5140-204T3188_Redacted.pdf
PDF 4 MB Posted
- Attached to
- Blue Ridge Parkway Pavement Preservation FY19
- Solicitation number
- 693C73-20-R-000002
About this file
This document contains a bridge inspection report and related federal contract opportunity notice. The bridge inspection report provides details of a routine inspection conducted on June 26, 2013 of the Headquarters Pedestrian Bridge located on the Blue Ridge Parkway. The three-span weathering steel through truss bridge was found to be in generally good condition with some minor issues including rock accumulation, vegetation growth, and a broken paving stone. Cost estimates are provided for recommended maintenance and rehabilitation work.
The related federal contract opportunity is a notice for proposals for the Blue Ridge Parkway Pavement Preservation FY19 project. The project involves pavement preservation of approximately 53.40 miles of roadway on the Blue Ridge Parkway through thin asphalt overlay or chip seal overlay with fog seal treatments. The solicitation number is 693C73-20-R-000002 and proposals are being accepted for work to be completed by December 11, 2020. Offerors must demonstrate experience in one of the pavement preservation treatment methods. The contract value is estimated between $1-5 million and will be awarded by the Department of Transportation Federal Highway Administration.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BRIDGE INSPECTION REPORT
HEADQUARTERS PEDESTRIAN BRIDGE
TRAIL OVER SWAMP
BLUE RIDGE PARKWAY
LW
STRUCTURE NO. 5140-204T
INSPECTION TYPE: ROUTINE
INSPECTION DATE: 6/26/13
Report prepared by: NS
Federal Highway Administration Federal Lands Bridge Office Bridge Inspection and Management Program 21400 Ridgetop Circle Sterling, Virginia 20166 http://www.efl.fhwa.dot.gov/FLHBO/BIP http://www.efl.fhwa.dot.gov/FLHBO/BIP
STRUCTURE SUMMARY STRUCTURE NO. 5140-204T
HEADQUARTERS PEDESTRIAN BRIDGE INSPECTION DATE: 6/26/13
BRIDGE IDENTIFICATION AND DESCRIPTION
MAIN SPAN MATERIAL:
MAIN SPAN TYPE:
# OF BEAMS, MAIN SPAN: ..
DECK TYPE:
WEARING SURFACE:
ABUT. FOUNDATIONS:
PIER FOUNDATION(S):
ABUTMENT / PIER MAT'L: ...
PROJ./PLAN REF. NO:
NPS ROAD CLASS:
STRUCTURE HISTORY:
STEEL
TRUSS - THRU
CONCRETE CAST-IN-PLACE
NONE
SPREAD FTG ON BEARING MAT'L
SPREAD FTG ON BEARING MAT'L
MASONRY / STEEL
5 - ADMINISTRATIVE
NO. OF MAIN SPANS:
NO. OF APPR. SPANS:
STRUCT. TOTAL LENGTH: ..
MAX. SPAN LENGTH:
DECK WIDTH:
CURB TO CURB WIDTH:
YEAR BUILT:
YEAR RECONSTRUCTED: ..
SKEW ANGLE:
FRACTURE CRITICAL:
181.0 FT (55.2 M)
60.2 FT (18.3 M)
8.9 FT (2.7 M)
7.9 FT (2.4 M)
N/A
0 °
YES
LOCATION
BLUE RIDGE PARKWAY MILE POINT: ..................... 0.00 (KM PT 0.00)
STATE: ................................. NORTH CAROLINA LOCATION: Between Visitor Center Parking Lot and Park Headquarters Building. FACILITY CARRIED: ............ TRAIL
FEATURE INTERSECTED: .. SWAMP
STRUCTURE EVALUATION SUMMARY
This weathering steel through truss bridge is in good condition overall. Problems include a moderate accumulation of rock on the abutment bearing seats, moderate vine growth on the east pier, and a broken paving stone on the north side of the west approach. There is up to 2" of soil in a recess in the west abutment bearing seat, but it appears to have been constructed in this manner.
