FINAL WICHITA FALLS ENGINEERING PACKAGE.pdf

PDF 15 MB Posted

Attached to
SCREENING INFORMATION REQUEST/REQUEST FOR OFFER Shelter Repair and Tower Installation Wichita Falls, Texas
Solicitation number
6973GH-19-R-00270
Issued by

About this file

This solicitation announcement is for a firm-fixed-price construction contract to perform shelter repair and tower installation work in Wichita Falls, Texas. The work includes repairing an existing shelter and installing five 40-foot self-supporting antenna towers. The Federal Aviation Administration is the contracting agency. Interested contractors must be registered in the System for Award Management by November 13, 2019 to be eligible. Questions about the project specifications, plans, or solicitation are due by November 6 to allow responses prior to the proposal submission deadline. Proposals must be received by January 13, 2020. The selected contractor will be required to provide all labor, materials, and equipment to complete the shelter repair and tower installation work as described in the statement of work and attachments.

FINAL WICHITA FALLS ENGINEERING PACKAGE (pdf)

View the file

Other files

File Type Posted
6973GH-19-R-00270(2).2 —
Wage Determination.pdf PDF
Amendment 0002-signed.pdf PDF
Experience Information Form.pdf PDF
Performance Bond.pdf PDF
FINAL WICHITA FALLS ENGINEERING PACKAGE.pdf PDF
Amendment 0001 Site Visit Info-signed.pdf PDF
Payment Bond.pdf PDF
Contractor's Release Form DOT F 4220.4.doc DOC document
SIR 00270 Amendment 0003.pdf PDF
Wage Determination.pdf PDF
Amendment 0001 Site Visit Info-signed.pdf PDF
Contractor's Release Form DOT F 4220.4.doc DOC document
FINAL WICHITA FALLS ENGINEERING PACKAGE.pdf PDF
Amendment 0002-signed.pdf PDF
6973GH-19-R-00270(2).2 —
Performance Bond.pdf PDF
Payment Bond.pdf PDF
Experience Information Form.pdf PDF
Wage Determination.pdf PDF
Amendment 0001 Site Visit Info-signed.pdf PDF
Payment Bond.pdf PDF
Performance Bond.pdf PDF
Contractor's Release Form DOT F 4220.4.doc DOC document
6973GH-19-R-00270(2).2 —
Experience Information Form.pdf PDF
Payment Bond.pdf PDF
Performance Bond.pdf PDF
Experience Information Form.pdf PDF
FINAL WICHITA FALLS ENGINEERING PACKAGE.pdf PDF
Contractor's Release Form DOT F 4220.4.doc DOC document
Wage Determination.pdf PDF
6973GH-19-R-00270(2).2 —
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of Transportation

Date Issued: JULY 15th, 2019

CENTRAL SERVICE AREA (CSA)

CIVIL ENGINEERING PACKAGE

PROJECT

WICHITA FALLS, TX

Job Control Number (JCN) 1004103 Job Order Number

(JON) 1218SW0567

Prepared by Rafael Silva, Civil Engineer Communications Engineering Center (AJW-2C13B)

Approved by: , date James Withers, Manager, Communications Engineering Center (AJW-2C13B)

TABLE OF CONTENTS

SECTION 1

SECTION 2

SECTION 3

SECTION 4

SECTION 5

SECTION 6

GENERAL PROJECT INFORMATION

PROJECT SAFETY INFORMATION

REFERENCE MATERIALS

INSTALLATION GUIDELINES

CSA-2815 SPECIFICATION

DRAWINGS PACKAGE

ATTACHMENTS

Enviromental Health and Safety (EHS) Checklist

Asbestos Work Permits

Project Drawings ii

SECTION 1.0 GENERAL PROJECT INFORMATION

1.1 PROJECT SCOPE.

There are two sites, SPS (33°58'50.42"N 98°40’13.69"W) and SPSA (33°59'3.49"N 98°40'16.92"W);

SPSA will be a complete demolition and retirement of service, while SPS will be a renovation/improvements and repairs. There are two buildings, which have asbestos, in SPSA that will be demolished along with three existing towers. All tower material and foundation material will have to be hauled off. In addition, any fences or material on site will be discarded and the site will be returned to pre-existing conditions to match surrounding farmland.

In site SPS we will demolish four antenna towers and their foundations, as well as the roof in the existing building. We will keep the existing walls and building foundation for this site and will refurbish the site once the new roof is placed. A total of 5 antenna towers and the respective foundations will be constructed in this site.

These specifications, along with the accompanying drawings, describe the requirements for the re-cabling of an existing Federal Aviation Administration (FAA) Remote Communications Air/Ground (RCAG) in Wichita Falls, Texas, contractor will comply with all procedures, and regulations of the city if you will be using a hydrant as a water source.

1) SCOPE OF WORK

The Contractor shall perform the following work:

a) Coordination for entire project

i) Contractor shall perform a subsurface utility search prior to any digging.

ii) In preparation Hydro-trench from tower to the building. When trenching near building and tower, hand dig to locate all underground, insure equipment is a high-pressure water and air vacuum system that utilizes 3000 lbs. of pressure.

iii) In preparation for Re-Cabling, contractor shall coordinate with FAA personnel to;

temporarily transfer tower's frequencies throughout the completion of the entire project.

iv) Contractor responsible for provide the Hazmat Materials Survey (HMS), and the disposal of any asbestos materials.

v) Contractor shall supply FAA Project Engineer, with environmental assessment prior to the beginning of demolishment of the old RCAG site.

vi) Manifest of debris must be supplied to RE

b) Hazardous Material Survey (HMS) Contractor is responsible for providing the Hazardous Materials Survey (HMS), and the disposal of any asbestos materials. That includes but is not limited to the following:

Task 1 – Within 14 calendar days after notice to proceed, the vendor shall prepare and provide the FAA with one complete hard copy and one complete electronic copy in Microsoft Word format the Draft

HMS.

Task 2 – Within 7 calendar days after the vendor is provided with written comments, if any, on the Draft HMS, the vendor shall revise the draft as necessary to address all the comments and to incorporate all requested changes into the Revised Draft HMS.

Task 3 - Within 1 calendar day after completion of Task 2, the vendor shall provide the FAA with two

(2) complete printed copies and one complete electronic copy, in Microsoft Word format, of the Revised Draft HMS.

Task 4 - Within 7 calendar days after the vendor is provided with written comments, if any, on the Revised Draft HMS, the vendor shall revise the draft as necessary to address all the comments and to incorporate all requested changes into the Draft Final HMS.

