This document summarizes a bid opening for a federal highway project solicitation. The solicitation was issued by the Eastern Federal Lands Highway Division of the Federal Highway Administration for projects on the Blue Ridge Parkway under number 693C73-23-B-000013. Three bids were received for schedules of work involving road and bridge repairs and improvements. Schedule A involved work estimated at $2.5 million, Schedule B (option 1) was estimated at $2.8 million, and Schedule C (option 2) was estimated at $2.5 million. The low bid was submitted by Kovilic Construction Company at $11 million if all schedules were awarded together, with individual schedule bids ranging from $3.5 to $4.1 million. The highest total bid was $14.2 million from Adams Contracting. The performance period if all schedules were awarded to one bidder would be 327 days, with individual schedules ranging from 246 to 310 days.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Highway Administration
Eastern Federal Lands Highway Division
Bid Opening for
Blue Ridge Parkway
PROJECT: NC NP BLRI 2A16
SOLICITATION NO. 693C73-23-B-000013
August 8, 2023 at 2:00 p.m.
Ashburn, VA
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-23-B-000013
Project: NC NP BLRI 2A16
August 8, 2023, 2:00 p.m. local time
BIDDERS BID TOTALS TOTAL PRICE
Adams Contracting, LLC SCHEDULE A
$5,345,939.00
SCHEDULE B (GOVERNMENT OPTION 1)
$4,791,558.75
SCHEDULE C (GOVERNMENT OPTION 2)
$4,097,439.25
SCHEDULE A + OPTION 1 + OPTION 2 =
$14,234,937.00
Kovilic Construction Company, Inc. SCHEDULE A
$3,473,167.00
SCHEDULE B (GOVERNMENT OPTION 1)
$4,074,267.00
SCHEDULE C (GOVERNMENT OPTION 2)
$3,496,707.00
SCHEDULE A + OPTION 1 + OPTION 2 =
$11,044,141.00
MC3 Solutions, LC SCHEDULE A
$4,401,790.00
SCHEDULE B (GOVERNMENT OPTION 1)
$4,191,004.00
SCHEDULE C (GOVERNMENT OPTION 2)
$3,904,373.00
SCHEDULE A + OPTION 1 + OPTION 2 =
$12,497,167.0
If the Government awards the contract as Schedules A + B + C, the performance period will be 327 calendar days.
If separate: Schedule A will be 267 calendar days, Schedule B will be 310 calendar days, and Schedule C will be 246 calendar days.
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-23-B-000013
Project: NC NP BLRI 2A16
August 8, 2023, 2:00 p.m. local time
If the Government awards the contract as Schedules A + B + C, the performance period will be 327 calendar days.
If separate: Schedule A will be 267 calendar days, Schedule B will be 310 calendar days, and Schedule C will be 246 calendar days.
BIDDERS BID TOTALS TOTAL PRICE
Engineer’s Estimate SCHEDULE A
$2,542,000.00
SCHEDULE B (GOVERNMENT OPTION 1)
$2,814,000.00
SCHEDULE C (GOVERNMENT OPTION 2)
$2,540,000.00
SCHEDULE A + OPTION 1 + OPTION 2 =
$7,896,000.00