Corrective action should be taken as outlined in this report to prevent the possible development of more serious or costly problems in the future.
INSPECTION TEAM: D. KENT, C. MARBURGER (GANNETT FLEMING)
CONDITION ASSESSMENT:
DANIEL E. KENT, P.E., FIELD TEAM LEADER
REPORT REVIEW :
MARCUS MILLER, P.E., SENIOR INSPECTION ENGINEER 703-404-6252
REPORT APPROVAL: DATE: 10/31/13
JORGOMAI CEESAY, PH.D., P.E., BIP SUPERVISORY ENGINEER 703-404-6244
RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 5140-204T
A (Critical) - Structure is closed, in imminent danger of collapse, or presents a critical safety hazard.
B (Major) - Structure is seriously deficient or presents a safety hazard, but can remain in service at reduced loads or with frequent inspections.
C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.
D (Minor) - Structure is generally in good condition. Preventative maintenance may be required.
E (Special) - Structure is under construction or reconstruction.
D226 PRIORITY OF IMPROVEMENT
ITEM
NO.
MAINTENANCE RECOMMENDATIONS
(GENERALLY NOT FLHP ELIGIBLE)
QTY. UNIT COST
UNIT
ESTIMATE
COST
PRELIM.
60.3 REMOVE ROCK ACCUMULATION FROM ABUTMENT BEARING SEATS. 1 LS $
60.14 PERIODICALLY REMOVE VINE GROWTH FROM BENTS. 1 LS
222.4 REPLACE BROKEN PAVING STONE ON NORTH SIDE OF WEST APPROACH. 1 LS
PRELIM. MAINTENANCE TOTAL :
ITEM
NO.
REHABILITATION/RECONSTRUCTION
(TYPICALLY NEEDED WITHIN 5 YEARS)
QTY. UNIT
UNIT
COST ESTIMATES
PRELIM. COST
REHAB. RECONSTR.
PRELIM. REHABILITATION/RECONSTRUCTION TOTAL :
COST ESTIMATE SUMMARY
PRELIM. MAINTENANCE TOTAL:
PRELIM. REHABILITATION TOTAL:
PRELIM. RECONSTRUCTION TOTAL: ..
TOTAL ITEMIZED COSTS:
PRELIMINARY ESTIMATE TOTAL* :
(*Includes typical contract costs for mobilization, traffic control, and design/construction engineering; but does not include detour bridges, work beyond the bridge limits, or work not listed above. Estimates are approximate and are for preliminary planning purposes only; they should not be used as a complete or final engineers estimate.)
REMARKS: Cost estimates assume that recommended actions will be combined with similar work being performed on other structures.
FIELD INSPECTION REPORT STRUCTURE NO. 5140-204T
CONDITION RATING CODES FOR ITEMS 58 - 62, 222, 223
N NOT APPLICABLE 3 SERIOUS CONDITION - loss of section, deterioration, spalling, or scour have seriously affected primary structural components. Local failures are possible.
9 EXCELLENT CONDITION Fatigue cracks in steel or shear cracks in concrete may be present.
8 VERY GOOD CONDITION - no problems noted. 2 CRITICAL CONDITION - advanced deterioration of primary structural elements. Fatigue cracks in steel or shear cracks in concrete may be present
7 GOOD CONDITION - some minor problems. or scour may have removed substructure support. Unless closely monitored it may be necessary to close the structure until corrective action can be taken.
6 SATISFACTORY CONDITION - structural elements show some minor deterioration. 1 “IMMINENT” FAILURE CONDITION - major deterioration or section loss present in critical structural components or obvious vertical or horizontal
5 FAIR CONDITION - all primary structural elements are sound but may have movement affecting structure stability. Structure is closed to traffic but minor section loss, cracking, spalling, or scour. corrective action may return structure to light service.
4 POOR CONDITION - advanced section loss, deterioration, spalling, or scour. 0 FAILED CONDITION - out of service; beyond corrective action.
CONDITION RATING CODE EQUIVALENTS FOR SUB-ELEMENTS
G = GOOD (CODES 7 - 9) F = FAIR (CODES 5 - 6) P = POOR (CODES 0 - 4)
58. DECK 8 ITEM REFERENCE AND REMARKS
G1. DECK SLAB
G2. EXPANSION JOINTS
N3. WEARING SURFACE
G4. RIDEABILITY
N5. CURBS, SIDEWALKS, AND MEDIAN
G6. PARAPETS AND/OR RAILINGS
G7. DRAINS AND DRAINAGE
N8. UTILITIES
G9. DEFLECTION AND/OR VIBRATION
N10. OTHER
59. SUPERSTRUCTURE 8
G1. BEARING DEVICES
N2. GIRDERS OR BEAMS
N3. ARCH(ES) OR SLAB(S)
G4. FLOOR BEAMS AND STRINGERS
G5. TRUSSES
G6. DIAPHRAGMS AND BRACING
N7. PAINT
N8. FASCIA(E)
G9. DEFLECTION AND/OR VIBRATION
G10. ALIGNMENT
N11. OTHER
60. SUBSTRUCTURE 8
58.1 CAST-IN-PLACE CONCRETE DECK WITH STAY-IN-PLACE FORMS.
MINOR DEPRESSION ON DECK SURFACE NEAR EAST ABUTMENT.
58.1, 59.5, 60.14
NUMEROUS WASP AND HORNET NESTS; SOME INSIDE
STRUCTURAL TUBING.
58.6 ALUMINUM HANDRAILS MOUNTED TO BOTH TRUSSES.
60.3 UP TO 2" OF SOIL FILLS RECESS IN BEARING SEAT AT WEST
ABUTMENT, POSSIBLY CONSTRUCTED IN THIS MANNER.
MODERATE ROCK ACCUMULATION ON NORTHWEST AND EAST
ABUTMENT ABUTMENT BEARINGS.
60.4 MINOR SPALLING WITH EXPOSED FORM TIES IN WEST ABUTMENT
BACKWALL.
60.14 MODERATE VINE GROWTH ON EAST BENT.
ABUTMENTS
BREASTWALLS OR COLUMNS1. G
PILE BENTS2. N
CAPS AND/OR BEARING SEATS3. G
BACKWALLS AND/OR BULKHEADS4. G
FOUNDATIONS5. N
WINGWALLS6. G
WEEP HOLES7. N
EXPANSION JOINTS8. N
EROSION AND/OR SCOUR9. G
SETTLEMENT OR DEFLECTION10. G
SLOPE PROTECTION11. N
OTHER 12. N
PIER(S)
WALLS AND/OR COLUMNS 13. N
PILE BENTS14. G
CAPS AND/OR BEARING SEATS15. G
FOUNDATIONS16. G
EROSION AND/OR SCOUR17. G
SETTLEMENT OR DEFLECTION18. G
OTHER 19. N
FIELD INSPECTION REPORT STRUCTURE NO. 5140-204T
ITEM REFERENCE AND REMARKS
STREAM BED COMPOSITION : 9.
AVERAGE CLEAR OPENING 8.
NORMAL VELOCITY 7.
ADEQUACY OF OPENING 6.
OTHER 5.
WATERWAY OBSTRUCTIONS 4.
CHANNEL PROTECTION3.
EROSION AND/OR SCOUR2.
ALIGNMENT1.
61. CHANNEL N
222. APPROACHES 8
OTHER 9.
ALIGNMENT 8.
SIGNS7.
SETTLEMENT 6.
EROSION5.
SURFACING4.
APPROACH GUARDRAIL 3.
2. RELIEF JOINTS
APPROACH SLABS1.
(BOLLARDS)
N N G G G G G G G
223. RETAINING WALL N
OTHER 6.
SETTLEMENT OR DEFLECTION5.
EROSION AND/OR SCOUR4.
