Results of Bid Opening - Project NP-BLRI 2J17.pdf

PDF 114 KB Posted

Attached to
Blue Ridge Parkway
Solicitation number
693C73-21-B-000001
Issued by

About this file

This document summarizes the results of a bid opening for a federal highway project. Four contractors submitted bids to complete rehabilitation of the Linville River Bridge on the Blue Ridge Parkway, with total bid amounts ranging from $2.2 million to $3.4 million. The lowest bid was submitted by Bryant's Land & Development at $2.2 million, while the engineer's estimate for the project's base work and two options was $2.2 million. Contractors provided proposed schedules of 119 to 142 days to complete the base work and options. The Eastern Federal Lands Highway Division will award the contract for National Park Service Project NP-BLRI 2J17, with work to consist of bridge and approach repairs.

View the file

Other files

File Type Posted
Bridge Inspection Report.pdf PDF
VETS-4212 Form.pdf PDF
FP14_Eng.pdf PDF
ADV_Bidders Qualifications Form.doc DOC document
Plans - NP-BLRI 2J17.pdf PDF
IFB Solicitation - NP-BLRI 2J17.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Federal Highway Administration Eastern Federal Lands Highway Division

Bid Opening for

Blue Ridge Parkway

PROJECT: NP-BLRI 2J17

SOLICITATION NO. 693C73-21-B-000001

November 3, 2020 at 2:00 p.m. EST Ashburn, VA

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

BID OPENING for SOLICITATION NO. 693C73-21-B-000001 Project: NP-BLRI 2J17

November 3, 2020, 2:00 p.m. local time

BIDDER’S BID TOTALS DAYS TOTAL PRICE

Bryant’s Land & Development SCHEDULE A

$2,012,288.75

SCHEDULE B (GOVERNMENT OPTION 1)

$72,589.35

SCHEDULE C (GOVERNMENT OPTION 2)

$125,735.68

SCHEDULE A + OPTION 1 + OPTION 2 =

$2,210,613.78

JHC Corporation SCHEDULE A

$2,678,304.00

SCHEDULE B (GOVERNMENT OPTION 1)

$393,489.00

SCHEDULE C (GOVERNMENT OPTION 2)

$356,046.00

SCHEDULE A + OPTION 1 + OPTION 2 =

$3,427,839.00

GC Works Inc. SCHEDULE A

$1,749,733.50

SCHEDULE B (GOVERNMENT OPTION 1)

$831,047.00

SCHEDULE C (GOVERNMENT OPTION 2)

$254,617.75

SCHEDULE A + OPTION 1 + OPTION 2 =

$2,835,398.25

If the Government awards the contract as Schedules A + B + C, the performance period to complete all contract work will be 142 calendar days. If separate: Schedule A will be 119 calendar days; Schedule B will be 83 calendar days; and Schedule C will be 39 calendar days.

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

BID OPENING for SOLICITATION NO. 693C73-21-B-000001 Project: NP-BLRI 2J17

November 3, 2020, 2:00 p.m. local time

BIDDER’S BID TOTALS DAYS TOTAL PRICE

Kovilic Construction CO, Inc. SCHEDULE A

$2,120,310.00

SCHEDULE B (GOVERNMENT OPTION 1)

$482,439.00

SCHEDULE C (GOVERNMENT OPTION 2)

$276,196.00

SCHEDULE A + OPTION 1 + OPTION 2 =

$2,878,945.00

SCHEDULE A

SCHEDULE B (GOVERNMENT OPTION 1)

SCHEDULE C (GOVERNMENT OPTION 2)

SCHEDULE A + OPTION 1 + OPTION 2 =

ENGINEER’S ESTIMATE SCHEDULE A

$1,615,000.00

SCHEDULE B (GOVERNMENT OPTION 1)

$490,000.00

SCHEDULE C (GOVERNMENT OPTION 2)

$120,000.00

SCHEDULE A + OPTION 1 + OPTION 2 =

$2,225,000.00

If the Government awards the contract as Schedules A + B + C, the performance period to complete all contract work will be 142 calendar days. If separate: Schedule A will be 119 calendar days; Schedule B will be 83 calendar days; and Schedule C will be 39 calendar days.

Slide Number 1
�FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-21-B-000001� Project: NP-BLRI 2J17�November 3, 2020, 2:00 p.m. local time �
�FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-21-B-000001� Project: NP-BLRI 2J17�November 3, 2020, 2:00 p.m. local time �

File details come from the government source that posted it. Updated .