This is a Questions and Answers document clarifying key requirements and evaluation criteria for RFP 693JF726R000009, a Maritime Administration (MARAD) solicitation for long-term lay berthing services for up to two Watson-class LMSR vessels on the U.S. West Coast. The base contract term is five years, with a ten-year option available for consideration. Proposals are due May 4, 2026, with MARAD typically requiring one month for technical review and award determination.
The Q&A addresses critical submission and evaluation requirements including: permits, licenses, and lease documentation must be submitted with the proposal rather than within 30 days of award; updated soundings (within six months of proposal) may be older at proposal submission if verified with current soundings 30 days prior to contract commencement; the contractor should anticipate approximately two fender removal and installation evolutions annually for moored vessel movements; and evidence of port services availability—such as a list of companies or historical berthing records—is sufficient, with actual letters from three ship repair facilities no longer required. The wind requirement has been reduced from 130 mph to 85 mph due to industry concerns.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP 693JF726R000009 Q&Q
Sec M.1 | Pg 59 The solicitation states layberthing for 5yrs however under section M.1 it states the offeror can provide a 10yr option – please clarify if 10yr options will be considered.
Section M.1 Pg 59: The solicitation is for 5 years.
Sec C-4 (C) | Pg 13 Permits/Licenses/Leases shall be provided (30) days after contract award but in the evaluation criteria it states a lease must be submitted with the proposal – please clarify if lease/ownership documentation must be submitted with the proposal or (30) days after contract award.
Section C-4(C) Submitted with the proposal.
Sec C-8 (A)1 | Pg 21 States that updated soundings (within 6 months) shall be provided 30 days prior to contract commencement. The evaluation criteria in Sec M.3.2 state that the same must be submitted to be found technically acceptable. Please clarify if official sounds can be provided prior to contract commencement. Will the Maritime Administration accept an older set of soundings for the proposal as long as they are verified with updated soundings before contract commencement as stated?
Section C-8 (A)1 Older sounds will be acceptable at time of proposal with updated sounding within 6 months 30 days prior to the contract.
Sec C-10 (A) | Pg 25 This states the contractor is responsible for removing and installing fenders between moored vessels however does not give an amount of estimated ship movements in order to accurately bid. Please provide an annual estimate of evolutions the contract would have to provide removal and installation services for the fenders.
C-10 (A). Roughly 2 evolutions per year.
Sec L.4.1 Factor 4 | Pg 58 Port Services Availability – it states provide letters for OR evidence of but then in Sec M Evaluation Factors for Award it states letters from at least three ship repair facilities. Please clarify if actual letters are needed, and for what services, or simply evidence of. If ships have historically been birthed in proposed area, can that constitute as evidence of?
Section L.4.1 Factor 4. Evidence is sufficient. Letters are not required. If ships were previously berthed at this location, a list of companies is sufficient.
General Question Can an award timeline be provided? MARAD typically takes one month to review proposals for technical accuracy and to make an award.