Phase 2 QA A00003.pdf

PDF 57 KB Posted

Attached to
Technical Expertise and Support Services for the FHWA Office of Safety
Solicitation number
693JJ325R000004_Final
Issued by

About this file

This document is a Questions and Answers (Q&A) file for a Federal Highway Administration (FHWA) solicitation, containing two key clarifications for potential offerors. The first Q&A addresses whether projects in Volume II (Factor 4: Past Performance) must match projects in Volume I (Factor 1: Experience), with the answer being no - though if past performance involves a partner/subcontractor, that entity must have been previously submitted in Volume I. The second Q&A clarifies small business subcontracting plan requirements, specifically confirming that offerors only need to submit Attachment J.3 for the subcontracting plan, and a separate Master Subcontracting Plan is not required, with the RFP language having been updated to reflect this guidance.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

# Reference: Paragraph/Sentence Question Answer

L.6.2, Volume III: Factor 4: Past Performance, Page 65

Do the projects in Volume II Factor 4 Past Performance need to match the projects included in Volume I Factor 1 Experience?

No, the projects identified in Past Performance do not need to match the projects included in Factor 1 Experience.

However, if the past performance is for a partner or subcontractor, the Offeror must have submitted partner/subcontractor info for the at company in Volume I.

2 L.6.2, pages 65-66

For the Volume II small business subcontracting plan requirements (as described in Section L.6.2, page 65-66), we see that FHWA is requesting a Master Subcontracting Plan and the Attachment J.3 Subcontracting Plan. In accordance with FAR 52.219-9, we intend to provide — in Attachment J.3 — the estimated percentage goal and dollar amounts for each subcontract socioeconomic category, and answers for Questions 1.1 to 10. We do not intend to provide a separate Master Subcontracting Plan, since we do not have a firm-wide plan, and FAR 52.219-9 allows for individual plans instead. Can FHWA confirm that our intended approach to only submit Attachment J.3 complies with the requirements of FAR 52.219-9, and that a separate Master Subcontracting Plan is not required? If not, can FHWA clarify what else is needed to remain compliant?

A separate Master Subcontracting Plan is not required - Attachment J.3 is sufficient.

RFP language has been updated.