This is an Environmental Document Reevaluation Form for the Veterans Drive (Route 30) Project in St. Thomas, US Virgin Islands, conducted pursuant to 23 CFR 771.129(c).
The document reevaluates the Federal Highway Administration's May 9, 2017 Finding of No Significant Impact (FONSI) based on an Environmental Assessment (EA). The original Environmental Impact Statement and Record of Decision were approved on October 2, 1984 (Federal Number FHWA-VI-EIS-75-01-F, Project Number DPC-0034(1)). The project, located along Charlotte Amalie Harbor shoreline at coordinates 18.339678°N, -64.933965°W (Station 196+89.25 to Station 264+89.27), proposes to widen and revitalize Veterans Drive into a tree-lined, four-lane, divided roadway with a waterfront pedestrian promenade spanning 1.38 miles. Phase I was completed in December 2021 using GARVEE funds; Phase II (Hospital Gade to Kronprindsens Tvaer Gade) is now being pursued with RAISE Grant funding and has been subdivided into Phase II A and Phase II B. The improvement requires building a new seawall and backfilling approximately 50 feet into the harbor, with the pedestrian promenade varying from 20 to 40 feet in width to accommodate double tree rows between Palm Passage and Tolbod Gade.
The reevaluation determines that no changes to the project design, applicable law, or regulatory requirements have occurred since 2017, and no changes in impacts to social, economic, cultural, natural, or physical resources are identified. The initial USACE Section 10/404 Permit (SAJ-1996-01459) expired July 27, 2022; a new 10-year permit application is expected within three months. The CZM Permit (CZM03-12(L&W)) extension is similarly expected within three months. The FHWA concluded that the Administrative Action remains valid and the project can advance. VISHPO confirmed continued support for project completion. The reevaluation was recommended by USVI Department of Public Works on September 23, 2024, and approved by FHWA on September 23, 2024.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Environmental Document Reevaluation
Conducted Pursuant to 23 CFR 771.129(c)
VETERANS DRIVE (ROUTE 30) PROJECT
RE-EVALUATION FORM
1. GENERAL PROJECT INFORMATION
A. Re-evaluation Type(s): Re-evaluation of the May 9, 2017, FHWA Finding of No Significant Impact (FONSI) based on an Environmental Assessment (EA)
B. Original approved Environmental Document:
Document Type: Environmental Impact Statement (EIS) / Record of Decision (ROD)
Date of Approval: October 2, 1984
Federal Number: FHWA-VI-EIS-75-01-F
Project Numbers: DPC-0034(1)
Federal-Aid Project Name: DPC-0034(1)
Brief History of other Environmental efforts: Since 1984 EIS / ROD project was re-evaluated multiple times and several environmental assessments evaluated in subsequent years to better address public and agency concerns related to cultural resources, natural resources and aesthetic. In 2012, USVI DPW propose to amend the project again. FHWA propose to use an Environmental Assessment to re-evaluate the project and fully consider existing and identified new impacts resulting from proposed changes. The USACE NMFS agreed to be cooperating agencies for the EA. As a result of the EA on May 9, 2017 a Finding of No Significant Impact was determined by FHWA. USACE SAJ-1996-01459 / CZM03-12(L&W)
Project Location: The project is located along the shoreline of Charlotte Amalie Harbor in St. Thomas, US Virgin Islands. The approximate central project coordinates for Phase II are:
Latitude: 18.339678°N
Longitude: -64.933965°W
Project Limits: Station 196+89.25 to Station 264+89.27.
C. Prior Re-evaluation(s): Has this project been previously re-evaluated? Yes [ ] No [X] – See brief history on environmental efforts. However, since the 2017 FONSI the project has not been re-evaluated.
Description of Approval: EA that led to a FONSI in 2017.
D. Project or project segment(s) being evaluated: The Veterans Drive project, as the preferred alternative contained in the 2017 NEPA FONSI, is composed of two phases. The first phase (Phase I) is from the Long Bay Road intersection to Hospital Gade. Construction of this first phase was completed in 2021 using GARVEE funds and is currently in service. The second phase (Phase II) is from Hospital Gade to Kronprindsens Tvaer Gade (Windward Passage Hotel). This second phase (Phase II) was submitted and awarded as the RAISE Grant project. It should be indicated that this second phase (Phase II) has been further divided in two subphases, the first subphase (Phase II A) from Hospital Gade to
Tolbod Gade and the second subphase (Phase II B) from Tolbod Gade to Kronprindsens Tvaer Gade (Windward Passage Hotel).
E. Purpose of Reevaluation the Re-evaluation: The purpose of this reevaluation is due to the time that has lapsed since the most recent approval of environmental document, May 2017. Phase 1 of the project began in 2018 and was successfully completed in December 2021. The Department intends to proceed with the construction of Phase 2 or the remaining segment of the originally proposed work.
2. PROJECT DESCRIPTION:
The United States Virgin Islands through the Department of Public Works, in accordance with the National Environmental Protection Act (NEPA) and associated laws, regulations, and orders proposes to widen and revitalize Veterans Drive to provide a tree-lined, four-lane, divided roadway with a waterfront pedestrian promenade that simultaneously addresses Charlotte Amalie’s congestion problems and creates a signature pedestrian-friendly environment. The work will cover a total area of 1.38 miles from west of Kronprindsens Tvaer Gade (Windward Passage Hotel) to Long Bay Road/W.G. Lewis Lane (formerly Lovers Lane).
The width of the pedestrian promenade varies from 20 to 40 feet, to provide space for a double row of trees between Palm Passage and Tolbod Gade. The proposed improvements will be accomplished by building a new seawall and backfilling it to create additional land on which to construct the improvement.
