department of Transportation Federal Aviation Administration Franchise Acquisition Services under number 6973GH-24-R-00014.
The CLIN structure includes line items for technical design and pre-project planning, cone penetration testing, optional tasks for cased borehole drilling, lined large borehole drilling, technology support services, and change management contingency. Mobilization and demobilization costs are included in sub-CLINs for the applicable drilling tasks. Unit prices are to be provided by respondents. The services are to be performed in accordance with the statement of work, with tasks including those outlined in sections 2.1 through 2.3.5 of the SOW.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 16 Attachment 1 Statement of Work Rev 1.pdf | ||
| 16 Attachment 2 Schedule B Rev 1.docx | DOCX document | |
| 16 6973GH-24-R-00014-0001.pdf | ||
| 16 Attachment 6 Past Experience Form.docx | DOCX document | |
| 16 Attachment 3 Contractor Release Form.doc | DOC document | |
| 16 Attachment 1 Statement of Work.pdf | ||
| 16 Attachment 5 Performance Bond.pdf | ||
| 16 6973GH-24-R-00014.pdf | ||
| 16 Attachment 7 Wage Determination.pdf | ||
| 16 Attachment 4 Payment Bond.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Draft CLIN structure for Douglas, AZ Drilling Effort
| Estimated | |||||
| Item | Description | Quantity | Unit | Unit Price | Total Price |
| 00001 | 00001 Technical Design and Pre-Project Planning | 1 | Lot | $___________ | $_____________ |
| IAW SOW 2.1 |
| 00002 | 00002 Cone Penetration Testing | 10 | Each | $___________ | $_____________ |
| IAW SOW 2.2 |
| 00003 | Sub-CLIN 00002a | ||||
| Mobilization / Demobilization for CLIN 00002 | 1 | Lot | $___________ | $_____________ |
| 00004 | 00003 Optional Task 1: Cased Borehole Drilling | 1 | Lot | $___________ | $_____________ |
| IAW SOW 2.3.1 |
| 00005 | Sub-CLIN 00003a | ||||
| Mobilization / Demobilization for CLIN 00003 | 1 | Lot | $___________ | $_____________ |
| 00006 | 00004 Optional Task 2: Cased Borehole Drilling | 1 | Lot | $___________ | $_____________ |
| IAW SOW 2.3.2 |
00007 If Option 1 (CLIN 00003) is Exercised, No Additional Mobilization / Demobilization is Necessary for this Option
| 00008 | 00005 Optional Task 3: Lined Large Borehole Drilling | 1 | Each | $___________ | $_____________ |
| IAW SOW 2.3.3 |
| 00009 | Sub-CLIN 00005a | ||||
| Mobilization / Demobilization for CLIN 00005 | 1 | Lot | $___________ | $_____________ |
| 00010 | 00006 Optional Task 4: Technology Support Services | 6 | Days | $___________ | $_____________ |
| IAW SOW 2.3.4 |
Sub-CLIN 00006a Mobilization / Demobilization for CLIN 00006 1 Lot $___________ $_____________
| 00011 | 00007 Optional Task 5: Change Management Contingency1 | Lot | $___________ | $_____________ |
| IAW SOW 2.3.5 |