Amendment A001.pdf
PDF 1 MB Posted
- Solicitation number
- 69056725R000016
About this file
This document is an Amendment of Solicitation for a Pavement Preservation project at Indiana Dunes National Park, issued by the Department of Transportation's Federal Highway Administration. The amendment (No. A001) is dated 01/12/2026 and modifies the original solicitation (No. 69056725R000016) from 12/02/2025. Key modifications include updates to contract clauses, wage determinations, and special contract requirements, with specific changes to electronic documentation procedures, quality control processes, and scheduling requirements.
The amendment introduces new requirements for contractors, such as using the Masterworks web-based system for daily record keeping, submitting electronic documentation, and preparing detailed schedules and daily construction records. It updates wage rates for various labor classifications across Lake, LaPorte, Porter, and St. Joseph Counties in Indiana, and modifies provisions related to measurement, payment, and contract management. The project appears to involve pavement preservation work, with specific attention to documentation, quality control, and precise administrative processes.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
N/A
PAGE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)
A001 01/12/2026 N/A IN NP INDU PMS(1)
Pavement Preservation Indiana Dunes
6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A
Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.
X 69056725R000016
9B. DATED (SEE ITEM 11)
12/02/2025
10A. MODIFICATION OF CONTRACT/ORDER NO.
N/A
10B. DATED (SEE ITEM 13)
CODE: N/A FACILITY CODE: N/A
N/A
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
(__ ) is extended, ( x ) is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN
ITEM 10A.
N/A
B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
N/A
C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
N/A
D OTHER (Specify type of modification and authority)
N/A
E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
IN NP INDU PMS(1), Pavement Preservation Indiana Dunes
See page 2
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
N/A
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION NOT USABLE
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Amendment No. A001, dated 01/12/2026 Project No: IN NP INDU PMS(1)
Solicitation No. 69056725R000016 Project Name: Pavement Preservation Indiana Dunes
REVISIONS ARE AS FOLLOWS:
NOTICE TO OFFEROR
Page A-2a, Section IV. Specifications and Permits. Removes subsection “Electronic
Documentation” and adds subsection “Masterworks.”
CONTRACT CLAUSES
Page C-18. Removes FAR clause 52.217-6 Option for Increased Quantity and adds FAR
Clause 52.217-7 Option for Increased Quantity- Separately Priced Line Item.
MINIMUM WAGE SCHEDULE
Page D-1 through D-30. Updates Davis-Bacon General Wage Decision Number
IN20250001 to IN20260001, effective date of 01/02/2026.
SPECIAL CONTRACT REQUIREMENTS
Page E-1, Subsection 101.03 Abbreviations. Adds definition for CDR.
Page E-3, Subsection 101.04 Definitions. Adds definition for Masterworks.
Page E-6a, Adds Subsection 104.04 Electronic Documentation.
Page E-18, Updates Subsection 108.05 Failure to Complete Work on Time.
Page E-19 through E-19a, Revises Subsection 109.01 Measurement of Work.
Page E-20, Subsection 109.06 Pricing Adjustments. Revises Subsection (c)(3) and revises the first paragraph of Subsection (d).
Page E-20a, Subsection 109.08 Progress Payments. Revises Subsection (c).
Page E-27, Updates Subsection 153.01 Description.
Page E-32, Updates Subsection 155.01 Description.
Page E-40 through E-41a, Revises Subsection 155.12 Contractor’s Daily Record of
Construction Operations.
Amendment No. A001, dated 01/12/2026 Project No: IN NP INDU PMS(1)
Solicitation No. 69056725R000016 Project Name: Pavement Preservation Indiana Dunes
ENCLOSURES
Pages:
A-2a
C-18
D-1 through D-30
E-1
E-6a
E-18 through E-20a
E-27
E-32
E-40 through E-41a
A-2a
Notice to Offeror
Project: IN NP INDU PMS(1), Pavement Preservation Indiana Dune directly through the System for Award Management (SAM) website and never through a third party. You can access SAM at https://www.sam.gov/SAM/ .
III. Post Award Information.
Insurance. Insurance requirements are described in Subsection 107.05.
Contractor Performance Evaluations. This office posts performance evaluations in the
Contractor Performance Assessment Reporting System (CPARS); for additional information, see http://www.cpars.gov/index.htm. Upon receiving an email notice of evaluation availability, you will have 14-60 days to review the evaluation online and submit comments. If you are unable to access the system, call 360.619.7520 for assistance or for a copy of the evaluation.
IV. Specifications and Permits.
Specifications. This solicitation and subsequent contract are governed by the Federal Acquisition
Regulation (FAR), agency supplemental regulations, and the Standard Specifications for
Construction of Roads and Bridges on Federal Highway Projects, FP-24. An electronic version may be found at https://highways.dot.gov/federal-lands/specs.
Electronic Documentation. Requires all documents (including but not limited to correspondence, notifications, submittals, reports, and pay notes) to be submitted in a pdf format, or an approved fixed-layout electronic format. See Subsection 104.04.
Masterworks. Requires the Contractor to use the Government’s web-based system Masterworks to prepare all “Inspector’s Daily Record of Construction Operations” (Contractors Daily Reports) and measurement notes (pay notes). Attend a training session on the use of Masterworks. The virtual training sessions will be either a video presentation or live training as determined by the
CO. Train additional staff. Submit a user account form to gain access to Masterworks. See
Subsection 104.04.
Material Sources. Material sources have not been identified for this project. Secure all permits and clearances for Contractor-located sites and sources. See Subsection 105.02(c).
Progress Schedules. This project includes new specifications for Prosecution and Progress and for Schedules for Construction Contracts. Carefully review Special Contract Requirements
Section 108 - Prosecution and Progress, and Section 155 – Schedules for Construction Contracts.
Revised by Amendment A001 https://www.sam.gov/SAM/ http://www.cpars.gov/index.htm https://highways.dot.gov/federal-lands/specs
C-18
Contract Clauses IN NP INDU PMS(1), Pavement Preservation Indiana Dunes adequate for evaluating the reasonableness of the price of the modification. Such information may include-
(1) For catalog items, a copy of or identification of the catalog and its date, or the appropriate pages for the offered items, or a statement that the catalog is on file in the buying office to which the proposal is being submitted. Provide a copy or describe current discount policies and price lists (published or unpublished), e.g., wholesale, original equipment manufacturer, or reseller. Also explain the basis of each offered price and its relationship to the established catalog price, including how the proposed price relates to the price of recent sales in quantities similar to the proposed quantities.
(2) For market-priced items, the source and date or period of the market quotation or other basis for market price, the base amount, and applicable discounts. In addition, describe the nature of the market.
(3) For items included on an active Federal Supply Schedule contract, proof that an exception has been granted for the schedule item.