This will require placing an approximate 50-foot-wide section of fill into the harbor.
Describe the project segment(s) being advanced, and include a brief status of other segments: Phase II as described in section 1D.
3. CHANGES IN APPLICABLE LAW OR REGULATION
Are there changes in federal or state laws, rules, regulations, or guidance that require consideration since the date of the original Environmental Document or subsequent Reevaluation(s)? Yes [ ] No [X]
Describe the changes and as appropriate, including supporting documentation: No changes have occurred.
4. EVALUATION OF MAJOR DESIGN CHANGES AND REVISED DESIGN CRITERIA
Are there major design changes, including but not limited to changes in the alignment(s), typical section(s), drainage/stormwater requirements, design control and criteria, or temporary road or bridge?
Yes [ ] No [X]
Describe the changes and as appropriate, include supporting documentation: Not applicable as the current scope of work is still the same as those evaluated under the most recently approved environmental document (FONSI 2017).
5. PUBLIC INVOLVEMENT
Were there additional public involvement activities? (Meetings, workshops, hearings) Yes [ ] No [X]
Describe public involvement activities and, as appropriate, include supporting documentation: Not applicable as there has not been changes in scope nor changes in circumstances that involve other environmental review laws that have their own public involvement requirements.
6. PROJECT or SEGMENT(S) PLANNING CONSISTENCY
Would only be required as needed: phase change requiring federal funding authorization; or updating previous consistency information.
Is Planning Consistency required for this project segment? Yes [X] No [ ] – Project is included in the latest TTIP.
EVALUATION OF CHANGES IN IMPACTS
a. SOCIAL & ECONOMIC
Are there changes in impacts to the social, economic, land use, mobility, and/or aesthetic effects?
Yes [ ] No [X] N/A [ ]
Are there changes in right-of-way needs? Yes [ ] No [X] N/A [ ]
Is there a change in anticipated relocation(s)? Yes [ ] No [X]
Are there changes in impacts to Prime or Unique Farmlands? Yes [ ] No [X] N/A [ ]
Describe the changes and as appropriate, upload supporting documentation: Not applicable a there have been no changes.
b. CULTURAL
Are there changes in impacts to cultural resources pursuant to Section 106 of the National Historic Preservation Act (historic sites/districts and archaeological sites)? Yes [ ] No [X] N/A [ ]
Are there changes in effects to Section 4(f) of the Department of Transportation Act protected resources, recreational areas, or other protected public lands? Yes [ ] No [X] N/A [ ]
Are there changes in impacts to lands purchased under Section 6(f) of the Land and Water Conservation Fund Act? Yes [ ] No [X] N/A [ ]
Are there changes in impacts to recreational areas or protected lands? Yes [ ] No [X] N/A [ ]
c. NATURAL
Are there changes in impacts to protected species and habitat, wetlands and other surface waters, and/or essential fish habitat? Yes [ ] No [X] N/A [ ]
Are there changes in impacts to designated Aquatic Preserves, Coastal Barrier resources, Wild and Scenic Rivers, and/or Nationwide Rivers Inventory Rivers? Yes [ ] No [X] N/A [ ]
Are there changes in impacts to Floodplains or Water Resources? Yes [ ] No [X] N/A [ ]
d. PHYSICAL
Are there changes in Air Quality? Yes [ ] No [X] N/A [ ]
What is the status of Highway Traffic Noise? Describe the changes and, as appropriate, include supporting documentation – No changes in highway Traffic noise have occurred.
What is the status of Contamination? Provide an update on the status of contamination assessment.
Describe the changes in involvement with potentially contaminated sites and as appropriate, include supporting documentation – No changes in the Contamination status have occurred.
Are there changes in impacts to Utilities and Railroads? Yes [ ] No [X] N/A [ ]
Are there changes in impacts to Navigation? Yes [ ] No [X] N/A [ ]
8. COMMITMENT STATUS
Are there prior commitments from the Environmental Document or previously approved re-evaluation(s)?
Yes [X] No [ ]
Are there new environmental commitments? Yes [ ] No [X] List new environmental commitments added since approval of the original Environmental Document or most recent Re-evaluation.
9. STATUS OF PERMITS
Federal Permit(s):
_X_ USACE Section 10 or Section 404 Permit _Initial Permit expired 7/27/2022 (SAJ-1996-01459).
USACE advised DPW to submit new application for remainder of uncompleted work from original permit. New permit application will be submitted; 10-year permit expected within the next 3 months.
__ USACE Section 408 _____________
__ USCG Bridge Permit _____________
USVI Local Permit(s): CZM Permit (CZM03-12(L&W)) extension expected within the next 3 months.
10. CONCLUSION:
[X] The project has been re-evaluated pursuant to 23 CFR § 771.129. The FHWA has determined that no changes to the project affect the original decision. Therefore, the Administrative Action remains valid and the project can advance.
11. RECOMMENDATION AND APPROVAL
Recommended:
USVI Department of Public Works Date
Approval:
Federal Highway Administration Date
FHWA Remarks:
1 - Enclosed 2017 NEPA FONSI.
2 - As indicated by DPW, VISHPO confirmed that they are still in support of the continuation and completion of the Veterans Drive Project.
3 - We have been informed by DPW that:
a) DPW has been in coordination with USACE related to the application of the new permit and have addressed / updated documents to be submitted as requested by USACE's November 17, 2023 email.
b) Answers to the re-evaluation questions reflect the latest document to be submitted to USACE for permit.
c) Draft DPW documentation enclosed is the same as the one to be submitted to USACE for permit.
| 2024-09-23T16:27:24-0400 | |
| ANDRES ALVAREZ-IBANEZ |
File details come from the government source that posted it. Updated .