This document contains bid opening results for a federal solicitation seeking sign and safety repairs in Puerto Rico. The Eastern Federal Lands Highway Division opened bids on July 28, 2022 for solicitation number 693C73-22-B-000012 to repair signs and guardrails damaged by hurricanes in multiple municipalities. The project was split into three schedules, with five contractors providing total price quotes ranging from $14.2 to $21.4 million. Schedule A repairs were estimated between $7.6 to $11.5 million, Schedule B (optional guardrail repairs) between $4.1 to $8.2 million, and Schedule C (additional optional work) between $0.9 to $1.7 million. The fully awarded contract including all options would need to be completed within 880 calendar days. The engineer's estimate for all work was $16.7 million.
View the file
Other files
Show 40 more
Latest 50 of 51 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Highway Administration
Eastern Federal Lands Highway Division
Bid Opening for
Sign and Safety Repairs – North and South Region in Puerto Rico
PROJECT: PR ER PRMNT RPR (11)
SOLICITATION NO. 693C73-22-B-000012
July 28, 2022 at 2:00 p.m. EST
Ashburn, Virginia
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-22-B-000012
Project: PR ER PRMNT RPR (11)
July 28, 2022, 2:00 p.m. EST
If the Government awards the contract as Schedules A through C, the performance period to complete all contract work will be 880 calendar days. If the Government awards the contract as Schedules A + B, the performance period to complete all contract work will be 880 calendar days. If separate: Schedule A will be 880 calendar days; and Schedule B will be 640 calendar days. If Schedule C is exercised after the award of the original contract, the performance period of the contract will not be extended and the performance of Schedule C work is to be simultaneous with the performance of the executed contract.
BIDDER’S BID TOTALS DAYS TOTAL PRICE
Caribbean Sign Supplies
Manufacturers, Inc
SCHEDULE A
$11,476,113.50
SCHEDULE B (GOVERNMENT OPTION 1)
$8,218,666.00
SCHEDULE C (GOVERNMENT OPTION 2)
$1,733,711.50
SCHEDULE A + OPTION 1 +
OPTION 2 =
$21,428,491.00
Desarrolladora J.A., Inc SCHEDULE A
$10,423,252.00
SCHEDULE B (GOVERNMENT OPTION 1)
$5,912,900.00
SCHEDULE C (GOVERNMENT OPTION 2)
$1,230,018.00
SCHEDULE A + OPTION 1 +
OPTION 2 =
$17,566,170.00
BID OPENING for SOLICITATION NO. 693C73-22-B-000012
Project: PR ER PRMNT RPR (11)
July 28, 2022, 2:00 p.m. EST
If the Government awards the contract as Schedules A through C, the performance period to complete all contract work will be 880 calendar days. If the Government awards the contract as Schedules A + B, the performance period to complete all contract work will be 880 calendar days. If separate: Schedule A will be 880 calendar days; and Schedule B will be 640 calendar days. If Schedule C is exercised after the award of the original contract, the performance period of the contract will not be extended and the performance of Schedule C work is to be simultaneous with the performance of the executed contract.
BIDDER’S BID TOTALS DAYS TOTAL PRICE
JC & Associates Property
Management Group, Inc
SCHEDULE A
$9,150,573.00
SCHEDULE B (GOVERNMENT OPTION 1)
$4,143,260.00
SCHEDULE C (GOVERNMENT OPTION 2)
$876,677.00
SCHEDULE A + OPTION 1 +
OPTION 2 =
$14,170,510.00
JM Caribbean Builders Corp. SCHEDULE A
$10,606,517.00
SCHEDULE B (GOVERNMENT OPTION 1)
$5,384,923.00
SCHEDULE C (GOVERNMENT OPTION 2)
$927,000.00
SCHEDULE A + OPTION 1 +
$16,918,440.00
BID OPENING for SOLICITATION NO. 693C73-22-B-000012
Project: PR ER PRMNT RPR (11)
July 28, 2022, 2:00 p.m. EST
If the Government awards the contract as Schedules A through C, the performance period to complete all contract work will be 880 calendar days. If the Government awards the contract as Schedules A + B, the performance period to complete all contract work will be 880 calendar days. If separate: Schedule A will be 880 calendar days; and Schedule B will be 640 calendar days. If Schedule C is exercised after the award of the original contract, the performance period of the contract will not be extended and the performance of Schedule C work is to be simultaneous with the performance of the executed contract.
BIDDER’S BID TOTALS DAYS TOTAL PRICE
RV Engineering Group Corp. SCHEDULE A
$7,618,187.50
SCHEDULE B (GOVERNMENT OPTION 1)
$6,863,840.00
SCHEDULE C (GOVERNMENT OPTION 2)
$1,534,305.00
SCHEDULE A + OPTION 1 +
OPTION 2 =
$16,016,332.50
ENGINEER’S ESTIMATE SCHEDULE A
$10,960,000.00
SCHEDULE B (GOVERNMENT OPTION 1)
$4,890,000.00
SCHEDULE C (GOVERNMENT OPTION 2)
$805,000.00
SCHEDULE A + OPTION 1 +
$16,655,000.00
File details come from the government source that posted it. Updated .