FOUNDATION3.
WEEP HOLES2.
1. WALL
36. TRAFFIC AND SAFETY FEATURES
APPROACH GUARDRAIL ENDSD.
APPROACH GUARDRAILSC.
TRANSITIONSB.
BRIDGE RAILINGSA. 1
N N
222.4 BROKEN PAVING STONE ON NORTH SIDE OF WEST APPROACH.
222.6 MINOR SETTLEMENT OF PAVING STONES AT WEST APPROACH.
222.7 "OFFICE HOURS MONDAY-FRIDAY 8:30AM-4:30PM" SIGN POSTED ON
NORTHEAST APPROACH GUARDRAIL. BUILDING DEDICATION
PLAQUE AT SOUTHEAST APPROACH.
222.9 STEEL BOLLARDS AT EAST APPROACH.
TRAFFIC SAFETY RATING CODES
N
Does not meet standards or a safety feature is required and none is provided.
Meets currently acceptable standards.
Not applicable or a safety feature is not required.
APPENDIX STRUCTURE NO. 5140-204T
PHOTOGRAPHS STRUCTURE NO. 5140-204T
PHOTO #1 - LOOKING EAST TOWARD PARKING LOT
PHOTO #2 - SOUTH SIDE
PHOTO #3 - GENERAL TOP SIDE VIEW LOOKING EAST
PHOTO #4 - GENERAL UNDERSIDE VIEW OF EAST SPAN LOOKING
WEST
PHOTO #5 - TYPICAL APPROACH RAILING,
NORTHEAST RAILING SHOWN
PHOTO #6 - TYPICAL JOINT AT BRIDGE END,
EAST END SHOWN
PHOTO #7 - DEPRESSION IN CONCRETE DECK NEAR EAST ABUTMENT
PHOTO #8 - TYPICAL CONDITION OF PIER BEARINGS, NORTH BEARING
AT EAST PIER SHOWN FROM DECK; NOTE VEGETATION
PHOTO #9 - TYPICAL CONDITION OF
WEATHERING STEEL AND ALUMINUM
HANDRAIL
PHOTO #10 - TYPICAL JOINT COVER OVER
PIERS, EAST PIER SHOWN
PHOTO #11 - BROKEN STONE ON NORTH SIDE OF WEST APPROACH
PHOTO #12 - SOUTH TRUSS AND RAIL
PHOTO #13 - GENERAL VIEW OF EAST ABUTMENT; NOTE ROCK
ACCUMULATION
PHOTO #14 - SOUTH BEARING AT EAST ABUTMENT; NOTE ROCK
ACCUMULATION, NORTH BEARING SIMILAR
PHOTO #15 - TYPICAL CONDITION OF
WEATHERING STEEL FLOOR BEAMS AND
BRACING
PHOTO #16 - GENERAL VIEW OF EAST PIER;
NOTE VEGETATION GROWTH
PHOTO #17 - GENERAL UNDERSIDE VIEW OF
CENTER SPAN LOOKING EAST
PHOTO #18 - GENERAL VIEW OF WEST PIER
PHOTO #19 - TYPICAL CONDITION OF PIER BEARINGS, NORTH
BEARING AT WEST PIER SHOWN
PHOTO #20 - TYPICAL PIER FOUNDATION, NORTH FOOTING AT WEST
PIER SHOWN
PHOTO #21 - GENERAL VIEW OF WEST
ABUTMENT
PHOTO #22 - SOIL ACCUMULATION IN RECESS
IN WEST ABUTMENT BEARING SEAT
PHOTO #23 - NORTH BEARING AT WEST ABUTMENT; NOTE SOIL AND
ROCK ACCUMULATION
PHOTO #24 - SOUTH BEARING SEAT AT WEST ABUTMENT; NOTE SOIL
AND ROCK ACCUMULATION
PHOTO #25 - TYPICAL SPALLING WITH EXPOSED FORM TIE ON WEST
ABUTMENT BACKWALL