(2) The Contractor grants the Contracting Officer or an authorized representative the right to examine, at any time before award, books, records, documents, or other directly pertinent records to verify any request for an exception under this clause, and the reasonableness of price. For items priced using catalog or market prices, or law or regulation, access does not extend to cost or profit information or other data relevant solely to the Contractor’s determination of the prices to be offered in the catalog or marketplace.
(b) Requirements for certified cost or pricing data. If the Contractor is not granted an exception from the requirement to submit certified cost or pricing data, the following applies:
(1) The Contractor shall submit certified cost or pricing data, data other than certified cost or pricing data, and supporting attachments in accordance with the instructions contained in Table 15-1 of FAR 15.408-2, which is incorporated by reference with the same force and effect as though it were inserted here in full text. The instructions in Table 15-1 are incorporated as a mandatory format to be used in this contract, unless the Contracting Officer and the Contractor agree to a different format and change this clause to use Alternate I.
(2) As soon as practicable after agreement on price, but before award (except for unpriced actions), the Contractor shall submit a Certificate of Current Cost or Pricing Data, as prescribed by FAR 15.403-4.
52.217-6 Option for Increased Quantity (Mar 1989)
The Government may increase the quantity of supplies called for in the Schedule at the unit price specified. The Contracting Officer may exercise the option by written notice to the Contractor within 90 days of contract award. Delivery of the added items shall continue at the same rate as the like items called for under the contract, unless the parties otherwise agree.
52.217-7 Option for Increased Quantity--Separately Priced Line Item (Mar 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 60 days of award. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Nov 2025)
(a) Evaluation preference.
(1) Offers will be evaluated by adding a factor of 10 percent to the price of all offers, except-
(i) Offers from HUBZone small business concerns that have not waived the evaluation preference; and
(ii) Otherwise successful offers from small business concerns.
(b) Waiver of evaluation preference. A HUBZone small business concern may choose to waive the evaluation preference. If the concern waives the preference, the factor will be added to its offer for evaluation purposes.
□ Offeror chooses to waive the evaluation preference.
D - 1
Revised by Amendment A001
General Wage Decision
Project: IN NP INDU PMS(1), Pavement Preservation Indiana Dunes
General Decision Number: IN20260001 01/02/2026
Superseded General Decision Number: IN20250001
State: Indiana
Construction Types: Building, Heavy and Highway
Counties: La Porte, Lake, Porter and St Joseph Counties in Indiana.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes and apartments up to and including 4 stories, HEAVY AND HIGHWAY CONSTRUCTION PROJECTS
Modification Number Publication Date
0 01/02/2026
ASBE0017-002 06/01/2025
LAKE AND PORTER COUNTIES
Rates Fringes
ASBESTOS WORKER/HEAT & FROST
INSULATOR........................$ 56.02 37.24
HAZARDOUS MATERIAL HANDLER
(INCLUDES PREPARATION,
WETTING, STRIPPING REMOVAL
SCRAPPING, VACUUMING, BAGGING
AND DISPOSAL OF ALL
INSULATION MATERIALS, WHETHER
THEY CONTAIN ASBESTOS OR NOT,
FROM MECHANICAL SYSTEMS).........$ 44.82 34.00
ASBE0075-001 06/01/2025
REMAINING COUNTIES
ASBESTOS WORKER/HEAT & FROST
INSULATOR........................$ 41.20 30.93
HAZARDOUS MATERIAL HANDLER
(includes preparation, wetting, stripping, removal, scrapping, vaccuming, bagging, and disposal of all insulation materials, whether they contain asbestos or not, from mechanical systems).........$ 41.20 30.93
D - 2
Project: IN NP INDU PMS(1), Pavement Preservation Indiana Dunes
BOIL0001-005 05/01/2025
LAKE COUNTY, City of Hammond; North of 114th Street
BOILERMAKER......................$ 58.91 39.75
BOIL0374-003 05/01/2025
BOILERMAKER......................$ 43.24 38.17
BRIN0004-011 09/21/2024
LAKE, LAPORTE AND PORTER COUNTIES
BRICKLAYER
Bricklayer; Stone Mason;
Pointer, Cleaner, Caulker...$ 43.49 29.53
Marble Finisher; Tile
Finisher....................$ 34.00 21.84
Marble Mason; Terrazzo
Worker; Tile Layer..........$ 43.49 29.53
Terrazzo Finisher...........$ 33.00 21.84
BRIN0004-018 09/21/2024
SOUTH BEND: ST. JOSEPH COUNTY
BRICKLAYER
BRICKLAYER; STONE MASON;
POINTER, CAULKER, CLEANER...$ 36.00 20.46
MARBLE AND TILE FINISHER....$ 33.00 21.84
MARBLE AND TILE LAYER.......$ 31.71 20.88
TERRAZZO FINISHER...........$ 33.00 21.84
TERRAZZO WORKER.............$ 37.25 24.33
CARP0413-002 06/01/2025
St. Joseph County
CARPENTER........................$ 35.51 25.98
D - 3
CARP0765-001 06/01/2025
LAKE, LAPORTE AND PORTER COUNTIES
CARPENTER........................$ 45.91 35.90
MILLWRIGHT.......................$ 47.92 37.23
CARP1029-001 06/01/2025
ADAMS, ALLEN, CASS, DEKALB, ELKHART, FULTON, GRANT, HOWARD,
HUNTINGTON, KOSCIUSKO, LAGRANGE, MARSHALL, MIAMI, NOBLE, ST.
JOSEPH, STEUBEN, TIPTON, WABASH, WELLS and WHITLEY COUNTIES
MILLWRIGHT.......................$ 35.89 30.52
ELEC0153-001 06/03/2025
ST JOSEPH COUNTY
Communication Technician.........$ 26.50 18.33
ELECTRICIAN......................$ 46.00 29.23
Includes the installation, operation, inspection, modification, maintenance and repair of systems used for the transmission and reception of signals of any nature, for any purpose, including but not limited to, sound and voice transmission/transference systems, communication systems that transmit or receive information and/or control systems, television and video systems, micro-processor controlled fire alarm systems, and security systems and the performance of any task directly related to such installation or service. The scope of work shall exclude the installation of electrical power wiring and the installation of conduit raceways exceeding fifteen (15) feet in length.
ELEC0531-001 05/31/2025
LAPORTE and PORTER COUNTIES
ELECTRICIAN......................$ 49.00 32.89
D - 4
ELEC0697-001 06/01/2025
LAKE COUNTY
ELECTRICIAN......................$ 52.00 32.85
ELEC0697-004 08/31/2025
Telecommunication Technician.....$ 41.50 31.23
Work covers low voltage installation, maintenance and removal of telecommunication facilities (voice, sound, data and video) including, telephone and data inside wire, interconnect, terminal equipment, central offices, PABX, fiber optic cable and equipment, micro waves, V/SAT, bypass, CATV, WAN (WIDE AREA NETWORKS), LAN (local area networks), and ISDN (integrated system digital network).
