This document is an attachment containing vicinity and site maps for a tree clearing project as part of the Yellowstone National Park Norris to Golden Gate, Phase 3 contract opportunity.

The federal contract opportunity is for a Firm Fixed Price (FFP) Request for Quote (RFQ) to perform 11.5 acres of tree clearing work along the Norris to Golden Gate road corridor in Yellowstone National Park. The project is a Small Business Set-Aside under NAICS code 113310. The solicitation is being issued by the Department of Transportation Federal Highway Administration, with a technical evaluation using Lowest Price Technically Acceptable (LPTA) criteria. The clearing limits are shown across 7 site plan drawings. Contractors must be registered in SAM.gov prior to submitting a quote.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 0003

N

Begin Project

I- --, U1 0 s:: 2 = 0 C'D ., SCALE IN FEET

1000 ft,___ _ ___.

End Project

YELLOWSTONE

NATIONAL PARK

Bunsen Peakf

WY NPS YELL 10(24)

NPS PMIS NO. 317309

STATE

WY

PROJECT

NPS YELL 10(24)

NORRIS TO GOLDEN GATE, PHASE 3

TREE REMOVAL

FALL 2024

CLEARING WORK

VICINITY MAP

SHEET

NUMBER

1 or 7

I SCAlE

500FT

I

NOTE:

Clearing limits are approximate.

Tree removal limits will be staked or flagged in the field.

STATE PROJECT

WY NPS YELL 10(24) 2 of 7

NORRIS TO GOLDEN GATE, PHASE 3

CLEARING PLAN

Total Clearing Area: 11.5 Acres

SCALE

SODFT

NOTE:

Clearing limits are approximate.

Tree removal limits will be staked or flagged in the field.

STATE PROJECT

WY NPS YELL 10(24)

NORRIS TO GOLDEN GATE, PHASE 3

SOOFT

I

NOTE:

Clearing limits are approximate.

Tree removal limits will be staked or flagged in the field.

STATE PROJECT

WY NPS YELL 10(24)

NORRIS TO GOLDEN GATE, PHASE 3

SOOFT

I

NOTE:

Clearing limits are approximate.

Tree removal limits will be staked or flagged in the field.

STATE PROJECT

WY NPS YELL 10(24) s of 7

NORRIS TO GOLDEN GATE, PHASE 3

SOOFT

NOTE:

Clearing limits are approximate.

Tree removal limits will be staked or flagged in the field.

STATE PROJECT

WY NPS YELL 10(24) 6of7

NORRIS TO GOLDEN GATE, PHASE 3

SOOFT

I

NOTE:

Clearing limits are approximate.

Tree removal limits will be staked or flagged in the field.

STATE PROJECT

WY NPS YELL 10(24) 7 of 7

NORRIS TO GOLDEN GATE, PHASE 3

Cover Page
Sheet 2
Sheet 3
Sheet 4
Sheet 5
Sheet 6
Sheet 7

File details come from the government source that posted it. Updated .