SCOPE OF WORK

QRC ARSR Fire Life Safety Upgrades

Benton Pennsylvania 03/04/2019

1.0 BACKGROUND

The QRC Benton Radar Facility is contained in a five story high concrete equipment building. It has a round fiberglass radar cover on the roof. The building contains a First floor EG Room, Second floor Telco Room, Fourth floor equipment room, a Fourth floor Bathroom, stairway and, freight elevator.

The FAA wants a lump sum price to upgrade the fire life safety features of the Benton Radar facility equipment building. The FAA also wants a bid alternate price to include removal of the steam boiler heat system and install an electrical heat system in the equipment building.

1.1 SCOPE OF WORK

The Contractor shall perform the following instructions:

1. Provide all labor, equipment and, materials to upgrade the fire life safety features in Benton Radar equipment building.

A. Perform all work contained on drawings QRC-1505568 dated 09/13/2017.

B. Perform all work in accordance with Specification QRC-1505568 dated 03/05/2019

C. Provide a lump sum price for items 1., A. through B. $

2. Provide all labor, equipment and, materials to remove the steam boiler system and install electrical heat in the Benton Radar equipment building.

A. Perform all work contained on Bid Alternate #1 HVAC SOW dated 03/05/2019

B. Provide a bid alternate lump sum price for items 2., A. $

1.2 DRAWINGS

QRC-1505568-G003 09/13/2017

QRC-1505568-D008 09/13/2017

QRC-1505568-A001 09/13/2017

QRC-1505568-A002 09/13/2017

QRC-1505568-A003 09/13/2017

QRC-1505568-A004 09/13/2017

QRC-1505568-A005 09/13/2017

QRC-1505568-A006 09/13/2017

QRC-1505568-F001 09/13/2017

QRC-1505568-F002 09/13/2017

QRC-1505568-F003 09/13/2017

QRC-1505568-F004 09/13/2017

QRC-1505568-F005 09/13/2017

QRC-1505568-F006 09/13/2017

QRC-1505568-F007 09/13/2017

1.3 SPECIFICATIONS

a) QRC-1505568 BENTON FLS SPECIFICATIONS 03/04/2019

b) QRC HVAC BID ALTERNATE #1 03/04/2019

c) FAA-STD-019E

d) FAA-C-1217F

e) FAA-C-1391C

f) NFPA 70

1.4 SUBMITTALS

All products & materials used shall meet FAA approval before work begins. Submittals will include the following:

a) Work Schedule

b) Safety and Accident Prevention Plan

c) Emergency medical action plan

d) Bonding and Insurance

e) Description of equipment, cranes, man lift, boom lift, or aerial work platform

f) Certification of Skills & Qualifications. Electrician’s License

g) All materials called out on Part 1.3 Specifications above

h) Firestopping products

i) Fire alarm parts and equipment

j) Paint and coatings

k) Electrical sub panel

l) Electrical conduit and wire

m) Electric unit heaters, heat tape, & heat pumps called out in HVAC Bid Alternate #1

2.0 GENERAL REQUIREMENTS

a.) Contractor will give FAA twenty one day advance notice before construction begins.

b.) All work shall be coordinated, scheduled, & approved by FAA Air Traffic Management and Airway Facilty Management.

c.) QRC ARSR is a NAS critical system that operates 24 hours a day 365 days a year.

d.) QRC ARSR will remain in operation during all work.

e) All Electrical work shall be performed by a Licensed Electrician. FAA may accept license from States outside Pennsylvania if necessary.

f) Contractor shall repair any damage done by him to any entity, at his cost. Contractor shall be covered by minimum locally required liability.

g) Contractor must provide FAA with a safety and security plan before any work begins. Plan will include procedures for accident prevention, emergency procedures, phone number & map to nearest emergency medical facility.

h) Contractor's Superintendent shall be present at the work site during all times work is performed. Superintendent shall carry a cell phone and, be prepared to make and receive calls to & from the FAA at all times while on work site.

2.1 WORK HOURS AND CONDITIONS

a) Contractor will obtain authorization to work from the FAA and be subject to continuous FAA escort.

b) Contractor will report & coordinate each days work in advance with an FAA technician that is trained to operate and repair ARSR equipment.

c) Work will be done during daylight hours between 7:00AM to 4:00PM. Mon thru Fri.

d) Overtime, Saturday & Sunday work will not be allowed unless special circumstances warrant it.

3.0 PRE – BID SITE VISIT

The Contractor is expected to carefully examine the areas of the proposed work, to see first hand the extent of work involved. The submission of a proposal will be considered evidence that the bidder has made such examination and is satisfied as to the conditions to be encountered in performing the work.

The FAA Contracting Officer will provide a date for one official site visit with the Engineer. If any other visits are needed, Contractor must give FAA at least five days advance notice before appearing on site. All visitors must be escorted by an FAA employee, or other authorized personnel.

3.1 REFERENCE MATERIALS

Drawings of the existing building systems will be provided on request.

4.0 LOCATION

QRC ARSR LAT 41` 21’ 26.60” N

48 Mountain Springs Rd #1 LON 76` 17’ 34.53” W

Benton PA 17814 Ph.: 570-477-5611

OTHER: State of Pennsylvania - Red Rock Job Corps Center, P.O. Box 218, Hwy 487 N, Lopez. PA 18628 ph: 570-477-9221, 1-800-495-2234. RRJCC is located in rural Sullivan County adjacent to Ricketts Glen State Park on top of a 2,700’ Red Rock Mountain redro@jcdc.jobcorps.org

5.0 CONTACTS

Cindy Briggs, SSC Mgr. WER14-AVP Richard Polk, FAA Engineering FAA Wilkes-Barre SSC 1701 Columbia Ave AVP SSC, 534 Lidy Rd College Park, GA 30337 Dupont, PA 18641 w:404-305-7445 c:678-485-6811 570-655-7511 x5232 e:mail: richard.polk@faa.gov e:mail cindy.briggs@faa.gov

****END****

mailto:redro@jcdc.jobcorps.org mailto:richard.polk@faa.gov mailto:cindy.briggs@faa.gov

SCOPE OF WORK
QRC ARSR Fire Life Safety Upgrades
Benton Pennsylvania