This document contains questions and answers regarding a federal solicitation for highway repairs in Montana. The solicitation is for Project No. MT FS ERFO 2018(1) - 73(1) Helena-Lewis & Clark 2018 Repairs, Phase 1 issued by the Department of Transportation Federal Highway Administration. One question asks for clarification on measurement and payment terms for flagger time, as it is not listed in the bid schedule. The answer directs the contractor to review the measurement guidelines in Section 635 and 109.02 of the contract documents, and notes that temporary traffic control is a lump sum bid item.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project No. MT FS ERFO 2018(1)‐73(1) Project: Helena‐Lewis & Clark 2018 Repairs Phase I
# General Technical Question Answer Date
1 X
General Question on Measurement and Payment:
Bid Schedule Page A‐10 Measure is LPSM And Section 635. — TEMPORARY TRAFFIC CONTROL Measurement Page F‐12 Do not match units of measure.
How is contractor getting paid for Flagger time Not in Bid Schedule?
Sub‐Section 635.24‐Measurement of the contract specifications provide the contractor measurement guidelines for section 635 pay items listed in the bid schedule in accordance with 635 and 109.02 as applicable. Please see Section 109 and 635 of the FP‐14 and Special Contract Requirements (SCR’s) of the contract for measurement and payment guidelines. Temporary traffic control is listed in the bid schedule as a lump sum bid item. Please bid accordingly.
17‐Mar‐22
Check General or Technical