Amendment 0001 - NP-GWMP MVT(5).pdf
PDF 223 KB Posted
- Attached to
- George Washington Memorial Parkway Federal contract opportunity
- Solicitation number
- 693C73-23-B-000004
About this file
This document provides an amendment to a solicitation for the George Washington Memorial Parkway project. The amendment extends the bid opening date from November 8, 2022 to November 10, 2022 at 2:00 PM EST. It also provides responses to questions from potential bidders regarding details such as the availability of as-built plans, existing bridge specifications, acceptable work areas and access, in-water work restrictions, and material requirements. Sealed bids from certified Small Business Concerns only will be accepted for replacing two trail bridges. The cost of the project is expected to be between $2,000,000 to $5,000,000. The solicitation number is 693C73-23-B-000004 and is issued by the Eastern Federal Lands Highway Division of the Federal Highway Administration for the National Park Service.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Results of Bid Opening - NP-GWMP MVT(5).pdf | ||
| Amendment 0005 - NP-GWMP MVT(5).pdf | ||
| Amendment 0004 - NP-GWMP MVT(5).pdf | ||
| Amendment 0003 - NP-GWMP MVT(5).pdf | ||
| Amendment 0002 - NP-GWMP MVT(5).pdf | ||
| Geotechnical Report.pdf | ||
| IFB Solicitation - NP-GWMP MVT(5).pdf | ||
| NPS Supplemental Specifications.pdf | ||
| ADV_Bidders Qualifications Form.doc | DOC document | |
| Plans - NP-GWMP MVT(5).pdf | ||
| Categorical Exclusion Form (NEPA).pdf | ||
| FP14_Eng.pdf | ||
| VETS-4212 Form.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
693C7323B000004 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
ASHBURN VA 20147
ATTN: Construction
693C73
SUITE E2-3-300
QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
ASHBURN VA 20147
ATTN: Acquisitions
693C73
SUITE E2-3-300
QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
See Block 1411/07/20220001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
10/05/2022
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Project NP GWMP MVT(5)
The purpose of this Amendment is to:
1. Provide a summary of responses to questions/clarifications asked by potential bidders.
2. Extend the bid opening date from November 8, 2022, to November 10, 2022, at 2:00 p.m.
EST.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Amendment No. 0001
Info Page 1 of 3
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
NP-GWMP MVT(5)
George Washington Memorial Parkway
Solicitation: 693C73-23-B-000004
The purpose of this Amendment is to:
1. Provide a summary of responses to questions/clarifications asked by potential bidders.
2. Extend the bid opening date from November 8, 2022, to November 10, 2022, at 2:00 p.m.
EST.
Questions / Clarifications
The following questions and issues were submitted to EFLHD at eflhd.conracts@dot.gov. The
Government response or clarification is provided. Due to the repetitive nature of several questions and issues, the wording of the questions may have been revised and some questions have not been included. The Government’s direct response to the sender may also have been updated below for better clarity.
1. Are existing as-built plans and inspection reports available?
Response: As-built plans and inspection reports are not available for bridges 23 and
24.
2. On sheet number M03, the alignment of bridge 23 shows what looks like to be an existing center pile supporting existing structure. Please clarify if each pier has 2 or 3 existing timber pile.
Response: The three single less bold circles at each pier seen on M03 are survey points, not piers.
3. Are existing bridges 23 & 24 rated for vehicular loading and if so, what is load capacity/rating?
Response: No information is available on the original bridge design rating, and a current load rating is not available.
4. How deep are the existing timber piles supporting bridges 23 & 24?
Response: No information is available on the existing timber pile depth.
../../../../../../../natr/1e10/Proj_Dev/Eng_Coord/3Advertisement/Amendments/Amendment%201/Final%20Documents/eflhd.conracts@dot.gov
Info Page 2 of 3
5. Do the existing timber piles supporting bridges 23 & 24 need to be fully extracted or would it be acceptable to cut off exposed portion/abandon?
Response: Piles must be removed so that the same holes can be used for the new piles.
Do not leave original materials in place.
6. Per the bridge plan sheets 2, 3, 4, 5, 15 note 1: “Install helical piles at the same location as existing timber piles.” The removal of the existing timber piles will likely create void in ground. Would it be acceptable to offset the proposed helical 3’ from the existing timber pile locations to be an undisturbed area better suited to reach bearing?
Response: No. Install helical piles at the same location as the existing timber piles.
7. Would it be acceptable to build temporary access adjacent/parallel to existing bridge 23 and
24 to facilitate the removal and replacement of bridge? Are wooden laydown mats within the confines of the trail be allowed?
Response: No.
8. Please confirm the helicals are designed by Contractor in accordance with project specification 582. Please also confirm the diameter, thicknesses and helix bearing plates can differ from what is referenced in the Geotechnical report as long as the ultimate pile capacity of 90 kips per pile is achieved.
Response: The helical piles are to be designed by the Contractor according to Section
582. The minimum dimensions for the helical piles as provided in the Geotechnical
Report must be provided.
9. Per specification 156.07(d) on page J-12 of the IFB Solicitation document the contractor can use NPS’s Fort Hunt Road maintenance facility for a staging area. Please advise as to the approximate usable space (i.e. dimensions and total square footage) and if there are personnel/hourly access restrictions.
Response: The useable space for the contractor’s staging area at Fort Hunt
Maintenance facility is approximately 70 ft x 40 ft or 2800 sqft. It is located behind the gate in the maintenance facility. During construction there would be no personnel/hourly access restrictions. The contractor is to provide their own lock on the gate, to daisy chain with the NPS lock, to allow access for both contractor and
NPS.
10. Is the NPS Fort Hunt Road maintenance facility an acceptable location to put a temporary office for Government field office? Is power available and accessible for temporary hook up? Is this site currently accessible for bidders?
Response: The Fort Hunt maintenance facility is not an acceptable field office for the
Government.
Info Page 3 of 3
11. In accordance with EFLHD NEPA Categorical Exclusion Form page 2 “In order to avoid impacts to shortnose and Atlantic sturgeon, a time of year restriction prohibiting all in-water work will be implemented from February 15 to June 30 of any given year.” Since
Bridge 23 is a tidal wetland area, how will the in-water work restriction be defined. For example, would it be acceptable to install a helical pier in 1’ of water at high tide between
February 15 to June 30? Based on review of bid documents and available tidal information, piers 59 through 64 require turbidity curtains – will the in-water work restriction be limited to those piers?
Response: In water work will include any work below the mean high-water level based on available tidal information.
12. Confirm no construction equipment is allowed in wetland.
Response: No construction equipment is allowed in the wetland.
13. What are the design bearing of the existing wooden piles?
Response: No information is available on the design bearing of the existing piles.
14. Can a polymer coating be used for the helical piles?
Response: Provide a galvanized coating, do not use a polymer coating.
15. Can the existing boardwalk support construction equipment necessary to construct the new boardwalk?
Response: It is the contractor’s responsibility to determine the safe installation of the project components based on the advertised documents and permits.
16. Would you accept an oil borne preservative of Copper Napthenate for all wooden members?
Response: The contract requires waterborne copper based preservatives.
17. Would the government consider the use of treated solid SYP grade 1 that match all the dimensions on the plans rather than the glulams?
Response: Perform the contract work according to the bid documents.
18. We will need to weld our steel sleeves on site. Do we have permission to do this welding on the helical pier sleeves?
Response: Perform the contract work according to the bid documents.