Does not cover any work which properly comes under the work description of Inside JW (Journeyman Wireman), but shall cover the pulling of wire in raceways, but not the installation of raceways.
ELEC1393-003 01/02/2025
LAKE & PORTER COUNTIES
(Calumet Area, North of U.S. Hwy 30)
Line Construction:
EQUIPMENT OPERATOR 1:
(Diggers 5th wheel type trucks, crawler type, D-4 and smaller, bucket trucks and live boom type line trucks).....................$ 38.33 29%+7.80
EQUIPMENT OPERATOR 3
(Backhoe over 1/2 yard bucket capacity, cranes rated at 15 ton or more capacity) 95% of J.L. Rate..$ 47.35 29%+7.80
GROUNDMAN...................$ 31.49 29%+7.58
GROUNDMAN-TRUCK DRIVER......$ 31.49 29%+7.58
LINEMAN.....................$ 50.28 29%+7.58
D - 5
ELEV0002-005 01/01/2025
ELEVATOR CONSTRUCTION
ELEVATOR MECHANIC................$ 70.68 38.435+a+b
FOOTNOTES:
a) Eight Paid Holidays: New Year's Day; Veterans Day, Memorial Day; Independence Day; Labor Day; Thanksgiving
Day; Friday after Thanksgiving and Christmas Day.
b) Employer contributes 8% of regular hourly rate to vacation pay credit for employee with more than 5 years of service, and 6% of regular hourly rate for less than 5 years of service.
ELEV0044-001 01/01/2025
LA PORTE and ST. JOSEPH COUNTIES
ELEVATOR MECHANIC................$ 62.27 38.435+a+b
a) PAID HOLIDAYS: New Year's Day, Memorial Day, Independence
Day, Labor Day, Veterans' Day, Thanksgiving Day, the Friday after Thanksgiving, and Christmas Day.
b) Employer contributes 8% of regular hourly rate to vacation pay credit for employee with more than 5 years of service;
6% for less than 5 years' service.
ENGI0150-001 06/01/2025
BUILDING CONSTRUCTION POWER EQUIPMENT OPERATORS:
LAKE, LAPORTE, and PORTER COUNTIES
POWER EQUIPMENT OPERATOR
GROUP 1.....................$ 48.70 45.93
GROUP 2.....................$ 47.90 45.93
GROUP 3.....................$ 43.60 45.93
GROUP 4.....................$ 41.40 45.93
GROUP 5.....................$ 35.95 45.93
D - 6
POWER EQUIPMENT OPERATOR CLASSIFICATIONS:
GROUP 1: Asphalt Plant; Autograde; Batch Plant); Benoto
(requires 2 engineers; Boiler & throttle valve; Boring machine (mining machine); Caisson Rigs; Central redi-mix plant; Combination Backhoe Endloader with backhoe bucket over 1/2 cu. yd. or with attachments; Combination tugger hoist & air compressor; Compressor & throttle; Concrete
Breaker (truck mounted); Concrete conveyor; Concrete conveyor (truck mounted); Concrete paver over 27E cu.ft.;
Concrete paver 27E cu. ft. & under; Concrete placing boom;
Concrete pump/grout pump with boom (truck mounted);
Concrete pump with boom (truck mounted); concrete tower;
Cranes and Backhoes (All Attachments); Cranes, Hammerhead
Tower; Creter Crane; Derricks (all); Derricks (traveling);
Forklift lull type; Forklift, 10 ton & over; Gradall, Hoist
1, 2, and 3 drums; Hoist (2 tugger l floor), Hydraulic Boom truck, Laser Screed, Locomotive (all), Motor patrol, Mucking Machine; Pile Driving and Skid rig, Pit machine, Prestress Machines, Pump cretes (and similar types), Rock
Drill (self-propelled), Rock Drill Truck mounted; Slip form paver, Straddle buggies, Tractor with boom and side boom, Trenching Mechine; Winch Tractors, Welding machines (6-9), GROUP 2: Air Comporessor (3) (feeding a common receiver);
Asphalt Spreader; boilers; bulldozers; Combination Backhoe end loader with Backhoe bucket 1/2 cu. yd. and under or with attachments; Corboy drilling machine; Grader, Elevating; Grouting machines; Guard rail post driver;
Highlift Shovel or frontend loader; Hoist (automatic), Hoist (all elevators); Hoist (tugger and single drum); Post hole digger; rollers (all); Scoop (tractor drawn); Stone crushers; Tournapull; Winch trucks
GROUP 3: Air compressor - small 210 and under (1 to 5 not to exceed a total of 300 feet); Air compressor - large over
210; Air compressor (2) feeding a common receiver;
Combination - small equipment operator; Concrete mixer (two bag & over); Conveyor, portable; Forklift-under 10 ton;
Generator; Pumps (1 to 3 not to exceed a total of 300 feet); Pumps, well points; Steam generators; Tractors, farm
& similar type; Welding machines (2 thru 5); Winches, 4 electric drillo winches
GROUP 4: Bull gang (crane erection crew); Heaters, mechanical (1 to 5); Oilers; Switchmen
GROUP 5: Fork lifts (Housing and commercial only)
ENGI0150-012 06/01/2025
D - 7
BUILDING CONSTRUCTION
ST. JOSEPH COUNTY
GROUP 1.....................$ 36.15 38.65
GROUP 2.....................$ 34.80 38.65
GROUP 3.....................$ 34.00 38.65
GROUP 4.....................$ 33.20 38.65
GROUP 5.....................$ 30.60 38.65
POWER EQUIPMENT OPERATOR CLASSIFICATIONS:
GROUP 1: Mechanic, Asphalt Plant, Asphalt Spreader, Auto
Grader; Batch Plant, Benoto (requires 2 Engineers), Boiler and Throttle Valve, Boring Machine (road), Bulldozers (with engines of 140 net horse power or more) Caisson Rigs, Central Redi-mix Plant, Concrete Conveyor Systems, Concrete
Power (over 27E cu. ft.), Concrete Paver (27E cu. ft. and under), Concrete Pumps/Grout cncrete placer (Truck
Mounted), Concrete Tower, Cranes and backhoes (all), Cranes, Hammerhead Tower, Creter Crane, Derricks (all), Forklift (capble of hoisting and mechanically moving forks horizontally), Grader, Elevating, Highlift Shovels or Front
End Loaders (over 3 yd bucket), Hoists (2 or more drums), Locomotives (all), Laser screed, Motor Patrol, Pile Drivers and Skid Rig, Pre-Stress Machines, Pump Cretes & Similar
Types, Rock Drill (Self-Propelled), Rock Drill (self propelled Truck Mounted), Scoops (tractor drawn), Slip-Form
Paver, Tournapull, Tractor with Boom & Side Boom, Trenching
Machine (12 or more inches in width), Combination Backhoe
Front End Loader Machine with backhoe 1/2 yd bucket or attachments.
