This is an Amendment of Solicitation/Modification of Contract (Standard Form 30) issued by the Maritime Administration, Division of Atlantic Operations, located in Norfolk, Virginia. The amendment is numbered 0003 with an effective date of August 18, 2026, and pertains to solicitation 6933A226Q000015 dated July 31, 2026. The contract is for JRRF Trestle Pier Repair services.
The amendment responds to nine vendor questions and provides clarifications on contract requirements. Key responses include: (1) no bid bond is required based on estimated dollar value; (2) performance and payment bonds are not mandatory under FAR Part 28 based on project cost; (3) personnel must possess Real ID or acceptable identification and appropriate personal protective equipment including steel-toed shoes, hard hats, and personal flotation devices for water work; (4) portable toilets will be available; (5) a laydown area will be provided for materials and equipment; (6) floating platforms are permitted but must be contractor-provided; (7) guardrail systems must meet OSHA safety standards with flat-top rails at 36 inches and mid-rails at 18 inches above finished deck; (8) hot-dip galvanized hardware meeting ASTM A153 standards is acceptable, with 316 Stainless Steel required for main walkway boards; and (9) the Contractor Superintendent may serve concurrently as Quality Control Manager and Site Safety and Health Officer if the individual independently meets all three position qualifications, including construction supervision experience, valid Construction Quality Management certification, and 30-hour OSHA Construction card with EM 385-1-1 training.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Trestle Amendment 0002.pdf | ||
| Trestle Amendment 0001.pdf | ||
| Trestle Pier repair SOW.pdf | ||
| Trestle WD.gov.pdf | ||
| RFQ 6933A226Q000015 JRRF Trestle Pier Repair.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
WILLIAM A. WILE
See continuation page
MARITIME ADMINISTRATION
DIVISION OF ATLANTIC OPERATIONS
7737 HAMPTON BLVD BLDG 19 STE 300
NORFOLK VA 23505
6933A2
6933A226Q000015
08/18/2026
07/31/2026
1 4
8/18/2026 william.wile Alans Stamp
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
6933A226Q000015/0003
JRRF Trestle Pier Repair
This amendment responds to questions from a vendor. See below:
1. Is a Bid Bond required for this Contract?
Under federal contracting law, no mandatory federal requirement exists for a bid bond on this construction project based on the estimated dollar value.
2. Are Payment and Performance Bonds required for this Contract?
Under federal law (FAR Part 28), performance and payment bonds are not mandatory for this construction project based on the estimated dollar value.
3. Will workers be required to meet any special security requirements to gain access and work within the secured area?
All personnel will be required to have a Real ID or another acceptable form of Id for entry to the base.
Workers must have steel-toed shoes, hard hats, and personal flotation devices for work over the water as is required by OSHA.
4. Will on-site restroom facilities be available for workers, or will a portable toilet be required near the work area?
The facility can make portable toilets available for workers during the project period.
5. Will a designated Laydown Area be provided for the Contractor’s materials and equipment?
An area will make an area available for laydown of materials and equipment.
6. Will the use of a floating platform be permitted to perform the reconstruction work?
A floating platform can be used, however, the facility does not have one available, so the contractor would need to provide it.
7. What are the requirements for the integrated handrail system? Would a guardrail system consisting of a flat-top rail at 36 inches above the finished deck and a mid-rail at 18 inches above the finished deck, installed between each set of pilings, be acceptable?
Yes, this would be acceptable, our requirement is that it meets all required OSHA safety standards regarding handrails.
8. Is hot-dip galvanized hardware acceptable for use on this project?
This is acceptable as long as it meets ASTM A153 standards for use in brackish water areas. However, 316 Stainless would be required for the main walkway boards.
9. Can the Superintendent also serve as the Quality Control Manager (QC) and Site Safety and Health Officer (SSHO) for this project?
Yes, the Contractor Superintendent may also serve as the Quality Control Manager (QC) and Site Safety and Health Officer (SSHO) since this project falls below major threshold triggers (such as the Simplified Acquisition Threshold, currently set at $350,000) based on the estimated dollar value. However, the single individual must still independently satisfy the qualifications for all three positions:
• Superintendent: Demonstrated construction supervision experience.
• QCM: Valid Construction Quality Management (CQM) for Contractor’s certification.
• SSHO: 30-hour OSHA Construction card, EM 385-1-1 training, and required safety experience.
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .