Results of Bid Opening - Project NP-BLRI 2J17.pdf
PDF 114 KB Posted
- Attached to
- Blue Ridge Parkway
- Solicitation number
- 693C73-21-B-000001
About this file
This document summarizes the results of a bid opening for a federal highway project. Four contractors submitted bids to complete rehabilitation of the Linville River Bridge on the Blue Ridge Parkway, with total bid amounts ranging from $2.2 million to $3.4 million. The lowest bid was submitted by Bryant's Land & Development at $2.2 million, while the engineer's estimate for the project's base work and two options was $2.2 million. Contractors provided proposed schedules of 119 to 142 days to complete the base work and options. The Eastern Federal Lands Highway Division will award the contract for National Park Service Project NP-BLRI 2J17, with work to consist of bridge and approach repairs.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bridge Inspection Report.pdf | ||
| VETS-4212 Form.pdf | ||
| FP14_Eng.pdf | ||
| ADV_Bidders Qualifications Form.doc | DOC document | |
| Plans - NP-BLRI 2J17.pdf | ||
| IFB Solicitation - NP-BLRI 2J17.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Highway Administration Eastern Federal Lands Highway Division
Bid Opening for
Blue Ridge Parkway
PROJECT: NP-BLRI 2J17
SOLICITATION NO. 693C73-21-B-000001
November 3, 2020 at 2:00 p.m. EST Ashburn, VA
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-21-B-000001 Project: NP-BLRI 2J17
November 3, 2020, 2:00 p.m. local time
BIDDER’S BID TOTALS DAYS TOTAL PRICE
Bryant’s Land & Development SCHEDULE A
$2,012,288.75
SCHEDULE B (GOVERNMENT OPTION 1)
$72,589.35
SCHEDULE C (GOVERNMENT OPTION 2)
$125,735.68
SCHEDULE A + OPTION 1 + OPTION 2 =
$2,210,613.78
JHC Corporation SCHEDULE A
$2,678,304.00
SCHEDULE B (GOVERNMENT OPTION 1)
$393,489.00
SCHEDULE C (GOVERNMENT OPTION 2)
$356,046.00
SCHEDULE A + OPTION 1 + OPTION 2 =
$3,427,839.00
GC Works Inc. SCHEDULE A
$1,749,733.50
SCHEDULE B (GOVERNMENT OPTION 1)
$831,047.00
SCHEDULE C (GOVERNMENT OPTION 2)
$254,617.75
SCHEDULE A + OPTION 1 + OPTION 2 =
$2,835,398.25
If the Government awards the contract as Schedules A + B + C, the performance period to complete all contract work will be 142 calendar days. If separate: Schedule A will be 119 calendar days; Schedule B will be 83 calendar days; and Schedule C will be 39 calendar days.
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-21-B-000001 Project: NP-BLRI 2J17
November 3, 2020, 2:00 p.m. local time
BIDDER’S BID TOTALS DAYS TOTAL PRICE
Kovilic Construction CO, Inc. SCHEDULE A
$2,120,310.00
SCHEDULE B (GOVERNMENT OPTION 1)
$482,439.00
SCHEDULE C (GOVERNMENT OPTION 2)
$276,196.00
SCHEDULE A + OPTION 1 + OPTION 2 =
$2,878,945.00
SCHEDULE A
SCHEDULE B (GOVERNMENT OPTION 1)
SCHEDULE C (GOVERNMENT OPTION 2)
SCHEDULE A + OPTION 1 + OPTION 2 =
ENGINEER’S ESTIMATE SCHEDULE A
$1,615,000.00
SCHEDULE B (GOVERNMENT OPTION 1)
$490,000.00
SCHEDULE C (GOVERNMENT OPTION 2)
$120,000.00
SCHEDULE A + OPTION 1 + OPTION 2 =
$2,225,000.00
If the Government awards the contract as Schedules A + B + C, the performance period to complete all contract work will be 142 calendar days. If separate: Schedule A will be 119 calendar days; Schedule B will be 83 calendar days; and Schedule C will be 39 calendar days.
| Slide Number 1 |
| �FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-21-B-000001� Project: NP-BLRI 2J17�November 3, 2020, 2:00 p.m. local time � |
| �FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-21-B-000001� Project: NP-BLRI 2J17�November 3, 2020, 2:00 p.m. local time � |
File details come from the government source that posted it. Updated .