Task 5 - Within 1 calendar day after completion of Task 4, the vendor shall provide the FAA with two

(2) complete printed copies and one complete electronic copy, in Microsoft Word format, of the Draft Final HMS.

Task 6 – Within 7 calendar days after the vendor is provided with written comments, if any, on the Draft Final HMS, the vendor shall revise the draft as necessary to address all the comments and to incorporate all requested changes into the Final HMS.

Task 7 - Within 1 calendar day after completion of Task 6, the vendor shall provide the FAA with five

(5) complete printed copies and one complete electronic copy, in Microsoft Word format, of the Final

HMS.

i) The consultant shall inspect of the following materials:

(1) Asbestos-Containing Building Materials (ACM);

(2) Lead-Based Paint

(3) Mercury sources in miscellaneous materials, such as switches, gauges, and light bulbs;

(4) Polychlorinated Biphenyls (PCBs) in electrical transformers, light ballasts, and hydraulic fluids;

(5) Lead-acid batteries, focusing in the generator room, emergency lighting systems and mechanical and maintenance areas;

(6) Hydraulic and waste oils;

(7) General hazardous materials, such as general household chemicals and other materials located in the facility

ii) All sampling methods, collections, locations, quantities, and findings must be documented in the final report.

iii) The contractor shall provide all labor, materials, and equipment necessary to conduct the HMS in accordance with the following:

iv) All work shall be done using personnel appropriately accredited and licensed with the Texas State Department, and shall follow all Federal and state requirements for asbestos and lead inspection work.

v) The contractor shall coordinate and prepare a schedule to be approved by the FAA for conducting a site visit to the facilities. The HMS must be completed in one visit to the facilities.

vi) The contractor shall notify the FAA IMMEDIATELY if any conditions are identified during the HMS, which may require immediate attention to prevent potential employee exposure at any of the facilities.

vii) Security and insurance requirements: All FAA facilities are secured facilities and all personnel entering the facilities shall meet all security and insurance requirements for gaining access to the facilities.

viii) Employee information, security investigation, employee badging, may be required at some locations either by the FAA or by airport authorities. At some facilities, the contractor and/or their employees may have to sign in and out. The contractor and/or their employees will be escorted at all times while working in FAA facilities and must have valid photo ID.

ix) Asbestos Inspection Requirements:

(1) The contractor shall inspect all previously identified ACM and non-accessible presumed ACM (PACM) listed in the previous facility reports and shall note the present condition.

(2) The contractor shall sample previously identified PACM listed in the facility inspection/air monitoring reports, such as roofing materials and fire doors (if applicable), utilizing Asbestos Hazard Emergency Response Act (AHERA) protocols.

(3) If suspect ACM is identified during the inspection that has not been previously tested for asbestos, the contractor shall sample these materials for asbestos utilizing AHERA protocols.

(4) All ACM bulk sample analysis shall be completed by a National Voluntary Laboratory Accreditation Program (NVLAP) accredited laboratory and samples shall be analyzed using Polarized Light Microscopy (PLM).

(5) The contractor shall report all laboratory findings and make recommendations for future actions based on the results.

(6) Inspection findings shall be evaluated using the same criteria as identified in previous reports. The criteria includes the following:

(a) Potential for Disturbance

(b) Disturbance Source ACM

(c) Condition AHERA Hazard

(d) Ranking Recommended Actions

(7) The final report shall clearly identify areas and materials that contain ACM, and shall contain pictures of all homogenous ACMs identified.

(8) Based on the site observations and analytical results, the contractor will provide recommendations regarding the presence of all regulated and PACM that may require abatement before demolition / removal activities.

x) Lead-Based Paint Sampling Requirements:

(1) All exterior and interior homogenous painted surfaces shall be tested for lead-based paint.

(2) All analysis for lead-based paint should be conducted utilizing x-ray florescence (XRF) technology. The XRF device shall have current calibration certificates and the consultant using the device shall have documented training for the device. A copy of the calibration and training certificates shall be included in the final report. The contractor shall report all inspection findings and make recommendations for future actions based on the results.

The final report shall clearly identify areas and materials that contain lead-based paint, and shall contain pictures of all homogenous lead-based paint identified.

xi) PCB Survey Requirements

(1) All materials in the equipment shelter shall be inspected for suspected PCBs. If suspect PCB containing materials are identified during the survey, such as dielectric fluids or hydraulic fluids, those materials would be sampled by the consultant and tested for PCBs utilizing SW-846 8082 methodology, if possible. Unless marked as PCB free, light ballasts shall be assumed to contain PCBs. The contractor shall report all laboratory findings and make recommendations for future disposal actions, including a cost estimate, based on the results. Quantities and locations of all suspect and actual PCB containing materials identified during the survey should be noted in the final report.

xii) Hydraulic and Waste Oil Survey Requirements

(1) The equipment shelter shall be inspected for hydraulic and waste oils. If it is determined that these materials are present at the facility, approximate quantities and locations of these materials identified during the survey shall be identified in the final report. The contractor shall make recommendations for future disposal actions, including a cost estimate, in the final report based on the results of the survey.

xiii) FUEL TANKS

(1) BOTH sites should be tested using a non-invasive method to determine whether there is a Fuel storage tank present or not. If there is a fuel storage tank present, the contractor is responsible for removing the tank and conducting all applicable required testing, as well as notifying all regulatory agencies. Once the tank is removed, it is the contractor’s responsibility to backfill the empty section with fresh soil clear of rocks and debris.

xiv) General Hazardous Materials Survey Requirements

(1) The equipment shelter shall be inspected for general hazardous materials, such as common household chemicals. Quantities, types, and locations of general hazardous materials identified during the survey shall be noted in the final report. The contractor shall make recommendations for future disposal actions, including a cost estimate, based on the results of the survey.

c) Demolition of SPSA

i) Contractor shall demolish SPSA RCAG site, which contains asbestos in both interior and exterior. Contractor should follow all protocols the FAA has in place for the disposal of asbestos containing material. Site location can be found at 33°59' 97"N, 98°40'.19.62"W, where elevation is zero. Contractor shall remove the two existing buildings, three towers and the fence surrounding the site and have it back to previous/original state to match surrounding farmland this includes fence removal.

ii) Remove and dispose existing tower, cables, RCAG junction boxes, and connectors at the tower.

iii) There is a road that connects the two sites together, this road is to be demolished along with the site by the contractor

d) Demolition of towers in SPS

i) Remove and dispose existing tower, cables, RCAG junction boxes, and connectors at the tower.

e) Construction/refurbish of SPS building

i) Roof

(1) Contractor shall demolish and install new roofing for the RCAG building. For more details see: (SPS-D-RCAG-A008).

ii) Power

(1) There will be a new point of entrance for main power; it will change from overhead, to underground and into a meter base. It is the contractor’s responsibility to install 3” PVC coated steel rigid conduit from the meter frame rack to the building.

