NC NP BLRI 2A16_Scour_Analysis_Report_Amended.pdf

PDF 237 KB Posted

Attached to
Blue Ridge Parkway Federal contract opportunity
Solicitation number
693C73-23-B-000013
Issued by
Department of Transportation Federal Highway Administration

About this file

This memorandum amends scour countermeasure recommendations for Bridge No. 5140-081P over Brush Creek. The original recommendation proposed using riprap Class 2 for scour protection. However, upon further discussion between bridge, construction, geotechnics, and hydraulics staff, it was determined that Class 2 riprap would be too small and prone to washing away. Class 4 riprap was preferred but deemed difficult to source and construct. As an alternative, the memorandum recommends using Class 3 riprap, which is expected to withstand stream forces better than Class 2 while presenting fewer construction challenges than Class 4. No additional hydraulic analysis was performed to support the amended recommendation.

View the file

Other files for this federal contract opportunity

Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FHWA:W. Hiciano:6218:RF:

M:\PROJECTS\blri\2a16\Techserv\Hydra\Correspondence\BLRI 2A16 Bridge Scour memo CC: Hydraulics, Geotech, Env, HD Engineer, TS Engineer, Bridge

Form FHWA-201 U.S. DEPARTMENT OF TRANSPORTATION (Rev. 11-87) FEDERAL HIGHWAY ADMINISTRATION

MINUTE - MEMO

Use this form in lieu of transmittal slips within Dept. of Trans. when message comment is to be retained as file material. Do not prepare carbons. Not to be used in lieu of Form FHWA-121 for informal correspondence.

SUBJECT: BLRI 2A 16 Scour Countermeasures Amended Recommendations

TO MESSAGE/COMMENT FROM/DATE

Sheila Foronda Project Manager

Ashley Timm Highway Design Manager

This memo intends to summarize the final recommendations provided for Structure No. 5140-081P: Bridge #1 over Brush Creek.

Memo Update:

Scour analysis and design were completed in October 2017. The project had been on standby, until 2021 when the design was resumed for the project. A site field visit was conducted, where discussion between Bridge, Construction, Geotechnical, and Hydraulics team members discussed that the riprap size recommended for the structure for scour countermeasure class 2, would be small and there are concerns that riprap would wash away after a stream event and it was agreed that class 4 would be more suitable and stable.

Construction has brought up the concern that using Class 4, would be a constructability issue, and it is hard to source in the project vicinity, due availability. Based on this information, Hydraulics agrees that installing Class 3 could be used as scour countermeasure for Structure No. 5180-081P, and that riprap Class 3, should be able to withstand stream erodible forces and have better performance than the original recommendation of Class 2.

These changes are not based on additional hydraulic analysis, but on multi-disciplinary discussion. Hydraulic analysis has not been performed, and the need to perform additional hydraulic analysis would require updated stream survey, since the stream has changed since final survey was conducted in early 2016.

For your reference, please refer to the Final Bridge Hydraulics Memo and Scour Memo for any additional information.

Please let us know if you have any questions or concerns.

Wendy Hiciano Hydraulics Team Leader

6/6/2023