Results of Bid Opening - NC NP BLRI 2A16.pdf

PDF 94 KB Posted

Attached to
Blue Ridge Parkway
Solicitation number
693C73-23-B-000013
Issued by

About this file

This document summarizes a bid opening for a federal highway project solicitation. The solicitation was issued by the Eastern Federal Lands Highway Division of the Federal Highway Administration for projects on the Blue Ridge Parkway under number 693C73-23-B-000013. Three bids were received for schedules of work involving road and bridge repairs and improvements. Schedule A involved work estimated at $2.5 million, Schedule B (option 1) was estimated at $2.8 million, and Schedule C (option 2) was estimated at $2.5 million. The low bid was submitted by Kovilic Construction Company at $11 million if all schedules were awarded together, with individual schedule bids ranging from $3.5 to $4.1 million. The highest total bid was $14.2 million from Adams Contracting. The performance period if all schedules were awarded to one bidder would be 327 days, with individual schedules ranging from 246 to 310 days.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Federal Highway Administration

Eastern Federal Lands Highway Division

Bid Opening for

Blue Ridge Parkway

PROJECT: NC NP BLRI 2A16

SOLICITATION NO. 693C73-23-B-000013

August 8, 2023 at 2:00 p.m.

Ashburn, VA

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

BID OPENING for SOLICITATION NO. 693C73-23-B-000013

Project: NC NP BLRI 2A16

August 8, 2023, 2:00 p.m. local time

BIDDERS BID TOTALS TOTAL PRICE

Adams Contracting, LLC SCHEDULE A

$5,345,939.00

SCHEDULE B (GOVERNMENT OPTION 1)

$4,791,558.75

SCHEDULE C (GOVERNMENT OPTION 2)

$4,097,439.25

SCHEDULE A + OPTION 1 + OPTION 2 =

$14,234,937.00

Kovilic Construction Company, Inc. SCHEDULE A

$3,473,167.00

SCHEDULE B (GOVERNMENT OPTION 1)

$4,074,267.00

SCHEDULE C (GOVERNMENT OPTION 2)

$3,496,707.00

SCHEDULE A + OPTION 1 + OPTION 2 =

$11,044,141.00

MC3 Solutions, LC SCHEDULE A

$4,401,790.00

SCHEDULE B (GOVERNMENT OPTION 1)

$4,191,004.00

SCHEDULE C (GOVERNMENT OPTION 2)

$3,904,373.00

SCHEDULE A + OPTION 1 + OPTION 2 =

$12,497,167.0

If the Government awards the contract as Schedules A + B + C, the performance period will be 327 calendar days.

If separate: Schedule A will be 267 calendar days, Schedule B will be 310 calendar days, and Schedule C will be 246 calendar days.

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

BID OPENING for SOLICITATION NO. 693C73-23-B-000013

Project: NC NP BLRI 2A16

August 8, 2023, 2:00 p.m. local time

If the Government awards the contract as Schedules A + B + C, the performance period will be 327 calendar days.

If separate: Schedule A will be 267 calendar days, Schedule B will be 310 calendar days, and Schedule C will be 246 calendar days.

BIDDERS BID TOTALS TOTAL PRICE

Engineer’s Estimate SCHEDULE A

$2,542,000.00

SCHEDULE B (GOVERNMENT OPTION 1)

$2,814,000.00

SCHEDULE C (GOVERNMENT OPTION 2)

$2,540,000.00

SCHEDULE A + OPTION 1 + OPTION 2 =

$7,896,000.00

File details come from the government source that posted it. Updated .