(2) Contractor shall install Double Throw Safety Switch located at the building for more details see (SPS-D-RCAG-C012), and (SPS-D-RCAG-A010).

(3) Contractor shall install main power disconnect switch, as well as a E/G transfer switch with an Engine generator Hubble connector at the building, to have the building ready for cutover to E/G power. See (SPS-D-RCAG-C012).

(4) TXU Energy shall provide the power meter 200 AMP and remove the existing wood poles.

(5) TXU Shall remove their equipment and remove the exiting wood pole at SPSA site after work is completed with SPS site. For location, see (SPS-D-RCAG-C005).

(6) Contractor shall install new HVAC units. For more details see: (SPS-D-RCAG- M001).

(7) Contractor shall replace the power meter box, and install it at the entrance. See (SPS-D-

RCAG-C005).

(8) Contractor shall provide a power panel and TVSS Box and mount it on the building. See

(SPS-D-RCAG-C012)

iii) Aesthetics

(1) Contractor shall replace the entire Asbestos Tile on SPS, replacing it with a light color asbestos free tiles. As well, contractor shall install the wall-molding ceiling.

(2) Contractor shall paint outside of SPS building before installing the outdoor Sandstone at the entire building.

(3) Provide new exterior door, including new hinges, weather stripping, sweeps &latchset hardware for building entrance.

(4) Remove and discard old door leafs, hinges, closers, & latching hardware. Turn both latchsets &cores over to the FAA RE.

(5) Furnish and install new door and doorframes.

(6) Doors shall meet all current ANSI A250.8 & A250.6 and, SDI 100 requirements.

(7) New hinges shall be brushed stainless steel. Meet ANSI/BHMA A156.1 requirements and, contain ball bearing non-removable pins. Equal to those made by Assa Abloy, Hager, or Yale.

(8) Exterior door mortise locks and latches shall be ANSI/BHMA A156.13, Series 1000, Operational Grade 1, Security Grade 2, lever style, lockable with key from outside, lock or open with thumb set inside. New Latchsets will be capable of accepting Best Lock Cores. Latchset will be equal to that made by Yale, Assa Abloy, or Best.

(9) Provide door bottom sweeps. Attached to the door leaf with threaded fasteners. Bottom sweep shall be Pemko 3452 PK or approved equal.

(10) Paint doors and frames. Prepare the surfaces. Remove all corrosion and loose material.

Applytwo coats of exterior paint.

iv) Cabling

(1) Contractor shall provide and install 12” wide cable ladder from the Demarc boxes to the end of the equipment racks. As well, contractor shall provide and install 4”x4” square duct above the equipment racks. See (SPS-D-RCAG-C006).

f) Implementation of Earth Electrode System (EES)

i) Building

(1) Contractor shall install new single point ground plate (ALT-3832- MHO-12SPG). Location will be identified by RE. See details (SPS-D-RCAG- E019). Install new multi-point ground plate (ALT=3832-8-12-EMPG) in same exiting multi-point plate inside the building. Be advanced lighting technologies or approved equal. More details see

(SPS-D-RCAG-E018)

ii) Towers

(1) Contractor shall install two down conductors on each tower and have them exothermically welded to a EES ring on the crow’s nest of each tower

iii) Fence

(1) The ground rods shall be installed every 90 ft. along the fence line, and the distance shall not be less than 50 ft. Away from the towers.

(2) Contractor shall connect the fence grounding to the new grounding counterpoise on SPS.

For more details, see standards STD-FAA-19F. Note: Check with the RE before installing the new gate.

g) SPS Tower Construction (5)

i) Towers

(1) Contractor shall provide total of (5) 40' Self-Supporting RCAG tower, with installation.

See :( SPS-D-RCAG-C009).

ii) Cabling

(1) Contractor shall make sure the cable distance from towers to demark box on SPS shall be less or equal to 150'.

(2) Contractor shall install (2) 4" PVC SCH 80 conduits in trench from towers to quazite box. (2) 4" PVC SCH 80 conduits in trench from quazite box to building. Note: PVC at towers should extend approximately 6' from base of tower upwards. More details see

(SPS-D-RCAG-C008).

(3) Install (10) runs of LDF4-50a Heliax cables 1/2" from building's RCAG box to junction box at towers that have the 6 positions. Contractor will also install (12) runs of LDF4-50a Heliax cables 1/2" from building's RCAG box to junction box at towers that have the 8 position. Additionally the contractor will install 12 junction boxes. Two 24"H x 24"W x 12”D, junction boxes on each tower. (See SPS-D-RCAG-C005).

(4) Install Heliax boxes (NEMA rated for outside) on tower as shown in plans. All grounding must adhere to FAA standard 19F.

(5) Contractor shall install (2) 48"x48"x48" traffic rated quazite box. Make sure it hold total of (6)4" PVC conduits 80 SCH underground.

(6) Contractor shall install (2) 48"H x 48"W x 48"D COAX Demarc Boxes. More details see:

(SPS-D-RCAG-C007).

iii) Foundation for towers

(1) Contractor shall make sure the distance between towers in SPS has a minimum distance of

120'.

(2) All steel used should be American made Grade 60 steel

(3) Install 12’x12’x4’ concrete foundation in accordance to specifications. See drawing

(SPS-D-RCAG-S001)

(4) Contractor has to ensure 6 inches of the 4 foot, concrete slab is above grade and edge is chamfered.

(5) Use no. 7 rebar for rebar cage used for concrete foundation

iv) Grounding for towers

(1) Towers should have down conductors in accordance with 19F and two 4/0 bare copper cable going down the tower edges (opposite sides) and exothermically welded to the bottom of the legs. Then connected to the Earth Electrode System (EES) around the perimeter of the tower slab.

h) Site construction

i) Fence

(1) Contractor shall replace the existing fence on SPS: for more details see (sps-d-rcag-c013), and (sps-d-rcag-c014).

ii) Gravel

(1) Contractor shall install (6in) of gravel or equal on the entire site with a landscaping fabric underlay to prevent weeds from growing.

