Q&A_12-11-19.pdf

PDF 98 KB Posted

Attached to
OR DOT 204(1), Weston-Elgin Highway Resurfacing Federal contract opportunity
Solicitation number
69056719B000029
Issued by
Department of Transportation Federal Highway Administration

About this file

This document provides details on a federal contract opportunity for highway resurfacing work. The Oregon Department of Transportation is seeking bids for Project OR DOT 204(1), which involves milling and repaving 19.47 miles of Highway 204 with asphalt concrete, as well as guardrail repairs and surface treatment on three Sno-Parks. The estimated price range for the project is $5-10 million. Work is anticipated to be completed in fall 2020. This opportunity is set aside for small businesses. Interested vendors must register at beta.sam.gov to view the vendor list. The Department of Transportation Federal Highway Administration is the contracting agency.

View the file

Other files for this federal contract opportunity

Other files attached to OR DOT 204(1), Weston-Elgin Highway Resurfacing, newest first.
File Type Posted
Bid Opening Summary_Weston-Elgin.pdf PDF
Amendment A003.pdf PDF
Q&A_12-12-19.pdf PDF
Amendment A002.pdf PDF
Amendment A001.pdf PDF
OR204 - 17V-237.pdf PDF
Plan Request.pdf PDF
IFB_Weston Elgin.pdf PDF
Brand Name Justification Request_Weston-Elgin.docx DOCX document
OR2041_100% Weston-Elgin_PAVEMENT FIELD REVIEW MEMO.pdf PDF
Revised_Plans_OR2041 100% Weston Elgin.pdf PDF
OR204 32V-073_AC.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No. OR DOT 204(1) Project Weston‐Elgin Highway Resurfacing

# General Technical Question Answer Date

1 X

Regarding adjacent or virtually adjacent sites within ½ mile of the project (§ 108.01A Labor);

is that measurement of ½ mile aerial (as the crow fly’s) or measured along the access road to the site? My assumption is that its an aerial measurement but I need to verify.

Your assumption is correct. The actual distance from the project measured to the site is correct.

12/5/19

2 X

Plans Sheet C:3 shows full depth pavement widening. The section has geotextile, with roadway aggregate method 2, topped with asphalt. My question has to do with preparing this area to subgrade before installing the geotextile. I would assume this area needs some sort of excavation of material to get the section down to bottom of the fabric layer.

How would this be paid for?

See Subsection 109.05(b) of FP‐14. 12/11/19

3 X Is there any surveying grade books that will be made available for construction of this project?

No. 12/11/19

Check General or Technical

4 X

Sheet E‐36 of the specifications 156.07(n) requires adjacent lanes be paved to the same elevation by the end of each day. Does this mean that one should expect to pave a few hours, stop, back the paving operation up, let the mat cool to facilitate traffic and then begin paving again in the opposite lane until the lanes are squared up? Or is it within 24 hours the lanes need to be squared up? This would make a massive difference when determining asphalt production, cost, and time along with potential smoothness issues on the overlay section of the roadway.

This will be addressed under a forthcoming amendment.

12/11/19

5 X Is 24 hour/day work allowed on this project? No. See Subsections 156.07 and 156.08. 12/11/19