This document is an Amendment 0003 Questions and Answers (Q&A) for a Maritime Administration (MARAD) contract (Solicitation Number 6933A225Q000008) for drydocking and repairing vessel FB218 at the James River Reserve Fleet. The Q&A addresses ten specific technical questions from the contractor regarding project details, including clarifications on general requirements, structural repairs, materials specifications, and contract performance parameters. Key clarifications include confirmation of growth work procedures, specification of material requirements for deck hatch gaskets and rub-rails, zinc anode installation methods, and agreement to extend the performance period from 60 to 90 calendar days to accommodate the scope of work involving bulwark removal and paint system reapplication.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 0003 Questions and Answers
QUESTION 1 Paragraph 2.1.1 of Item 2 states "Provide the required drydocking facilities as outlined in "General Requirements" section of this specification and drydock the vessel." There is no General Requirements section in the specifications provided. Please clarify and provide the General Requirements.
Under 1. Services, items 1.1. through 1.16 are what we consider the General Requirements.
TITLE: DRYDOCKING
PARA. NO: 2.1.1
QUESTION 2 Paragraph 3.3.2 of item 3 states "Repair any damaged or eroded metal found after removal of bulwarks." Contractor assumes that these efforts will be considered Growth Work and subject to equitable adjustment after the exact scope of repair is determined. Please confirm.
Any HIDDEN damage or eroded metal found would require a Condition Found Report (CFR) and should be considered Growth Work.
TITLE: PLATE RENEWAL
AND
STRUCTURAL REPAIRS
PARA. NO: 3.3.2
QUESTION 3 Paragraph 3.3.4 of item 3 states "Crop out and remove all defective plating and any structural members or interferences as indicated by the COR." Contractor assumes that these efforts will be considered Growth Work and subject to equitable adjustment after the exact scope of repair is determined. Please confirm.
If the work is open to inspection prior to start of contract, that work, to include labor and materials, should be captured in the original bid. Growth work would occur if contracted quantities (labor or materials) are exceeded due to conditions found and a CFR will have to be submitted.
TITLE: PLATE RENEWAL
AND
STRUCTURAL REPAIRS
PARA. NO: 3.3.4
QUESTION 4 Please provide the size and type of material required for the sixteen (16) deck hatch gaskets/seals.
3/4" X 1-1/4" Black Rubber
TITLE: DECK HATCHES
PARA. NO: 5.1
QUESTION 5 Please provide the type, size and material required for the 10-feet of missing rub-rails/bumpers.
Black Rubber Material Base Width 10" Height 9-3/4"
TITLE: RUB-
RAILS/BUMPERS
PARA. NO: 6.1
QUESTION 6 Are the new zincs/sacrificial anodes weld on or bolt on?
We believe they are weld-on but have no way of confirming. If this is not the case the contractor should submit a CFR stating this. TITLE: ZINC
REPLACEMENT
PARA. NO: 7.1
QUESTION 7 The title of Item 9 is contradictory within itself. Is the area being addressed the Line of Flotation and Below or freeboard up to main deck? Please clarify and item 9 title as needed.
Remove "Including freeboard up to main deck:" after the first colon.to get the correct title.
TITLE: PAINTING (Line of Flotation and Below): Including freeboard up to main deck:
PARA. NO: 9 (Item Title)
QUESTION 8 Paragraph 13.1 of Item 13 requires the contractor to provide a fully burdened labor rate for an estimated amount of labor hours for additional work…and/or new work discovered during the performance of the contract. Line Item # 13 on MARAD provided Pricing/Bid document has a quantity of 1 Job. Does the customer want the contractor to insert a labor rate in the Labor Rate column for one (1) manhour? Please clarify.
Yes, any growth work will have a cost, capturing that cost will be used in budgeting and prioritizing growth work.
TITLE: SUPPLEMENTAL
GROWTH WORK
PARA. NO: 13.1
QUESTION 9 Paragraph 3.3.1 requires the contractor to remove the bulwarks on the main deck. This requires the installation and repositioning of staging and the removal of the paint system in each tank or void under the main deck. The paint system will have to be reapplied after the bulwark is removed. The contractor does not believe that the 60-day performance period is sufficient to complete the scope of work. The contractor recommends the performance period be extended to 90 calendar days.
90 calendar days is reasonable.
TITLE: Plate Renewal and Structural Repairs
PARA. NO: 3.3.1
QUESTION 10 Please provide the linear footage of exterior D-rubber fender for removal and re-installation per paragraphs
8.3.3 and 11.2.
100 linear feet + or - 1 foot.
TITLE: Hull Cleaning and Painting
PARA. NO: 8.3.3 and 11.2