2) SUBMITALS

The Contractor must submit information to FAA about all products, procedures, tools, and equipment selected for new work. All items shall meet FAA approval before work begins. Submittals include but are not limited to the following:

a) Work Schedule

b) Safety and Accident Prevention Plan

c) Bonding and Insurance

d) Asbestos Report

e) Materials, Tools & Equipment contained in 1.1, 1 through 6 above

f) Roof metal siding, roofing felt, roof trusses, roof plywood sheathing, weather tight caulk, Insulation board, fire rated plywood, & fasteners, tower and tower materials, fence materials.

g) LDF cable, bus bars and grounding plates, cable ladder

h) HVAC units

i) Demarc boxes, junction boxes, and disconnect switches

j) Rebar, rebar mesh, dowels, concrete mix and concrete testing.

k) Roof bitumen sheets

l) Sheet metal fascia trim & fasteners.

m) Roof system warranty.

n) #4, #500MCM AWG copper wire, 10’ copper ground rods, compression terminals

o) Exothermic welding materials, 2’ x 2’ ground well, PVC Conduit, PVC coated rigid steel electrical conduit, conduit clamps, & fasteners

p) Pressure treated lumber, galvanized fasteners, concrete footers

q) Equipment, cranes, man lift, boom lift, or aerial work platform, hydro-excavator

r) Doors & hardware

a) Gravel, backfill soil and crushed stone

b) Paint

3) WORK HOURS AND CONDITIONS

Contractor will be subject to all laws and regulations that apply to persons on State of Texas property and landowner regulations.

i) RCAG roof work must be complete within (6 months) calendar days.

ii) Work will be done during daylight hours between 7:00AM to 5:30PM. Mon thru Fri.

iii) Saturday, Sunday, & Overtime work will only be allowed to expedite roof repair in case of bad weather.

iv) Contractor will report & coordinate each day’s work in advance with the onsite FAA COR.

v) All work will be inspected and approved by an FAA Resident Engineer.

4) PRE-BID SITE VISIT

The Contractor is to examine the areas of the proposed work, to see first-hand the extent of work involved.

The submission of a proposal is considered evidence that the bidder has made such examination and is satisfied as to the conditions to be encountered in performing the work.

The FAA Contracting Officer will provide a date for one official site visit with the Engineer. If any other visits are needed, Contractor must give FAA at least five days advance notice before appearing on site. All visitors must be escorted by an FAA employee, or other authorized personnel.

5) LOCATION

FAA SPS & SPSA RCAG

Wichita Falls, Texas 33°58'50.42"N 98°40'13.69"W

SPS & SPSA RCAG is in a remote area approximately 1 mile from where Highway 287 and N Pacific Ave.

intersect. In addition, it is .14 miles from N pacific Ave. on an unpaved Service road.

1.2 PROJECT SCHEDULE. – The following schedule provides target start and finish dates for project installation activities. The communications Installation/Construction Center will keep the System Support Center (SSC) and project engineer informed of any changes to the provided target dates.

a. Plants Construction Start: 09/03/2019

b. Plants Construction Finish/CAI: 05/31/2020

c. Electronic Installation Start: 05/31/2020

d. Electronic Installation Finish: 07/04/2021

e. JAI: 07/05/2021

f. Commissioning/Cutover: 07/09/2021

1.3 POINTS OF CONTACT (POC).

1.3.1 Engineering Center Office POCs.

Name Title Phone Rafael Silva Civil Engineer, AJW-2C13B 817-222-4110 David Courtney Electronics Engineer, AJW-2C13B 817-222-4432 Brandon Wallace Manager, Construction/Installation, AJW-

2C13F 817-222-4453

Larry Cooper Coordinator, Construction/Installation, AJW- 2C13F

817-222-5170

James Withers Manager, Communications Engineering 817-222-4538 Center, AJW-2C13B

Ralph Bustamante PIM, SW ATO CSA Service Center 817-222-4463 Projects

1.3.2 District/SSC/Other Office POCs.

Name Title Phone Antonio Salas SPS, SSC Manager 817-321-7200 John Harlin Coordinator, SPS SSC 817-321-7200 Jeromy Williams John W. Stuart

TECH OPS, SPS SSC

TECH OPS, SPS SSC

817-321-7200 817-362-8671

1.4 TRAINING

Asbestos handling training is required for all work done on asbestos containing material

***Climbing training is required for personal that will be climbing towers***

Course Profile:

TBD

SECTION 2.0 PROJECT SAFETY INFORMATION

2.1 GENERAL

i) The FAA, before installation, must approve all materials used.

ii) Contractor will stage work in a manner that minimizes SPS & SPSA outage time.

iii) All shutdowns and cutovers shall be coordinated with and scheduled by local FAA Air Traffic

Management with 30 days of anticipation.

iv) Protection of work is essential. Contractor shall not leave roof open to elements and will have enough tarp on hand to prevent water from entering building. Building roof will remain covered at all times.

v) Contractor shall repair any damage done by him to any entity, at his cost. Contractor shall be covered by minimum locallyrequired liability.

vi) Contractor must provide FAA with a safety and security plan before work begins.

(1) Due to the remote location of this facility, extra precautions shall be established. Plan will include procedures for accident prevention, emergency procedures, phone number & map to nearest emergency medical facility.

vii) Contractor's Superintendent shall be present at the work site during all times work is performed.

Superintendent shall carry a cell phone and be prepared to make and receive calls to & from the FAA at all times while on work site.

The potential for risks, hazards, and safety issues may arise during normal construction and installation that takes place in a live FAA environment. Safety is the responsibility of all personnel on site. The developing of safe work practices is essential to the skills required to successfully complete this project. Personnel are to be aware of potentially unsafe conditions, report and/or correct potential hazards, and use appropriate safety equipment. There should be periodic safety meetings with all site personnel. If the installation cannot proceed because of some safety hazard or obstacle, notify the TOR immediately.

Risks include: Climbing and fall hazards; damage to subsurface utilities and cabling; working on and around “live” equipment: radios, radar, navigation aids; electrical hazards; remoteness of facility; access to several sites through Aircraft Operations Areas. There is the risk of site access cancellations due to last-minute site contingencies. When these instances occur, the installation team will contact the Systems/ Project Engineer to minimize schedule impact and revise their schedules accordingly.

2.2 SAFETY EQUIPMENT

Safety equipment will be used whenever applicable to the job. The following list is the minimum safety equipment required for this installation.

First Aid Kit - All personnel should know the location of the First Aid Kit on site. A quick check of the contents is to be made to insure an adequate kit is available.

Safety Belt/Harness - The safety belt/harness is to be used at all times when climbing and working on towers. Precaution should be taken to examine the belt/harness prior to use. It is the user’s responsibility to ensure that all buckles, straps, and lanyards are in good repair.

Hard Hats - All personnel on site are to be advised when overhead work is being performed.

Hard hats are required and must be worn while any overhead work is in progress.

