This document contains answers to technical questions regarding federal solicitation number 69056723B000022 for the Mitchell Street and Black Rock Road Reconstruction project by the Department of Transportation Federal Highway Administration. Key details include that the project involves reconstruction of Mitchell Street and Black Rock Road including a bridge over an ordinary high water mark, will utilize a small business set aside, has an estimated 10 overload permit requests per month, specifies concrete mix design requirements and testing procedures, and will address issues around utility relocations and traffic control through future amendments. The project construction is to be completed in half widths with traffic on gravel and will require excavation work not quantified in existing bid items.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OR FLAP POLK MITCHELL(1)
Mitchell Street and Black Road Reconstruction
# General Technical Question Answer Date
1 X
The way I read this is that it is a Small Business
Set‐Aside only requirement.
No minority contractor required participation
(DBE) or Trible employment (TERO) requirement?
Correct. 10/11/2023
2 X Are AASHTOWare or Expedite files available for this solicitation?
No. 10/16/2023
3 X
If there are no AASHTOWare or Expedite files available for this solicitation, is there an excel version of the bid schedule available for use?
No. 10/16/2023
4 X Please provide any of the existing bridge as‐ built drawings.
As‐built drawings of the existing bridge are not available. Please bid according to the solicitation documents.
10/16/2023
5 X
SCR 562.03 States temporary bridge to have minimum clear span length of 30 feet. It also states to provides structure to completely span the Ordinary High Water (OHW). Is a multi‐ span bridge with a minimum 30 foot clear span allowed?
Only if multi‐spans being used completely span over OHW.
10/18/2023
6 X
Plan Sheet J.3 calls out temporary bridge Stat
502+11.59 to 503+14.78. Does bridge need to span these Stations or just OHW per SCR
562.03?
The total length of the temporary bridge needs to cover the limits of 502+11.59 to
503+14.78, but each span must be at least
30‐feet long and completely span OHW.
10/18/2023
7 X
Contractor is to process all overload and permit load requests with 14 days. How may permit requests should be anticipated?
It is estimated at approximately 10 per month based on overload permit requests over the past year.
10/18/2023
8 X
SCR 562.07 says we need to provide an NBIS safety inspection of the bridge prior to opening to traffic and submit an inspection report. Does this inspection need to be completed by an
NBIS certified bridge inspector or is an inspection performed by the EOR acceptable?
In accordance with Subsection 562.07, see
23 CFR 650 Subpart C – National Bridge
Inspection Standards.
10/18/2023
9 X
The Guardrail Transitions for this project refers us to AKDOT Style G‐32.03. For maintenance purposes, would an Oregon BR207 with an asymmetrical transition panel for MGS be a better option? Please advise.
Please submit bids according to the solicitation documents.
10/27/2023
Check General or Technical
10 X Is ASTM C 33 allowed to be used instead of
AASHTO M6 & M80?
No. Please submit bids according to the solicitation documents.
10/27/2023
11 X
Sampling from Point of Placement is specified.
Per ASTM C 172 & NRMCA CIP 21, point of discharge should be used instead of point of placement. Will point of discharge sampling be used instead?
No. Please submit bids according to the solicitation documents.
10/27/2023
12 X
Concrete air is listed as 6% for ¾” aggregate.
Per ASTM C33 & ODOT, the Willamette Valley is considered Moderate, F1 Exposure – which is
5% +‐ 1.5%. Elevation of the jobsite is under
1000 ft. Will 5% be accepted?
Conform to the requirements of Subsection
552.03, and please submit bids according to the solicitation documents.
10/27/2023
13 X
Type V Cement is listed. Type V cement is unavailable in this market. Sulfate resistance is not needed for our climate. Type I/II and Type
1L are available, so will these types be accepted?
This will be addressed under Amendment
A003.
10/27/2023
14 X
300 Revolutions is specified. Due to the location of the jobsite in reference to a batch plant, this will need to be waived. Please advise if this can be waived.
The Government does not intend to waive this requirements. Please submit bids according to the solicitation documents.
10/27/2023
15 X No Shrinkage testing is listed. Can we confirm there is no Shrinkage requirements?
Please submit bids according to the requirements in the solicitation documents.
10/27/2023
16 X
Existing Aggregate Testing of AASHTO T 27/11 is available by KR personnel. Those results paired with existing ASTM C 33 testing provides ample amounts of data on the Aggregate. Will continued, daily testing still be required on existing stockpiles? Outside testing is strongly discouraged due to inaccuracy of testing and the unrepresentativeness of a stockpile sample.
