Amendment A001.pdf
PDF 174 KB Posted
- Solicitation number
- 69056725R000003
About this file
This document is an Amendment (A001) to a Federal Highway Administration solicitation for the MT FLAP PARK 2021(1) Old Yellowstone Trail South Improvements & Preservation project. The amendment, dated 4/30/2025, revises the Special Contract Requirements by updating the Table of Contents and adding requirements to Section 303 (Road Reconditioning). Specifically, the amendment adds Surface Course Aggregate to the material list and introduces a new construction requirement to break or pulverize boulders in-place within the roadway according to Section 622, using surface course aggregate to fill voids when needed.
The solicitation is exclusively available to six pre-selected prime contractors: H-K Contractors, M.A. Deatley Construction, Missouri River Contractors, Oftedal Construction, Riverside Contracting, and Sundt Construction. The project is being advertised on SAM.gov to help potential subcontractors identify opportunities, but proposals will only be accepted from the listed prime contractors. The solicitation is issued by the Department of Transportation Federal Highway Administration, with the project located in Vancouver, Washington.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| QA_04-30-2025.pdf | ||
| QA_04-29-2025.pdf | ||
| QA_04-28-2025.pdf | ||
| QA_04-24-2025.pdf | ||
| QA_04-23-2025.pdf | ||
| FLH Bridge oversized or overload vehicle permit request form.pdf | ||
| mta-park2021-1_control-points.xlsx | XLSX spreadsheet | |
| RFP_69056725R000003_MT FLAP PARK 2021(1).pdf | ||
| Physical Data.zip | ZIP file | |
| mta-park2021-1_Geotechnical report.pdf | ||
| mta-park2021-1_plans.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
N/A
PAGE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)
A001 4/30/2025 N/A See Box 14
6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A
Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.
X
69056725R000003
9B. DATED (SEE ITEM 11)
4/3/2025
10A. MODIFICATION OF CONTRACT/ORDER NO.
N/A
10B. DATED (SEE ITEM 13)
CODE: N/A FACILITY CODE: N/A
N/A
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
(__ ) is extended, ( x ) is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN
ITEM 10A.
N/A
B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D OTHER (Specify type of modification and authority)
N/A
E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
MT FLAP PARK 2021(1), Old Yellowstone Trail South Improvements & Preservation
See page 2
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
N/A
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION NOT USABLE
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Amendment No. A001, dated 04-30-2025 MT FLAP PARK 2021(1)
Solicitation No. 69056725R000003 Old Yellowstone Trail
Page 2 South Improvements & Preservation
REVISIONS ARE AS FOLLOWS:
SPECIAL CONTRACT REQUIREMENTS
Pages iii through iv, SCR Table of Contents. Revises Table of Contents.
Page F-7a, Section 303, Road Reconditioning. Adds requirements.
ENCLOSURES
Pages:
iii through iv
F-7a iii
Special Contract Requirements Project: MT FLAP PARK 2021(1), Old Yellowstone Trail South Improvements & Preservation
SCR TABLE OF CONTENTS
SPECIAL CONTRACT REQUIREMENTS (SCR)
The following Special Contract Requirements amend and supplement the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-24, U.S. Department of Transportation, Federal Highway Administration.
DIVISION 100 GENERAL REQUIREMENTS
Section 101. — TERMS, FORMAT, AND DEFINITIONS ................................................. E-1
Section 102. — BID, AWARD, AND EXECUTION OF CONTRACT .............................. E-4
Section 103. — SCOPE OF WORK ...................................................................................... E-6
Section 104. — CONTROL OF WORK ............................................................................... E-7
Section 105. — CONTROL OF MATERIAL ....................................................................... E-8
Section 106. — ACCEPTANCE OF WORK ...................................................................... E-10
Section 107. — LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC ..................................................... E-11
Section 108. — PROSECUTION AND PROGRESS ......................................................... E-21
Section 109. — MEASUREMENT AND PAYMENT ....................................................... E-23
DIVISION 150 PROJECT REQUIREMENTS
Section 151. — MOBILIZATION ...................................................................................... E-28
Section 152. — CONSTRUCTION SURVEY AND STAKING ....................................... E-29
Section 153. — CONTRACTOR QUALITY CONTROL .................................................. E-32
Section 154. — CONTRACTOR SAMPLING AND TESTING ........................................ E-37
Section 155. — SCHEDULES FOR CONSTRUCTION CONTRACTS ........................... E-38
Section 156. — PUBLIC TRAFFIC .................................................................................... E-48
Section 157. — SOIL EROSION AND SEDIMENT CONTROL...................................... E-49
DIVISION 200 EARTHWORK
Section 201. — CLEARING AND GRUBBING .................................................................. F-1
Section 204. — EXCAVATION AND EMBANKMENT .................................................... F-2
DIVISION 300 AGGREGATE AND BASE COURSES
Section 301. — UNTREATED AGGREGATE COURSES ................................................. F-3
Section 303. — ROAD RECONDITIONING ....................................................................... F-3
Revised by Amendment A001 iv
Project: MT FLAP PARK 2021(1), Old Yellowstone Trail South Improvements & Preservation
DIVISION 600 INCIDENTAL CONSTRUCTION
Section 617. — GUARDRAIL .............................................................................................. F-8
Section 622. — RENTAL EQUIPMENT .............................................................................. F-9
Section 623. — GENERAL LABOR .................................................................................. F-10
Section 624. — TOPSOIL ................................................................................................... F-11
Section 625. — TURF ESTABLISHMENT ....................................................................... F-12
Section 628. — TEMPORARY STREAM DIVERSIONS ................................................. F-14
Section 633. — PERMANENT TRAFFIC CONTROL ...................................................... F-15
Section 635. — TEMPORARY TRAFFIC CONTROL ..................................................... F-16
DIVISION 700 MATERIAL
Section 713. — ROADSIDE IMPROVEMENT MATERIAL ............................................ G-1
Section 718. — TRAFFIC SIGNING AND MARKING MATERIAL ............................... G-3
Section 719. — COATING MATERIAL ............................................................................. G-4
F-7a
Project: MT FLAP PARK 2021(1), Old Yellowstone Trail South Improvements & Preservation
Section 303. — ROAD RECONDITIONING
Material
303.02 Add the following to the material list:
Surface Course Aggregate 703.05
Construction
303.06 Roadbed Reconditioning Add the following:
Break or pulverize boulders in-place within the roadway according to Section 622. Use surface course aggregate to fill voids when needed.