Ear Plugs - Ear plugs or ear protection of some form is to be used when tools, machinery, or other devices present a noise hazard.

Safety Glasses - Some form of OSHA approved eye protection must be used at all times when operating tools or equipment where the possibility of eye injury is present.

Safety-Toe Footwear - Any employee who is exposed to hazards from heavy rolling or falling objects is required to wear Safety-Toe Footwear.

RISK ASSESMENT

a) Personal Protective Equipment (PPE)

i) Contractors onsite should wear their PPE AT ALL TIMES

(1) Hardhat/helmet

(2) Earplugs

(3) Safety glasses

(4) Steel toe boots

(5) Gloves

b) Fall hazards

i) Contractor should wear proper safety equipment when climbing towers or when elevated more than 4ft. no one is allowed to climb alone and special training (fall protection/climbing) is required.

ii) Open trenches need to be covered or fenced off AT ALL TIMES

c) Tripping hazards

i) At the end of everyday contractor should cleanup work area from any debris, tools, trash etc…

d) Excavation hazards

i) Cave-in

(1) Contractor shall provide safety barriers to prevent cave-ins or provide the proper slopes in accordance with OSHA

ii) Exposure to hazardous atmosphere

(1) When performing excavation always be aware of any foul smells and liquids and assess the situation by measuring oxygen levels in trenches.

e) Loss of service

i) In the event of loss of service, IMMIDIETLY talk to the FAA representative on site and began coordination with locals to re-establish service.

2.3 SAFETY DOCUMENTATION REQUIREMENTS

A Safety Risk evaluation memo is required for this project and included in the attachments.

If required for this project, the IRMC (Integrated Risk Management Checklist) can be accessed at http://irmc.faa.gov/.

2.4 ENVIRONMENTAL, OCCUPATIONAL SAFETY, AND HEALTH (EOSH) IMPACTS

This section contains a site specific discussion and must be provided by an EOSH Professional. In addition, specific attachments may be added (checked) on the Table of Contents page of this engineering package.

See EOSH attachments on APPENDIX A

SECTION 3.0 REFERENCE MATERIAL

3.1 GENERAL. - This section lists all reference documentation and forms necessary to support the installation portion of this project.

Original site drawings. Not for use in construction. Will be provided on request.

3.2.2 Handbooks, Standards, Orders and Plans. - List the Handbooks, Standards, and Orders that should be available at site. Contractor shall furnish all plant, labor, equipment material, supplies and transportation required to perform the work, including erection or installation of items, all in strict accordance with the drawings and specifications.

INSTALLATION OF ROOFING MEMBRANE ON OMN VOR ROOF

FAA-G-2100G

CSA 2815 SPECIFICATIONS

FAA Order 6950.19A

FAA-E-2013E

NFPA 70

ANSI A250.6, A250.8

SDI 100

ASTM D118, ASTM C136

FAA-STD-019f, Lightning Protection, Grounding, Bonding and

Shielding

FAA ORDER 5200.5B

FAA ORDER 1391D

FAA ORDER 1217G

Order 150/5370-2C

3.2.3 Forms. - The following forms are for completion of the facility H81 3900-17 3900-18 3900-19

3.2.4. On line site links. - The following sites may be referenced.

http://cwp.faa - Project Scope Agreement.

http://irmc.faa.gov/ - Integrated Risk Management Checklist (IRMC) search form. http://cwpportal.faa.gov - Contractor Acceptance Inspection (CAI)

3.3 PROJECT DRAWING LIST (APENDIX B)

f) SPS-D-RCAG-G006 Cover Sheet/Drawing Index

g) SPS-D-RCAG-C004 Existing Site plan

h) SPS-D-RCAG-C005 Site Plan

i) SPS-D-RCAG-C006 Proposed Site Layout

j) SPS-D-RCAG-C007 Coax Demark Box Details

k) SPS-D-RCAG-C008 Miscellaneous Details

l) SPS-D-RCAG-C009 40 ft. Self-Supporting Tower

m) SPS-D-RCAG-C010 Embedment Assembly, 20 ft., 30 ft., 40 ft., 50 ft. and 60 ft. Self-supporting RTR Towers

n) SPS-D-RCAG-C011 RTR Platform Assembly

o) SPS-D-RCAG-C012 Electrical Details

p) SPS-D-RCAG-C013 Chain-link Fence and Single Cantilever Slide

Gate

q) SPS-D-RCAG-C014 Fence Details

r) SPS-D-RCAG-C015 Electrical Rack Details

s) SPS-D-RCAG-A007 Floor Plan

t) SPS-D-RCAG-A008 Roof Plan

u) SPS-D-RCAG-A009 Roof Sections

v) SPS-D-RCAG-A010 Building Elevations

w) SPS-D-RCAG-S001 Tower Foundation Plans and Sections

x) SPS-D-RCAG-M001 HVAC Plan and Details

y) SPS-D-RCAG-E014 Towers Grounding Details SPS-D-RCAG-

E015 Antenna Tower/ Lightning Protection

z) SPS-D-RCAG-E016 Antenna Tower/ Typical Electrical Details

aa) SPS-D-RCAG-E017 Grounding Standards Typical Connections

bb) SPS-D-RCAG-E018 Panel Schedule and Details

cc) SPS-D-RCAG-E019 Lightning, Cable Tray, Grounding Plans

dd) SPS-D-RCAG-E020 Electrical/Grounding Details

ee) SPS-D-RCAG-E021 Electrical One Line Diagram Power System

ff) SPS-D-RCAG-E022 Air Terminal Mast Assemble

REFERENCE DRAWINGS

0980-0453-SHT-1 INSTALLATION RTR PLATFORM 8X MOUNT ARMS

0980-0453-SHT-2 INSTALLATION RTR PLATFORM 8X MOUNT ARMS

0980-0453-SHT-3 INSTALLATION RTR PLATFORM 8X MOUNT ARMS

0980-0453-SHT-4 INSTALLATION RTR PLATFORM 8X MOUNT ARMS

0980-0453-SHT-5 INSTALLATION RTR PLATFORM 8X MOUNT ARMS

SECTION 4.0 INSTALLATION GUIDELINES

4.1 SUMMARY OF WORK

PART 1.00 GENERAL 1.01

WORK INCLUDED:

Contractor will perform a total demolition of an RTR site (SPSA). Contractor will also refurbish an existing site by demolishing and removing the old roof and performing the construction of the new roof. Additionally, the contractor must demolish all existing towers on site SPS and install 5 new towers. The contractor will be doing perimeter Hydro-excavation for any digging done on site, and tower foundations as well as the electrical conduits runs. The contractor will be responsible for putting a perimeter fence on the entire RTR site.

AGL REGION EHS CONTACTS

EOSH COORDINATOR Michelle Sherman 816-222-4156

OTHER CONTACTS

Antonio Salas, SPS SSC Mgr. Rafael Silva, FAA Engineering 1050 Meacham Blvd. 10101 Hillwood Parkway Fort Worth, TX, 76106 Fort Worth, TX, 76177 W: 817-321-7200 W: 817-222-4110 Email: Antonio.Salas@faa.gov C: 817-357-7060

Email: Rafael.Silva@faa.gov

John Harlin, SPS SSC Coordinator Jeromy Williams, SPS Site Tech 1050 Meacham Blvd. 4000 Armstrong Drive Fort Worth, TX, 76106 Wichita Falls, TX, 76305 W: 817-321-7200 W: 817-321-7200 Email: John.Harlin@faa.gov email: Jeromy.Williams@faa.gov

John W. Stuart, SPS Site Tech 4000 Armstrong Drive Wichita Falls, TX, 76305 W: 817-362-1001 C: 817-659-8671 Email: John.W.Stuart@faa.gov

The specific Project Scope Agreement (PjSA) can be accessed on line at http://cwp.faa. Search under Job Control Number (JCN) 100410

SECTION 5

CSA-2815

June 2018

U. S. Department of transportation Federal aviation administration

Southwest region

Specifications

Volume I

Tower Re-Cabling Project Wichita Falls, Texas

June 2018

U. S. Department of transportation

Federal aviation administration

Southwest region

Specifications

Volume I

Remote Communications Air/Ground (RCAG)

Tower Re-Cabling Project

Wichita Falls, Texas

For

RCAG FACILITY, Wichita Falls, Texas

Volume II

Section Title

CSA-2815 TOC-1

DIVISION 1 GENERAL REQUIREMENTS

Section 01010 - Summary of Work

Section 01030 - Special Provisions

Section 01040 - Project Administration Section 01041 - Job Management

Section 01080 - Identification Systems

Section 01300 - Submittals Section 01400 - Quality Control

Section 01700 - Contract Closeout

Section 01710 - Cleaning

DIVISION 2 SITEWORK

Section 02050 - Demolition

Section 02053 - Existing Utility Exploration

Section 02080 - Asbestos Abatement

Section 02100 - Site Preparation

Section 02200 - Earthwork

Section 02223 - Aggregate Fill Classifications

Section 02224 - Earth Fill Classifications

Section 02225 - Excavating, Backfilling, and Compacting for Utilities

Section 02226 - Trench Safety

DIVISION 3 CONCRETE

RCAG FACILITY, Wichita Falls, Texas

Volume II

Section Title

CSA-2815 TOC-2

Section 03100 - Concrete Formwork

Section 03200 - Concrete Reinforcement

Section 03300 - Cast in Place Concrete

DIVISION 4 MASONRY

Section 04010 - Masonry

DIVISION 7 THERMAL AND MOISTURE PROTECTION

Section 07921 - Caulking and Sealants

DIVISION 9 FINISHES

Section 09661 - Resilient Flooring

Section 09901 - Painting

DIVISION 16 ELECTRICAL

Section 16010 - General Requirements for Electrical Work

Section 16111 - Conduits

Section 16114 - Cable Tray

Section 16131 - Pull and Junction Boxes

Section 16190 - Supporting Devices

Section 16450 - Grounding

RCAG FACILITY, Wichita Falls, Texas

Volume II

Section Title

CSA-2815 TOC-3

Section 16451 - High Frequency Grounding and Signal Reference Grid

Section 16500 - Lighting

Section 16670 - Lightning Protection

APPENDIX TO THE SPECIFICATIONS

Appendix B -

Appendix D -

Appendix E-

Appendix F-

List of Drawings

FAA Standard 019f – Lighting and Surge Protection, Grounding, Bonding, and Shielding Requirements for Facilities and Electronic Equipment

Installation, Termination, Splicing, And Transient/Surge Protection of Underground Electrical Distribution System Power Cables

Entergy Electric Service Details and Construction Requirements.

DRAWING NUMBER DRAWING TITLE

SPS-D-RCAG-G006 COVER SHEET/DRAWING INDEX

SPS-D-RCAG-C004 EXISTING SITE PLAN

SPS-D-RCAG-C005 SITE PLAN

SPS-D-RCAG-C006 PROPOSED SITE LAYOUT

SPS-D-RCAG-C007 COAX DEMARK BOX DETAILS

SPS-D-RCAG-C008 MISCELLANEOUS DETAILS

SPS-D-RCAG-C009 40 FT SELF SUPPORTING TOWER

SPS-D-RCAG-C010 EMBEDMENT ASSEMBLY, 20 FT, 30 FT, 40 FT, 50 FT AND

60 FT

SELF-SUPPORTING RTR TOWERS

SPS-D-RCAG-C011 RTR PLATFORM ASSEMBLY

SPS-D-RCAG-C017 ELECTRICAL DETAILS

SPS-D-RCAG-A007 FLOOR PLAN

SPS-D-RCAG-A008 ROOF PLAN

SPS-D-RCAG-A009 ROOF SECTIONS

SPS-D-RCAG-A010 BUILDING ELEVATIONS

SPS-D-RCAG-S002 TOWER FOUNDATION PLANS AND SECTIONS

SPS-D-RCAG-M002 HVAC PLAN AND DETAILS

SPS-D-RCAG-E014 TOWERS GROUNDING DETAILS

SPS-D-RCAG-E015 ANTENNA TOWER/LIGHTNING PROTECTION

SPS-D-RCAG-E016 ANTENNA TOWER/ TYPICAL ELECTRICAL DETAILS

SPS-D-RCAG-E017 GROUNDING STANDARDS TYPICAL CONNECTIONS

SPS-D-RCAG-E018 PANEL SCHEDULE AND DETAILS

SPS-D-RCAG-E019 LIGHTING, CABLE TRAY, GROUNDING PLANS

SPS-D-RCAG-E020 ELECTRICAL/GROUNDING DETAILS

SPS-D-RCAG-E021 ELECTRICAL ONE LINE DIAGRAM POWER SYSTEM

SPS-D-RCAG-E022 AIR TERMINAL MAST ASSEMBLY

REFERENCE DRAWINGS

0980-0453-13 INSTALLATION RTR PLATFORM 8X MOUNT ARMS

END OF SECTION

CSA-2815 01010-1

01010 SUMMARY OF WORK

PART 1.00 GENERAL

1.01 WORK INCLUDED:

A. These specifications, along with the accompanying drawings, describe the requirements for the re-cabling of an existing Federal Aviation Administration

(FAA)

Remote Communications Air/Ground (RCAG) Wichita Falls, Texas.

