MT NP GLAC 14(5), Many Glacier Road Landslides
Solicitation number
69056726B000015
Issued by

About this file

Project Solicitation Summary – MT NP GLAC 14(5), Many Glacier Road Landslides

This is a federal construction project solicitation for roadway reconstruction on the Many Glacier Road in Glacier County, Montana, approximately 4 miles west of Babb. The project encompasses approximately 2.55 miles of roadway and includes excavation, subgrade stabilization, roadway aggregate and asphalt concrete pavement placement, rock buttressing, riprap revetments, drainage improvements, and utility infrastructure. The estimated price range is between $20,000,000 and $30,000,000, with a tentative solicitation date in February or March 2027 and a tentative fixed completion date of Summer 2029 for both the base scope and Option A (Utility Relocation).

Work is specified using FP-24 specifications and includes Division 150 (Project Requirements) items such as mobilization, construction survey and staking, contractor quality control, and soil erosion control; Division 200 (Earthwork) with clearing, grubbing, roadway excavation (15,100 cubic yards), subexcavation (26,000 cubic yards), select borrow (25,700 cubic yards), and geotextile materials; Division 250 (Slope Reinforcement) including placed riprap classes 2-4 (totaling 6,120 cubic yards) and mechanically-placed rock buttress (3,300 cubic yards); Division 300 (Aggregate and Base Courses) requiring 21,500 tons of roadway aggregate; Division 400 (Asphalt Pavements) with 8,500 tons of asphalt concrete pavement and related treatments; and Division 600 (Incidental Construction) encompassing pipe culverts ranging from 18 to 60 inches in diameter, underdrain systems, gates, cattleguards, stone masonry, equipment rental hours, turf establishment, pavement markings, and extensive temporary traffic control measures including flaggers, pilot cars, and traffic control supervisors.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MT NP GLAC 14(5), Many Glacier Road Landslides

Glacier, Montana

Work consists of approximately 2.5 miles of roadway reconstruction including excavation, subgrade stabilization, placing roadway aggregate and asphalt concrete pavement, and constructing rock buttressing, riprap revetments, drainage improvements and utility infrastructure.

Project Location: This project is located approximately 4 Miles West of Babb (city). Glacier

County, Montana State.

Project Length: 2.55 Miles

Estimated Price Range: Between $20,000,000 and $30,000,000

Tentative Solicitation Date: Feb/Mar 2027

Tentative Fixed Completion Date:

• Base: Summer 2029

• Option A (Utility Relocation): Summer 2029

DESCRIPTION OF WORK in US CUSTOMARY UNITS

USING FP-24 SPECS

S ch

N am e

B as e

S ch

N am e

O p ti o n A

DIVISION 150 – Project

Requirements

151 Mobilization (yes/no) Yes

152 Construction Survey & Staking (yes/no) Yes

153 Contractor Quality Control (yes/no) Yes

154 Contractor Testing (yes/no) Yes

155 Construction Schedule (yes/no) Yes

157 Soil Erosion Control, Temporary Turf Establishment 4.0 ACRE

157 Soil Erosion Control, Fiber Roll 3,800 LNFT

157 Soil Erosion Control, Check Dam (Fiber Roll) 120 EACH

158 Watering for Dust Control LPSM

S ch

N am e

B as e

N am e

O p ti o

DIVISION 200 – Earthwork

201 Clearing & Grubbing 8.0 ACRE

203 Removal of Cattleguard 1 EACH

203 Removal of Gate 1 EACH

203 Removal of Sign/Maker 26 EACH

203 Removal of Structure (Abandonment of Existing Instrumentation) 14 EACH

203 Removal of Concrete Barrier 220 LNFT

203 Removal of Stone Masonry 26 SQYD

203 Plug, Existing Pipe 3 EACH

203 Sawcutting Pavement 520 LNFT

204 Roadway Excavation 15,100 CUYD

204 Subexcavation 26,000 CUYD

204 Select Borrow 25,700 CUYD

207 Separation Geotextile, Woven 25,500 SQYD

207 Geotextile Filter, Class 1, Non-Woven 6,000 SQYD

207 Geogrid, Stabilization 81,000 SQYD

DIVISION 250 – Slope Reinforcement and Retaining Walls

251 Placed Riprap, Class 2 300 CUYD

251 Placed Riprap, Class 3 20 CUYD

251 Placed Riprap, Class 4 5,800 CUYD

252 Rock Buttress, Mechanically-Placed 3,300 CUYD

268 Horizontal Drain Pipe 47,300 LNFT

271 Inclinometer Casing 470 LNFT

271 Geotechnical Instrumentation, Piezometer (and Data Logger) 5 EACH

DIVISION 300 – Aggregate and Base

Courses

302 Roadway Aggregate, Method 2 21,500 TON

DIVISION 400 – Asphalt Pavements &

Surface Treatments

N am e

B

N am e

O p ti o

401 Asphalt Concrete Pavement, Gyratory Mix, ½- INCH, or ¾-INCH Nominal Maximum Size Aggregate, 0.3 to <3 Million ESAL (type III roughness)

8,500 TON

401 Asphalt Concrete Pavement, Gyratory Mix, ½- INCH, or ¾-INCH Nominal Maximum Size Aggregate, Wedge and Leveling Course

120 TON

401 Antistrip Additive, Type 3 85 TON

412 Tack Coat 17 TON

413 Asphalt Pavement Milling, 1-INCH Depth 550 SQYD

418 Asphalt Concrete Pavement Patch, Type 1 10 SQYD

DIVISION 600 – Incidental

Construction

602 18-INCH Pipe Culvert 250 LNFT

602 24-INCH Pipe Culvert 800 LNFT

602 36-INCH Pipe Culvert 75 LNFT

602 48-INCH Pipe Culvert 210 LNFT

602 60-INCH Pipe Culvert 320 LNFT

602 42-INCH Equivalent Diameter Arch or

Elliptical Pipe Culvert 65 LNFT

602 End Section for 18-INCH Pipe Culvert 5 EACH

602 End Section for 24-INCH Pipe Culvert 23 EACH

602 End Section for 36-INCH Pipe Culvert 2 EACH

602 End Section for 48-INCH Pipe Culvert 2 EACH

602 End Section for 42-INCH Equivalent Diameter Arch or Elliptical Pipe Culvert 1 EACH

605 Standard Underdrain System 6,500 LNFT

619 Gate, Metal, 34 Feet Width 1 EACH

619 Cattleguard, 24 Feet 1 EACH

620 Stone Masonry 3 SQYD

620 Stone Masonry Headwall for 18-inch Pipe

Culvert 2 EACH

620 Stone Masonry Headwall for 24-inch Pipe

620 Stone Masonry Headwall for 48-inch Pipe

620 Repoint Stone Masonry 100 SQFT

N am e

B

N am e

O p ti o

622 Dump Truck, 10 Cubic Yard

Minimum Capacity 100 HOUR

622 Wheel Loader, 3 Cubic Yard Minimum Capacity 100 HOUR

622 Motor Grader, 12 Foot Minimum Blade 100 HOUR

622 Hydraulic Excavator, 1.0 Cubic Yard Minimum Capacity With Thumb Attachment

160 HOUR

623 General Labor 200 HOUR

624 Placing Conserved Topsoil, 4-inch Depth 6.3 ACRE

625 Turf Establishment 9.5 ACRE

628 Temporary Stream Diversion (Pipe Culverts) LPSM

633 Sign System 80 SQFT

633 Object Marker, Type 2 4 EACH

633 Object Marker, Type 3 8 EACH

633 Remove and Reset Sign System 5 EACH

634 Pavement Markings, Type D, Solid (Yellow) 39,000 LNFT

634 Pavement Markings, Type D, Solid (White) 18,800 LNFT

634 Pavement Markings, Type D, Broken (Yellow) 5,300 LNFT

635 Temporary Traffic Control, Construction Sign LPSM

635 Temporary Traffic Control, Barricade Type 3 (8 Feet Wide) 6 EACH

635 Temporary Traffic Control, Tubular Marker, Type 42-inch 280 EACH

635 Temporary Traffic Control, Warning Light Type A 4 EACH

635 Temporary Traffic Control, Warning Light Type B 6 EACH

635 Temporary Traffic Control, Portable Changeable Message Sign 3 EACH

635 Temporary Traffic Control, Traffic Signal System 1 EACH

635 Temporary Traffic Control, Pavement Markings 10,500 LNFT

635 Temporary Traffic Control, Flagger 1,200 HOUR

635 Temporary Traffic Control, Pilot Car 200 DAY

635 Temporary Traffic Control, Traffic Control Supervisor 300 DAY

N am e

B

N am e

O p ti o

636 System Installation, Electrical LPSM