Samples from the belt are unavailable daily due to material not being processed.
Testing according to the solicitation documents will be required. Please submit bids according to the solicitation requirements.
10/27/2023
17 X
The changes shown in Amendment A002 add to concerns related to the presence of overhead powerlines. The permanent relocation work outlined in Section 104.06 Utility Relocations does not describe the degree of relocation work to be performed by the Utility Companies.
Could you please clarify what utilities will be relocated by others, and to what extent?
This will be addressed under Amendment
A003.
10/27/2023
18 X
The response in Amendment A003 regarding overhead power seems to omit the relocation of overhead powerlines around the bridge, which would need to be removed prior to any work beginning around this area. Please confirm that these overhead powerlines are to be relocated as well.
This will be addressed under Amendment
A004.
10/31/2023
19 X
We are reaching out to see if you have a list of contractors that are bidding this project as prime? If you do could you send us a copy?
We do not. Bidders may obtain the registered vendors list (aka planholders list) from sam.gov after linking their entity to their registration. If you are signed into
SAM.gov with your registered entity and you cannot see the Interested Vendors List, you will need to be assigned the Contract
Opportunities Administrator role for your entity in SAM.gov.
See GSAFSD_kb_articles ‐ GSA Federal
Service Desk Service Portal for more information.
If you need additional assistance, you can reach the Federal Service Desk at 866‐606‐
8220.
11/2/2023
20 X
Section 156.07(m) and the traffic control plans indicate that a majority of the reconstruction for this project will be done one lane at a time to facilitate traffic in the opposite lane. The
Section at the rockery walls in the left lane and the section that is bypassed by the diversion bridge are the exceptions. That would mean there are 440 flagging hours to construct the project which with two flaggers at 10 hours a day that leaves 22 days, which is not enough flagging hours by a large margin. Please advise.
This will be addressed under Amendment
A005.
11/2/2023
21 X
Because the project is going to be constructed at half widths, can traffic run on gravel? It isn’t feasible for the contractor to pave back every shift.
Yes. 11/2/2023
22 X
If traffic can run on gravel, what does the contractor need to do with the centerline drop off? If the rock is left at bottom of pavement elevation there will be a differential between the old and new. Is the contractor supposed to over build the rock section and then remove it later? If so how is that aggregate paid?
This will be addressed under Amendment
A005.
11/2/2023
23 X
The contractor is to build the roadway in half sections and maintain an 11’ lane for traffic per section 156.07(c) of the SCR’s. With the existing roadway width this is not constructable, as the existing roadway is at most 20’ wide with the same centerline alignment. The new typical roadway section is also only a 10’ travel lane with a 1’ gravel shoulder, so even once the new section is built on the first half it still does not seem feasible that the contractor will be able to maintain an 11’ lane. Please advise.
This will be addressed under Amendment
A005.
11/2/2023
24 X
During paving operations it would seem that a pilot car would be beneficial for the safety of the workers and the traveling public as we will be paving a long stretch of roadways with quite a few curves per shift. If a pilot car was used how would it be paid?
Payments will be made according to the solicitation documents, so please submit bids according to the solicitation documents.
11/2/2023
25 X
In looking at the Earthwork Data Listings and the Cross Sections provided, it seems that the existing roadway inside the abutment limits
(Scour Mitigation area) are not included in either the roadway excavation or the structure excavation quantities. How will this excavation be paid? It does not seem to be incidental to any of the existing bid items, please advise.
Also is there a quantity for that excavation?
Payments will be made according to the solicitation documents, so please submit bids according to the solicitation documents.
11/2/2023
26 X Is the excavation required for the treatment ditch incidental to that bid item?
This will be addressed under Amendment
A005.
11/2/2023
27 X
The contractor is allowed a one lane closure utilizing traffic signals from July 8, 2024 to
August 5, 2024 for construction of the Rockery
Walls. There is no such closure allowed for the precast concrete block retaining wall even though we will run into the same issues, it is not feasible to construct the wall in a way to have it backfilled up to roadway elevation at the end of every shift. Please advise.
This will be addressed under Amendment
A005.
11/2/2023
28 X
Being that there are only 2 business days prior to the bid date, is the bid date going to be extended so we have time to go over the changes in Addendum 5?
The Government does not intend to extend the bid opening date. Please submit bids according to the solicitation documents.
11/2/2023