B. Contractor shall furnish all plant, labor, equipment material, supplies and transportation required to perform the work, including erection or installation of items listed in Appendix A, "Government Furnished Materials", all in strict accordance with the drawings and specifications.

C. The construction site is located in Wichita Falls, TX. Contractor will comply with all procedures, rules and regulations of the city. Refer to contract drawing SPS-D-RCAG-G006 for site location.

D. The construction site is located in an area having developed construction.

Utilities are existing on, or adjacent to the site as indicated on the drawings.

Modifications of and extensions to these utilities shall be made by the Contractor as indicated on the drawings.

E. Contractor shall make sure the distance between tower 1 and tower 2 with a minimum of 120', same distance between 3 and 2. Note: use the same dimensions between tower 4, and 5.

F. Contractor shall make sure the cable distance from towers to demark box shall be less or equal to 150'.

G. The scope of work includes placing conduit and running new coaxial cables from the building to the 5 RCAG towers and placing a new RCAG junction boxes. The Contractor shall perform all work, which will include but is not limited to:

1. Contractor shall install 3” SCH 80 PVC conduit from the meter frame to the building. See (SPS-D-RCAG-C005)

2. Contractor shall hydro-trench 12” depth from the meter base frame to the FAA COMM trailer. Moreover, 36” depth to the building. See (SPS-D-RCAG- C005).

3. Contractor shall install main power, E/G switch connector at the building, to have the building ready for cutover to E/G power. See (SPS-D-RCAG-C017).

CSA-2815 01010- 2

3. TXU Energy shall provide the power meter 200 AM and remove the existing wood poles.

4. In preparation for Re-Cabling, contractor shall coordinate with FAA personnel to temporarily transfer tower's frequencies throughout the completion of the entire project.

5. Contractor shall perform a subsurface utility search prior to any digging.

6. In preparation Hydro-trench from tower to the building. When trenching near building and tower, hand dig to locate all underground, insure equipment is a high-pressure water and air vacuum system that utilizes 3000 lbs. of pressure.

7. Cables including grounding counterpoise and underground power lines.

8. Remove and dispose existing Heliax cables, Junction box, conduit, and connectors on tower.

9. Contractor shall install new single point ground plate (ALT-3832-

MHO-12SPG). Location will be identified by RE. See details (SPS-D-RCAG-

E019). Install new multi-point ground plate (ALT=3832-8-12-EMPG) in same exiting multi-point plate inside the building. Be advanced lighting technologies or approved equal. More details see (SPS-D-RCAG-E018)

10. Contractor shall install (2) 4" PVC SCH 80 conduits in trench from towers to quazite box. (2) 4" PVC SCH 80 conduits in trench from quazite box to building. Note: PVC at towers should extend approximately 6' from base of tower upwards. More details see (SPS-D-RCAG-C008).

11. Remove and dispose existing tower, cables, RCAG junction boxes, and connectors at tower.

12. Prepare hydro-trench for conduit placement. From the new tower to the new RCAG junction box

CSA-2815 01010-3

14. Install (12) runs of LDF4-50a Heliax cables 1/2" from building's RCAG box to junction box at towers 3 & 4. Install (10) runs of LDF4-50a Heliax cables 1/2" from building's RCAG box to junction box at towers 1, 2 & 5. Install 10 junction boxes. Two 24"H x 24"W x 12”D, junction boxes on each tower.

(See SPS-D-RCAG-C005)

15. Close all trenches and restore site back to original grade.

16. Haul away all debris from site and restore to original state.

17. Install Heliax boxes (NEMA rated for outside) on tower as shown in plans.

All grounding must adhere to FAA standard 19F.

18. This work shall be accomplished using specification and the project drawings listed in appendix b of the specifications.

19. Repeat steps 1 through 12 for all other 5 RCAG towers.

20. Contractor shall replace the power meter box, and install it at the entrance.

See (SPS-D-RCAG-C005).

21. Contractor shall install new HVAC units. For more details see: (SPS-D-

RCAG-M002).

22. Contractor shall install (2) 48"x48"x48" traffic rated quazite box. Make sure it hold total of (6)4" PVC conduits 80 SCH underground.

23. Contractor shall install (2) 48"H x 48"W x 48"D COAX Demarc Boxes. More details see: (SPS-D-RCAG-C007).

24. Contractor shall provide total of (5) 40' Self-Supporting RCAG tower, with installation. See :(SPS-D-RCAG-C009).

25. Contractor shall demolish and install new roofing for the RCAG building. For more details see: (SPS-D-RCAG-A008).

26. Contractor Shall install Double Throw Safety Switch located at the building for more details see (SPS-D-RCAG-C017), and (SPS-D-RCAG-A010).

27. Contractor shall provide and install 12” wide cable ladder from the Demarc boxes to the end of the equipment racks. As well, contractor shall provide and install 4”x4” square duct above the equipment racks. See (SPS-D-RCAG-

C006).

CSA-2815 01010- 4

28. Contractor shall provide a power panel and TVSS Box and mounted on the building. See (SPS-D-RCAG-C017)

29. Contractor shall replace the entire Asbestos Tile, replacing it with a light color free asbestos tiles. As well, contractor shall install the wall-molding ceiling.

30. Contractor shall paint outside of the building before installing the Sandstone at the entire building.

31. Contractor shall demolish SPSA RCAG site. The site has an asbestos. Site location at 33°59' 97"N, 98°40'.19.62"W, and the elevation is zero.

32. The construction site is located within Wichita Falls, TX. The contractor will need to comply with all procedures, rules and regulations in effect by Wichita Falls, TX.

33. This work shall be accomplished using specification and the project drawings listed in appendix B of the specifications.

34. Contractor shall supply FAA Project Engineer Rafael Silva, 817-222-4110, rafael.silva@faa.gov with environment assessment prior to the beginning of demolish of old RCAG site.

35. Manifest of debris must be supplied to RE

36. All distances, elevations, quantities, and measurements are to be verified by the contractor at initial pre-bid site visit.

37. This work shall be accomplished using Specification CSA-2815 Volumes I, II, and the project drawings listed in Appendix B of the specifications.

38. The construction site is located within Wichita Falls, TX. The contractor will need to comply with all procedures, rules and regulations in effect by Wichita

Falls TX.

H. This work shall be accomplished using Specification CSA-2815 Volumes I, II, and the project drawings listed in Appendix B of the specifications.

mailto:Sadeer.Mustafa@faa.gov

CSA-2815 01010-5

I. The construction site is located within the Iowa Park Area. The contractor will need to comply with all procedures, rules and regulations in effect by Wichita

Falls, TX.

