Q&A_05-10-19.pdf

PDF 56 KB Posted

Attached to
MT DAR 2019(1), Defense Access Roads FY 2019 & MT TETON 144(1), North Fork Project
Solicitation number
69056719B000009
Issued by

About this file

Q&A 5-10-2019

View the file

Other files

File Type Posted
BidSum_MT_DAR_2019(1)_&_MT_Teton_144(1).pdf PDF
Plan_Request_Form.pdf PDF
IFB_DAR.pdf PDF
01_mt-d201901_DAR2019(1)_PLANS_SIGNOFF.pdf PDF
mt-d201901_DAR2019(1)_HydraulicsMemo_Final.pdf PDF
PROJECT_DESCRIPTION.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MT DAR 2019(1) & MT Teton 144(1) Defense Access Roads FY 2019 & North Fork Project

# General Technical Question Answer Date

1 X

With regard to Typical Sections Sheet 1 of 3, Sheet C‐2, we are to regrade existing ditches to a 17' Max. With this much disturbance are we required to obtain a SWPPP Permit? We will exceed the footage of a maintenance road project.

The project will not be disturbing enough area to warrant a SWPPP. The majority of the shoulder work along the length of the project will be to break up vegetated material on shoulders and 3 feet down foreslopes. Any areas where ditch work is wider will be verified by the CO according to Section 303.03A.

5/10/19