GROUP 2: Air Compressor (600 cu. ft. and over), Bob Cat
(over 3/4 cu. yd.), Boilers, Broom (all powered propelled), Bull Dozers with engines of less than 140 net horsepower, combination backhoe front end loader 1/2 yf bskhhoe or under, Compressor and Throttle Valve, Concrete Breaker
(truck mounted), Concrete Mixer (of moore than 21 cu. ft.
capacity), Forklift (with fixed or tilt mast), Greaser
Engineer, Highlift shovel or front endloader 3 yd bucket and under, Hoists (1 drum), Hydrulic Boom Truck, Post Hole
Digger (vehicle mounted), Pump Cretes (squeze crete type pumps, Gypsum, bulker , Rollers(all), Steam Generators, Stone Crushers, Stradddle Buggies, Tractors, Winch Trucks
(with ""a"" frame.
GROUP 3: Buck Hoist, Combination (small equipment operator), D - 8
Project: IN NP INDU PMS(1), Pavement Preservation Indiana Dunes
.Conveyor (portable), Grouting Machine, Hoist Elevators
(material and personnel), Hydraulic Power Units, Grouting and Pile Driving, Stud Welder, Trenching Machines less than
12 inches in width, Welding Machines (8 through 15).
GROUP 4: Bobcat (up to and including 3/4 cu. yd.).
Compressor (over 210 cu. ft. and less than 600 cu. ft.), Generator (over 50 kw.), Heaters, Mechanical, Hoists (all elevator, permanent installation), Hoist (automatic), Hoist
(tugger single drum), Oilers, Pumps, Well Points and electric submersible, Small Rubber Tired End Loaders (1/4
cu. yd. and under), Tractors (farm type) Welding Machines
(2 through 8).
GROUP 5: Bobcats and forklifts (commercial or residential).
ENGI0150-014 05/01/2025
POWER EQUIPMENT OPERATOR HEAVY/HIGHWAY
LAKE, LAPORTE, PORTER AND ST. JOSEPH COUNTIES
GROUP 1.....................$ 49.05 43.40
GROUP 2.....................$ 48.60 43.40
GROUP 3.....................$ 48.15 43.40
GROUP 4.....................$ 46.95 43.40
GROUP 5.....................$ 45.90 43.40
POWER EQUITMENT OPERATOR CLASSIFICATIONS
GROUP 1: Asphalt plants (construction), Asphalt plant
(permanent), Auto Patrol (Maintainer), Automatic Dry
Batch Plant, Automated Concrete Placer, Automated
Sub-Grader, Automated Slip Form Paver, Automated Finish
Machine, Combination Backhoe Front, End Loader Machine
(1/2 cu. yd.), Backhoe bucket or over or with attachments), Combination backhoe 1 cu yd, Backhoe bucket or over or with attachments, Ballast Regulator (RR), Belt Loader
(stationary), Boring Machine (road), Bulldozer, Concrete
Mixer(27 cu. ft. or over), Concrete Pump (truck mounted), Concrete Breaker (truck mounted and self-propelled), Core
Drilling Machine, Cranes and Backhoes (all attachments), Cranes, Hammerhead, Creter Crane, Crushers (concrete, rock, recycling, etc.), Derricks , Derricks (traveling), Dredge
Operator, Formless Curb and Gutter Machine (36 inches and over), Formless Curb and Gutter Machine under 36 inches, Gradall and Machines (of a like nature), Guardrail Post
Driver (truck mounted), Lead Greaser, Helicopter, Highlift
D - 9
Project: IN NP INDU PMS(1), Pavement Preservation Indiana Dunes
Shovel (3 yd. and over), Hoist (1 drum), Hoist (2, and 3 drums), Hydraulic Power Units (grouting, piledriving and extracting) Hydro or water blaster (self-propelled), Locomotive Operators, Mechanic, Welder, Mucking Machine, Panelboard Concrete Plant (central mix type), Paver
(Hetherington), Pile Driver (Skid or Crawler), Road Paving
Mixer, Rock Drill Crawler or Skid Rig, Rock Drill (truck
Mounted), Ross Carrier, Roto Mill Grinder (36"" and over), Roto mill grinder (less than 36""), Throttle Valve and
Compressor or Clever Brooks Type Combination, Throttle
Valve and Fireman Combination or Horizontal or Upright
Boiler, Tournapull or similar type equipment, Tractor
(boom), Tractor Drawn Belt Loader with attached Pusher
(requires two engineers), Trench Machine, Tug Boat
Operator, Wheel Excavator, Winch Tractor with ""a"" frame, Scoops, Turnapull or similar types machine used in Tandem
(add $1.00 to class l hourly rate for each machine attached there to).
GROUP 2: Combination Backhoe Front End Loader Machine with less than 1/2 cu. yd., Backhoe Bucket or with attachments, Bituminous Mixer, Bituminous Paver, Bridge Deck Finisher, Concrete Mixer (less than 27 cu. ft.), Compressor and throttle valve, Compressor (common receiver 3), Greaser, Highlift Shovels (under 3 cu. yds.), Jersey Spreader or
Base Paver, Pavement Bump Grinder (self-propelled), Roller
(Asphalt, waterbound, Macadam, Bituminous Macadam, Brick
Surface, Sheepfoot Roller (self- propelled with blade), Surface Heater and Planer, Tamper (mutiple vibrating, asphalt waterbound macadam, bituminouus macadam, brick surface), Tractor (push), Tractor with scoop, Widener, Apsco or similar type.
GROUP 3: Back Filler, Bituminous Distributor, Broom and Belt
Machine, Bull Float, Compressor (common receiver 2), Concrete cutter wheel type (rockwell), Concrete Finishing
Machine, Concrete Spreader (power driven), Digger, Post
Hole (power driven), Finishing Machine and Bull Float, Forklift, Form Grader, Form Tamper (motor driven), Hydraulic (boom truck) when used for hauling materials, Laser screed, Mutiple Tamping Machine, Paving Breaker, Roller (earth and subbase material), Roller sheepfoot
(self-propelled), Sub-grader, Tamper, Mutipile Vibrating
(earth and subbase material), Tractaire with Drill, Tractor
(with all drawn attachements except backhoe and including
Highlift, Endloader of 1 cu. yd. capacity and less.
GROUP 4: Air Compressors, Conveyor (all), Fireman on Boiler, Generator, Grout Machine, Power curing Spraying Machine
(self-propelled), Broom (self-propelled), Seaman Tiller, Skid steer loaders, Spike Machine (RR), Stripping Machine
(paint, self-propelled), Throttle Valve, Welding Machine, D - 10
Well Points System.
GROUP 5: Deck Hand, Hetherington Driver, Mechanical Heater
(1 to 5), Outboard or Inboard Motor Boat, Oiler, Power Saw
(Concrete Power Driven), Water Pump, Grasscutter.
IRON0292-001 06/01/2025
ST. JOSEPH and LAPORTE (Remainder of County) COUNTIES
IRONWORKER.......................$ 39.76 25.00
IRON0395-001 06/01/2025
LAKE, PORTER AND LAPORTE (FROM LAKE MICHIGAN ON NORTH TO 50
MILES S. OF LAKE MICHIGAN ON THE S. AND FROM IN/IL STATE LINE
ON W. TO 3 MILES E. OF IN. COUNTIES
IRONWORKER
SHEETER.....................$ 48.00 41.28
STRUCTURAL & ORNAMENTAL.....$ 47.75 41.28
LABO0041-001 06/01/2025
LAKE COUNTY (Western Half)
Laborers:
CAISSON AND TUNNEL WORK
(Compressed & Free Air).....$ 40.30 28.90
GROUP 1.....................$ 39.26 28.90
GROUP 2.....................$ 40.01 28.90
GROUP 3.....................$ 40.26 28.90
LABORER CLASSIFICATIONS:
GROUP 1: Building and Construction Laborers; Scaffold
Builders (other than for Mason or Plasterers); Railroad
Workers, Masonry Wall Workers, (interior & exterior);
Portable Water, Pumps with discharge up to 3 indches;
Handling of Creosote Lumber or Like Treated Material
(excluding railroad material); Asphalt Rakers and Lutemen;
Earth compactors; Jackmen and Sheetmen Working Ditches
D - 11
Project: IN NP INDU PMS(1), Pavement Preservation Indiana Dunes
Deeper than Six (6) Feet in Depth; Laborers Working Ditches
Six (6) Feet in Depth or Deeper; Assembly of Unicrete Pump;
Tile Layers (sewer or field) and Sewer Pipe Layers
(metallic or non-metallic); Motor Driven Wheelbarrows and
Concrete Buggies; Hyster Operators; Pump Crete Assemblers;
Core Drill Operators; Cement, Lime or Silica Clay Handler
(bulk or bag); Handling of Toxic Materail Damaging to
Clothing; Pneumatic Spikers; Deck Engine and Winch
Operators; Water main and Cable Ducking (metallic and non-metallic); Screed Man or Screw Operator on Asphalt
Paver; Chain Saw and Demolition Saw Operators; Concrete
Saw; Concrete Conveyor Assemblers; Applying of Curing
Compound; Sinking of Wellpoints; Dewatering Header Systems
GROUP 2: Plaster Tenders, Masons Tenders; Mortar Mixers;
Welders (acetylene or electric); Cutting Torch or Burner;
Cement Nozzle Laborers; Cement Gun Operators; Scaffold
Builders for Plasterers; Scaffold Builders for Masons;
Water Blast Machine Operators; Air Tool Operators and all
Pneumatic Tool Operators, Air and Electric Vibrators and
Chpping Hammer Operators; Asbestos Removal; Hazardous Waste
Removal; All Boiler Setters Laborers, including expediters, bottom men, bell men, and Mason Tenders
GROUP 3: Dynamite Men; Drillers, Air Track or Wagon Drilling for explosives.
CAISSON AND TUNNEL WORK (Compressed & Free Air)
GROUP 1: Cage Tenders, Dump Men, Flagman, Signalman, Top
Laborers, Rod Men, Concrete Repairmen, Motor Men, Muckers, Grout Machine, Track Layers, Air Hoist, Key Board, Agitator
Car, Car Pushers, Concrete Laborers, Grout Laborers, Sttl
Setters, Tuggers, Switchmen, Mucking Machine, Laser Beam, Liner Plate & Ring Setter, Shield Drivers, Power Knife, Burners, Pipe Jacking Machine, Skinners, Maintenance
Technician, Miner, Bricklayer Tenders, Concrete Blowers, Drillers, Erectors, Form Men, Jackhammermen, Mining
Machine, Dynamite Men, Drillers-air track or wagon drilling for explosives.
Premium for all employees working in compressed air shall be as follows:
0 - 15 lbs. $1.00 per hour
16 - 20 lbs. 1.50 per hour
21 - 26 lbs. 2.00 per hour
27 - 33 lbs. 3.00 per hour
34 & over 4.00 per hour
LABO0041-004 04/01/2025
D - 12
UTILITY CONSTRUCTION
LABORERS
Group 1.....................$ 33.45 27.50
Group 2.....................$ 33.75 27.50
Group 3.....................$ 34.45 27.50
LABORERS CLASSIFICATIONS (HEAVY AND HIGHWAY)
GROUP 1: Construction Laborer, Carpenter Tender, Fence
Erector, Grade Checker, Guard Rail Erector, Continuous
Steel Rod or Mat Installer, Wire Mesh Layer, Joint Man
(Mortar, Mastic, and all other types), Lighting Installer
(Permanent or Temporary), Lineman for Automatic Grade Maker on Paving Machines, Mortar Man, Multi-Plant Erector, Rip-rap Installer (all Products and Materials), Road
Marking and Delineation Laborer, Setting and Placing of all
Precast Concrete Products, Sing Installation including supporting structure, Spraying of all Epoxy, Curing
Compound, or Like Material, Flagperson, Air Tool, Power
Tool Operator, Asphalt Raker Man, Batch Truck Dumper, Bridge Hand Rail ERector, Handler (bulk or bag cement), Chain Saw Man, Concrete Puddler, Concrete Rubber, Concrete
Saw Operator, Core Drill Operator, Eye Level, Hand Blade
Operator Hydro Seeder Man, Motor Driven Georgia Buggy
Operator, Power Driven Compactor or Taper Operator, Power
Saw Operator, Pump Crete Assembly Man, Sreed Man or Screw
Man on Asphalt Paver, Regar Installer, Sandblaster Man, Sealer Applicator for Asphalt (toxic), Setting and Placing pre-stressed on Pre-cast Concrete Structural Members, Side
Rail Setters (for Sidewalk, Side Ditches, Radii, and
Pavement), Spreader Box Tender (manua or power driven), Straw Blower Man, Subsureface Drain and Culvert Pipe Layer, Concrete Conveyor, Horizonal Boring and Jackman and
Sheetman, Pipe Greade Man, Winch and Windless Operator
Conduit Installer, Sod Layer
GROUP 2: Cutting Torch Burner, Laser Beam Aligner, Manhole
Erector, Sewer Pipe Layer, Water Line Installer, Temporary or Permanent Welders (electric or Oxy Acetylene)
GROUP 3: Air Track and Wagon Drillman, Dynamite and Powder
Man, Concrete Barrier Rail Form Setter, Concrete Saw Joint
Control Cutting
LABO0081-001 04/01/2025
D - 13
HEAVY and HIGHWAY CONSTRUCTION:
LAKE, LA PORTE, and PORTER COUNTIES
GROUP 1.....................$ 33.45 27.50
GROUP 2.....................$ 33.75 27.50
GROUP 3.....................$ 34.45 27.50
LABORERS CLASSIFICATIONS (HEAVY AND HIGHWAY)
GROUP 1: Construction Laborer; Carpenter Tender; Fence
Erector; Grade Checker; Guard Rail Erector; Continuous
Steel Rod or Mat Installer; Wire Mesh Layer; Joint Man
(Mortar, Mastic, and all other types); Lighting Installer
(Permanent or Temporary); Lineman for Automatic Grade Maker on Paving Machines; Mortar Man; Multi-Plant Erector;
Rip-rap Installer (all Products and Materials); Road
Marking and Delineation Laborer; Setting and Placeing of all Precast Concrete Products; Sing Installation including
Supporting Structure; Spraying of all Epoxy, Curing
Compound, or Like Material; Flagperson; Air Tool, Power
Tool Operator; Asphalt Raker Man; Batch Truck Dumper;
Bridge Hand Rail Erector; Handler (bulk or bag cement);
Chain Saw Man; Concrete Puddler; Concrete Rubber; Concrete
Saw Operator; Core Drill Operator, Eye Level; Hand Blade
Operator Hydro Seeder Man; Motor Driven Georgia Buggy
Operator; Power Driven Compactor or Tamper Operator; Power
Saw Operator; Pump Crete Assembly Man; Screed Man or Screw
Man on Asphalt Paver; Rebar Installer; Sandblaster Man;
Sealer Applicator for Asphalt (toxic); Setting and Placeing
Prestressed on Precast Concrete Structural Members; Side
Rail Setters (for Sidewalk, Side Ditches, Radii, and
Pavement); Spreader Box Tender (manual or power driven);
Straw Blower Man; Subsurface Drain and Culvert Pipe Layer;
Concrete Conveyor; Horizonial Boring and Jackman and
Sheetman; Pipe Grade Man; Winch and Windlass Operator
Conduit Installer, Sod Layer.
GROUP 2: Cutting Torch Burner: Laser Beam Aligner; Manhole
Erector; Sewer Pipe Layer; Water Line Installer, Temporary or Permanent; Welders (electric or Oxy-Acetylene).
GROUP 3: Air Track and Wagon Drillman; Dynamite and Powder
Man; Concrete Barrier Rail Form Setter; General Laborer;
concrete saw, joint control cutting
LABO0081-002 04/01/2025
D - 14
LA PORTE & PORTER COUNTIES
GROUP 1.....................$ 33.45 27.50
GROUP 2.....................$ 33.75 27.50
GROUP 3.....................$ 34.45 27.50
LABORERS CLASSIFICATIONS (UTILITY CONSTRUCTION)
GROUP 1: Construction laborer; Fence erector; Flagger; Grade checker; Guard rail erector; Wire mesh layer; Joint man
(mortar, mastic and all other types); Lighting installer
(permanent or temporary); Lineman for automatic grade maker on paving machines; Mortar man; Multi-plate erector;
Rip-rap installer (all products and materials); Road marking and delineation laborer; Setting and placing of all precast concrete products; Sign installation including supporting structure; Spraying of all epoxy, curing compound, or like material; sod layer; Air tool, power tool, and power equipment operator; Asphalt lute man;
Asphalt raker man; Batch truck dumper; Bridge handrail erector; Handler (bulk or bag cement); Chain saw man;
concrete puddler; concrete rubber; Concrete saw operator;
Core drill operator, eye level; Hand blade operator; Hydro seeder man; Motor-driven Georgia buggy operator;
Power-driven compactor or tamper operator; Power saw operator; Pumpcrete assembly man; Screed man or screw man on asphalt paver; Rebar installer; Sandblaster man; Sealer applicator for asphalt (toxic); Setting and placing prestressed or precast concrete structural memebers; Side rail setter (for sidewalks, side ditches, radii, and pavements); Spreader box tender (manual or power-driven);
Straw blower man; Subsurface drain and culvert pipe layer;
Transverse and longitudinal hand bull float man; Concrete conveyor assembly man; Horizontal boring and jacking man;
Jackman and sheetman; Pipe grade man; Winch and windlass operator
GROUP 2: Cutting torch burner; Laser beam aligner; Manhole erector; Sewer pipe layer; Water line installer, temporary or permanent; Welder (electric or exy-acetylene) in connection with waterline and sewer work, Hod Carrier
(tending bricklayers); TVing and associated grouting of utility lines
GROUP 3: Air track and wagon drillman; Concrete barrier rail form setter; Dynamite and powder man; General leadman;
D - 15
Concrete Saw Joint Control cutting
LABO0081-004 06/01/2025
LAKE (Eastern Half), LA PORTE, and PORTER COUNTIES
Laborers
GROUP 1.....................$ 39.89 30.30
GROUP 2.....................$ 40.64 30.30
GROUP 3.....................$ 40.89 30.30
LABORER CLASSIFICATIONS (Building Construction)
Builders (other than for Mason or Plasterers); Mechanic
Tenders; Rodmen and Chainmen, Railroad Workers, Masonry
Wall Workers, (interior & exterior); Roofer Tenders, Cement
Finisher Tenders, Carpenter Tenders, Portable Water, Pumps with discharge up to 3 inches; Waterproofing; Hauling of
Creosote Lumber or Lutemen; Asphalt Rakers; Kettlem, Earth
Compactors; Jackman and Sheetmen in Ditches more than 6 ft.
deep; Laborers in ditches 6' deep or deeper; Assembly of
Uncrete Pump; Tile Layers (sewer or field); Sewer Pipe
Layers; Motor driven Wheelbarrows and Concrete Buggies;
Hyster Operator; Pump Crete Assemblers; Core Drill
Operator; Cement, Line or Silica Clay Handers; Handling of
Toxic Materials damaging to clothing; Pneumatic Spikers;
Deck Engine and Winch Operator; Water Main and Cable
Ducking; Screed Man or Screw Operator on Asphalt Paver;
Chain Saw and Demolition Saw Operator; Concrete Conveyor
Assembler
GROUP 2: Plaster Tenders, Masons Tenders; Mortar Mixers;
Welders (acetylene or electric); Cutting Torch or Burner;
Cement Nozzle; Cement Gun; Scaffold Builders when working for Plasterers, and Mason; Water Blast Machine Operator;
Air Tool Operators and all Pheumatic Tool Operators; Air and Electric Vibrators and Chipping Hammer Operators;
Asbestos Removal; Hazardous Waste Removal
GROUP 3: Dynamite Men; Drillers, Air Track or Wagon Drilling for explosives; Laborer Specialist
LABO0645-001 06/01/2025
D - 16
GROUP 1.....................$ 29.88 18.70
GROUP 2.....................$ 30.38 18.70
GROUP 3.....................$ 31.88 18.70
Builders (other than for Plasterers); Mechanic Tenders;
Window Washers and cleaners; Waterboys and Toolhousemen;
Roofers Tenders; Railroad Workers; Masonry Wall Washers
(interior and exterior); Cement Finisher Tenders; Carpenter
Tenders; All Portable Water pumps with discharge up to (3) inches; Plaster Tenders; Flag & Signal Person.
GROUP 2: Waterproofing; Handling of Creosot Lumber or like treated material (excluding railroad material); Asphalt
Rakers and Lutemen; Kettlemen; Air Tool Operators and all
Pneumatic Tool Operators; Air and Electric Vibrators and
Chipping Hammer Operators; Earth Compactors Jackmen and
Sheetmen working Ditches deeper than (6) ft.in depth;
Laborers working in ditches (6) ft.in depth or deeper;
Assembly of Unicrete Pump; Tile Layers (sewer or field) and
Sewer Pipe Layer (metallic or non-metallic); Motor driven
Wheelbarrows and Concrete Buggies; Hyster Operators; Pump
Crete Assemblers; Core Drill Operators; Cement, Lime or
Silica Clay Handlers (bulk or bag); Handling of Toxic
Materials damaging to clothing; Pneumatic Spikers; Deck
Engine and Winch Operators; Water Main and Cable Ducking
(metallic and non-metallic); Screed Man or Screw Operator on Asphalt Paver; Chain and Demolition Saw Operators;
Concrete Conveyor Assemblers.
GROUP 3: Water Blast Machine Operator; Mortar Mixers; Welders
(Acetylene or electric); Cutting Torch or Burner; Cement
Nozzle. Laborers; Cement Gun Operator; Scaffold Builders when Working for Plasterers. Dynamite Men; Drillers - Air
Track or Wagon Drilling for explosives Hazardous and Toxic material handler, Mason Tenders; asbestos removal or handler.
LABO0645-002 04/01/2025
D - 17
GROUP 1.....................$ 30.65 18.00
GROUP 2.....................$ 31.15 18.00
GROUP 3.....................$ 31.65 18.00
LABORER CLASSIFICATIONS (UTILITY CONSTRUCTION)
(mortar, mastic and all other types); Lighting installer
(permanent or temporary); Lineman for automatic grade maker on paving machines; Mortar man; Multi-plateerector; Rip-rap installer (all products and materials); Road markin and delineation laborer; Setting and placing of all precast concrete products; Sign installation including supporting structure; Spraying of all epoxy, curing compound, or like material; sod layer; Air tool, power tool, and power equipment operator; Asphalt lute man; Asphalt raker man;
Batch truck dumper; Bridge handrail erector; Handler (bulk or bag cement); Chain saw man; concrete puddler; concrete rubber; Concrete saw operator; Core drill operator, eye level; Hand blade operator; Hydro seeder man; Motor-driven
Georgia buggy operator; Power-driven cmpactor or tamper operator; Power saw operator; Pumpcrete assembly man;
Screed man or screw man or asphalt paver; Rebar installer;
Sandblaster man; Sealer applicator for asphalt (toxic);
Setting and placing prestressed or precast concrete structural members; Side rail setter (for sidewalks, side ditches, radii, and pavements); Spreader box tender (manual or power-driven); Straw blower man; Subsurface drain and culvert pipe layer; Concrete conveyor assembly man;
Horizontal boring and jacking man; Jackman and sheetman;
Pipe grade man; winch and windlass operator.
or permanent; Welder (electric or exy-acetylene) in connection with waterline and sewer work, Hod Carrier utility lines.
GROUP 3: Air track and wage drillman; Concrete barrier rail
Concrete Saw Joint Cutting.
LABO0645-004 04/01/2022
HEAVY AND HIGHWAY
D - 18
LABORERS
GROUP 1.....................$ 27.40 17.22
GROUP 2.....................$ 27.90 17.22
GROUP 3.....................$ 28.40 17.22
LABORER CLASSIFICATIONS (HEAVY AND HIGHWAY CONSTRUCTION)
(mortar, mastic and all other types); Lighting installer
(permanent or temporary); Lineman for automatic grade maker on paving machines; Mortar man; Multi-plateerector; Rip-rap installer (all products and materials); Road markin and delineation laborer; Setting and placing of all precast concrete products; Sign installation including supporting structure; Spraying of all epoxy, curing compound, or like material; sod layer; Air tool, power tool, and power equipment operator; Asphalt lute man; Asphalt raker man;
Batch truck dumper; Bridge handrail erector; Handler (bulk or bag cement); Chain saw man; concrete puddler; concrete rubber; Concrete saw operator; Core drill operator, eye level; Hand blade operator; Hydro seeder man; Motor-driven
Georgia buggy operator; Power-driven cmpactor or tamper operator; Power saw operator; Pumpcrete assembly man;
Screed man or screw man or asphalt paver; Rebar installer;
Sandblaster man; Sealer applicator for asphalt (toxic);
Setting and placing prestressed or precast concrete structural members; Side rail setter (for sidewalks, side ditches, radii, and pavements); Spreader box tender (manual or power-driven); Straw blower man; Subsurface drain and culvert pipe layer; Concrete conveyor assembly man;
Horizontal boring and jacking man; Jackman and sheetman;
Pipe grade man; winch and windlass operator or permanent; Welder (electric or exy-acetylene) in connection with waterline and sewer work, Hod Carrier utility lines.
GROUP 3: Air track and wage drillman; Concrete barrier rail
Concrete Saw Joint Cutting
PAIN0027-004 06/01/2025
LAKE COUNTY, West of Highway #41, including HAMMOND area
D - 19
GLAZIER..........................$ 53.55 44.88
PAIN0091-004 06/01/2025
LA PORTE (Everything East of Hwy 39 and North of Hwy 20, including the Cities of LaPorte and Michigan City); ST. JOSEPH
COUNTIES
PAINTER
Brush & Roller, Drywall
Taping & Finishing, Vinyl/Paper Hanging.........$ 32.50 19.86
Spray.......................$ 33.00 19.86
PAIN0460-003 06/24/2025
PORTER, LAKE and the remainder of LA PORTE COUNTY)
Painters:
DRYWALL FINISHING..........$ 41.00 31.26
PAINTER.....................$ 41.00 31.26
PAIN1165-005 07/01/2025
LAKE (EAST OF HIGHWAY #41 EXCLUDING HAMMOND AREA), LAPORTE and
PORTER COUNTIES
GLAZIER..........................$ 44.09 30.63
PAIN1165-009 07/01/2025
GLAZIER..........................$ 34.22 24.67
PLAS0101-006 06/01/2018
HEAVY/HIGHWAY
D - 20
CEMENT MASON/CONCRETE FINISHER...$ 31.50 14.30
PLAS0101-007 06/01/2018
CEMENT MASON/CONCRETE FINISHER...$ 28.84 14.48
PLASTERER........................$ 26.81 12.40
PLAS0165-001 07/01/2018
LAKE COUNTY (EXCEPT BY THE NORTHEAST SECTION LYING NORTH OF
CROWN POINT AND EAST OF GRIFFITH)
CEMENT MASON/CONCRETE FINISHER
BUILDING CONSTRUCTION.......$ 37.28 18.53
HEAVY & HIGHWAY
CONSTRUCTION................$ 33.94 13.80
PLASTERER........................$ 32.70 17.70
PLAS0406-001 07/01/2018
LAKE COUNTY (NORTHWARD ON LAKE COUNTY LINE TO AND INCLUDING THE
CITY OF MERRILLVILLE, BUT NOT THE CITY LIMITS OF CROWN POINT)
and PORTER COUNTIES
BUILDING CONSTRUCTION.......$ 35.48 21.68
HEAVY & HIGHWAY
CONSTRUCTION................$ 32.00 15.74
PLASTERER........................$ 33.28 17.32
PLAS0438-001 06/01/2018
LAPORTE COUNTY, EASTERN PORTION OF PORTER COUNTY WEST TO BUT
NOT INCLUDING CHESTERTON IN THE NORTH AND WEST TO AND INCLUDING
KOUTS IN THE SOUTH
D - 21
Cement Mason...............$ 36.01 25.40
HEAVY & HIGHWAY
CONSTRUCTION
Cement Mason...............$ 30.89 17.34
PLUM0172-006 06/01/2025
LA PORTE COUNTY (CITY OF LAPORTE) and ST. JOSEPH COUNTIES
Plumber, Pipefitter, Steamfitter......................$ 44.93 23.23.03
PLUM0210-001 06/01/2025
LAKE, LAPORTE (Excluding the City of LaPorte) and PORTER
COUNTIES
PLUMBER..........................$ 49.77 28.56
PLUM0597-003 06/01/2018
LAKE (Entire County), LA PORTE (Excluding the city of La
Porte), PORTER (Entire County)
PIPEFITTER.......................$ 48.50 31.12
ROOF0023-006 06/01/2024
LA PORTE and ST. JOSEPH COUNTIES
ROOFER
COMPOSITION.................$ 34.55 21.04
SLATE & TILE................$ 36.05 21.04
ROOF0026-003 06/01/2025
D - 22
ROOFER...........................$ 47.47 27.81
SFIN0281-001 01/01/2018
PORTER COUNTY (North of U.S. Route 30)
Sprinkler Fitters................$ 48.10 27.05
SFIN0669-002 04/01/2025
SPRINKLER FITTER.................$ 44.20 27.88
SHEE0020-013 07/01/2023
Sheet metal worker...............$ 38.40 28.05
SHEE0020-015 07/01/2023
LAKE, LAPORTE, and PORTER COUNTIES
Sheet metal worker...............$ 47.60 29.31
TEAM0135-004 04/01/2025
LA PORTE COUNTY
TRUCK DRIVER (BUILDING
CONSTRUCTION ONLY)
GROUP 1.....................$ 32.67 A
GROUP 2.....................$ 33.17 A
GROUP 3.....................$ 33.37 A
GROUP 4.....................$ 33.52 A
GROUP 5.....................$ 34.02 A
A: $37.90 PER DAY & 460.00 PER WEEK.
TRUCK DRIVER CLASSIFICATIONS
D - 23
GROUP 1: Single Axle Trucks, seven (7) cu. yds. or less than ten and one-half (10 1/2) tons, dupsters, scoop-mobiles five (5) cu.yds. and under or less than seven and one-half
(7 1/2) tons, mixer trucks three (3) cu.yds. and under, air compressors and welding machines, including those pulled by separate units, batch trucks-wet or dry- 2""34-E"" batches or less, truck driver helpers, warehousemen, mechanic's helpers, greasers and tiremen, all pick-up trucks and other vehicles. Drivers on dumpsters or similar dumpsters, mounted on four (4) wheel truck rated two (2) cu.yds. or less, and small pallet type fork-lift operator and drivers on pallet jacks or similar type equipment.
GROUP 2: Drivers on tandem axle eighteen (18) cu.yds. or twenty- four (24) tons gross, six (6) wheel trucks, Koehring or similar dumpsters, tract trucks, Euclids, hug bottom dumps, tournapulls, trounatrailers, tournarockers, or similar equipment when used for transportation purposes under nine (9) cu.yds. or less than thirteen and one-half
(13 1/2) tons, tandems and semi-trailer service trucks, mixer trucks over three (3) cu.yds. and including six and one-half (6 1/2) cu.yds., fork lift, four (4) wheel A-frame trucks when used for transportation purposes, four
(4) wheel winch trucks, pavement breakers, batch trucks-wet or dry- over 2 up to and including 4-""34-E"" batches two (2) men oil distributors, fork-lift under four (4) ton and vacuum trucks.
GROUP 3: Koehring or similar dumpsters, tract trucks, semi-trailer water trucks, Euclids, hug bottom dumps, tournapulls, tournatrailers, tournarockers, tractor trailers, tandems, Q- frame winch trucks, hydrolift turcks or similar equipment when used for transportation purposes, mixer trucks over six and one- half (6 1/2) cu.yds, batch trucks wet or dry over 4 - ""34-E"" batches single equipment operated by employees withing this Bargaining unit. Six
(6) wheel pole trailers and one (1) man oil distributors, fork-lift over four (4) ton and mobile mixers.
GROUP 4: Drivers on heavy equipment over sixteen (16) cu.yds.
or twenty-four (24) ton, such as Koehring or similar dumpsters, tract trucks, Euclids, hug bottom dumps, tournapulls, tournarockers or similar equipment when used for transportation purposes, pole trailers over six (6) wheels, water pulls, low-boy trailers tandem axles, quad axle or more no-weight limitation, diesel and/or heavy equipment mechanics.
GROUP 5: Mechanic furnishing his own tools.
D - 24
TEAM0135-011 04/01/2025
TRUCK DRIVER (HEAVY AND
HIGHWAY CONSTRUCTION (LaPorte
& St. Joseph Counties))
GROUP 1.....................$ 34.69 20.51
GROUP 2.....................$ 34.74 20.51
GROUP 3.....................$ 34.79 20.51
GROUP 4.....................$ 34.84 20.51
GROUP 5.....................$ 34.89 20.51
GROUP 6.....................$ 34.94 20.51
GROUP 7.....................$ 34.99 20.51
GROUP 8.....................$ 35.04 20.51
GROUP 9.....................$ 35.09 20.51
GROUP10.....................$ 34.54 20.51
GROUP11.....................$ 35.09 20.51
GROUP12.....................$ 35.19 20.51
TRUCK DRIVER CLASSIFICATIONS
GROUP 1: Single/batches axle straight trucks; Batch trucks, wet or dry 3 (34E) axle or less; Single axle Grease and maintenance truck
GROUP 2: Single axle fuel and water trucks
GROUP 3: Single axle ""dog-legs"", and tandem…
This is the start of the file's text. The full file is on GovTribe.