1.02 RELATED WORK COVERED ELSEWHERE:

Special Provisions Section 01030

Submittals Section 01300

1.03 SUBMITTALS:

Contractor will present a construction schedule and the following submittals prior to the Notice to Proceed (NTP):

Structural Fill Materials Electrical Work Materials

Concrete Mix Design Conduits

Reinforcing Steel Lightning Protection Materials

All submittals shall be presented for FAA approval.

1.04 STANDARDS AND REFERENCES:

A. STANDARDS:

All FAA, Military, Federal, Industrial and other Standards, Specifications, and Codes referenced in the following Divisions form a part of this specification and are applicable to the extent specified herein.

B. APPLICABLE DRAWINGS:

All architectural, structural, site improvement, landscaping, yard sprinkler system, mechanical, plumbing and electrical drawings form a part of requirements of the construction. Refer to the Index of Drawings, Appendix "B" for a listing of drawings that are applicable to this Project.

1.05 WORK COMPLETION TIME & DAYS:

Work shall be completed within 45 calendar days of the NTP. The contract period takes into account the following Federal holidays when NO work shall be performed at the site:

Normal work days shall be Monday – Friday for a 40-hour work week. Contractor is expected to coordinate work schedule with the Resident Engineer (RE).

CSA-2815 01010- 6

PART 2.00 PRODUCTS [Not Used]

PART 3.00 EXECUTION

3.01 COORDINATION AND REGULATORY AUTHORITY:

The Contractor shall coordinate all contacts with other governing agencies, such as airport authorities, through the FAA's designated Contracting Officer, or the Resident Engineer when such responsibility has been delegated by the Contracting Officer.

3.02 CONSTRUCTION SAFETY PLAN

The Contractor shall comply with the following safety plan:

a. GENERAL SAFETY CRITERIA: The installation of the RCAG equipment must be completed with minimum disruption to airport operations. A pre-construction meeting will be held prior to starting work. The contractor, FAA, & airport authorities will discuss all requirements during construction. All provisions of FAA Order SW-5200.5B (Airport Safety During FAA-Funded Airport Construction and FAA Facilities Maintenance), FAA AC 150/5370-2C (Operational Safety on Airports during Construction) and the Construction contract apply. The contractor shall comply with these requirements.

b. RCAG WORK COORDINATION. Due to the sensitivity of the RCAG facility, Contractor shall coordinate daily with FAA re and local System Support Center (SSC) personnel to ensure that all works to be performed will cause no interference to RCAG equipment or disruption to the National Airspace (NAS).

c. CONTRACTOR'S SECURITY CLEARANCE. The contractor is required to obtain badges from the airport authority. Contact the FAA SSC 48 hours prior to construction start date. Contractor employees shall submit to all security clearance requirements that may exist or as listed in the general provisions of the construction contract. He is also required to adhere to any local security requirements and to submit, if required by the airport operator, an employment history summary of all employees with access to the job site. Contractor shall also be required to meet the necessary insurance requirements of the airport.

d. CONSTRUCTION VEHICLE TRAFFIC: All motorized vehicles operating on the airport shall be equipped with flashing yellow lights and company sign while operating.

e. CONSTRUCTION LIMITS: All construction vehicles and traffic are required by FAA rules to stay within the limits of construction vehicle on the construction

CSA-2815 01010-7

site. These limits are strictly maintained. Access to the construction site is shown on haul/access plan. Vehicular traffic associated with construction is to use only areas shown for construction use. Failure to do so could result in offenders being removed from the construction site.

f. REFERENCE DRAWINGS: Drawings are included in plans for information only.

Where there are conflicts between the construction drawings and reference drawings, the construction drawings shall govern. The RE shall be notified of any conflicts prior to performing the related work.

CSA-2815 01030-1

01030 SPECIAL PROVISIONS

PART 1.00 GENERAL

1.01 RELATED WORK COVERED ELSEWHERE:

Submittals Section 01300

Site Preparation Section 02100

1.02 JOB CONDITIONS:

Contractor is hereby notified that written notification of any planned shut-down of existing facilities and/or utilities which may affect airport or FAA operations, shall be provided 2 weeks in advance of such a shut-down.

1.03 PLANS OF ACTION:

A. The Contractor shall not perform any work which will require shutting down essential services, including electrical power or control power, without an approved Plan of Action.

B. The Plan of Action shall consist of a typewritten report describing the construction necessary, the utilities, piping or other services that will be affected, the length of time that the service or utility will be disturbed, and the procedures to be employed by the Contractor to carry out the work in a timely manner. This plan shall also include action to be taken in the case of emergencies, and an alternate plan that can be employed in the event that the original schedule cannot otherwise be met. The Contracting Officer must approve the plan prior to any work being performed.

C. Shutdowns must be approved by the Contracting Officer in all circumstances, and shall be scheduled in a manner to create the minimum amount of interference’s with existing FAA or Airport facility operations. When shutdowns are necessary and have been approved by the Contracting Officer, Contractor shall employ additional labor and shall work overtime as necessary to restore the facilities to operation at the earliest possible time.

D. Contractor must be preparing to use Hydro Trenching methods.

1.04 OBSTRUCTION LIGHTING AND MARKING OF SUPERSTRUCTURE:

A. When the superstructure or construction machinery reaches a height of 100-feet, temporary day marking and night lighting shall be provided by the Contractor.

Temporary lighting shall consist of two (2) double obstruction lights, Crouse-Hinds

CSA-2815 01030-2

#50021-116, L810 obstruction marker light with two (2) 116 watt 116A21/TS lamps, or equal. The lights shall be placed at the highest points of the structure and spaced as designated by the Resident Engineer. Lights shall be operated by means of photocell having a manual by-pass switch. They shall be operative from sunset to sunrise and at time of low visibility and as directed by the Resident Engineer.

B. Daytime marking shall be provided by attaching four (4) aviation orange and white checkerboard pattern flags 36-inch square on the highest points of the construction, spaced as designated by the Resident Engineer. Day marking and night lighting shall be maintained during all construction. The Contractor shall provide all necessary power for the temporary obstruction lights until the building is accepted by Government.

1.05 HAZARDOUS MATERIAL CERTIFICATION:

A. Contractor shall provide letters of certification for the project certifying no asbestos was used.

B. Contractor shall provide letters of certification for the project certifying only lead-free paint, plumbing and flashing was used.

1.06 CONSTRUCTION LIMITS:

The contractor shall…