A001_ID_Snake_River.pdf

PDF 348 KB Posted

Attached to
ID BONVIL 2016(1), Snake River Road and Bear Creek Road
Solicitation number
69056718B000025
Issued by

About this file

A001_Snake River

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

N/A

PAGE

1 of X

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)

A001 01/11/2019 N/A See Blcok 10

6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A

Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.

X 69056718B000025

9B. DATED (SEE ITEM 11)

12/04/2018

10A. MODIFICATION OF CONTRACT/ORDER NO.

N/A

10B. DATED (SEE ITEM 13)

CODE: N/A FACILITY CODE: N/A N/A

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

(__ ) is extended, ( x ) is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

N/A

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN

ITEM 10A.

N/A

B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

N/A

C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

N/A D OTHER (Specify type of modification and authority)

N/A E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

ID BONVIL 2016(1), Snake River Road and Bear Creek Road

See page 2

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

N/A

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITION NOT USABLE

30-105 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

Project No. ID BONVIL 2016(1) Project Name: Snake River Road and Bear Creek Road

Amendment No. A001, dated 01/11/2019 Solicitation No. 69056718B000025

REVISIONS ARE AS FOLLOWS:

SPECIAL CONTRACT REQUIREMENTS

Page E-9, Subsection 105.04 Storing and Handling Material. Adds Stockpile location for Item 31401-0000 Stockpiled Aggregate.

Page E-12, Subsection 107.01. Adds anticipated Government secured permits at Bureau of Reclamation Pit

Page E-13 &14, Revises sheets to accommodate 107.01 language.

ENCLOSURES

Pages:

E-9 E-12 through 14

E-9 DIVISION 100

Special Contract Requirements Project: BONVIL 2016(1), Snake River Road and Bear Creek Road

Allow 12 days (in addition to other agency time requirements) for approval of documents submitted to the CO.

Weed free certification. All material sources and materials incorporated into the work must be certified to be free from noxious weeds, invasive plants, and other deleterious materials by a federal, state or local public agency. Commercial certifications may be acceptable if materials have been certified through the North American Weed Free Forage Program standard or a similarly recognized certification process approved by the CO. Submit material certifications to the CO for approval at least 5 days before their use in the work.

105.04 Storing and Handling Material. Delete the text of the second paragraph and substitute the following:

Use portions of the right-of-way approved by the CO for staging or storing of materials such as culverts, geotextile fabric, temporary traffic control devices, aggregates, and for equipment parking.

Stockpile item 31401-0000 STOCKPILED AGGREGATE at Bureau of Reclamation pit as directed by the CO and according to Subsection 107.01 and Section 314.-STOCKPILED

AGGREGATES.

Provide additional space as needed. Do not use private property for staging or storage without written permission of the owner or lessee. Submit copies of agreements and documents.

Revised by Amendment A001

E-12 DIVISION 100

Project: BONVIL 2016(1), Snake River Road and Bear Creek Road

Section 107. — LEGAL RELATIONS AND

RESPONSIBILITY TO THE PUBLIC

09/17/18– FP-14

107.01 Laws to be Observed. Delete the third paragraph and substitute the following:

Do not stockpile item 31401-0000 STOCKPILED AGGREGATE at Bureau of Reclamation Pit until the Government has secured permits and as directed by the CO. It is anticipated the permits will be secured prior to notice to proceed.

Obtain all permits or agreements that are required by the Contractor’s methods of operation. Allow adequate time in the construction schedule for obtaining permits and agreements. Furnish copies of all acquired permits and agreements to the CO.

Comply with the requirements of the Fire Protection and Suppression Plan included in this contract (See Section J).

107.02 Protection and Restoration of Property and Landscape. Amend as follows:

Delete the third paragraph and substitute the following:

Do not disturb any area outside the construction limits unless authorized according to Subsection 105.02(c). Replace trees, shrubs, or vegetated areas outside the construction limits damaged by construction operations as directed and at no cost to the Government. Only remove damaged limbs of existing trees when directed by an approved arborist.

Delete the sixth paragraph and substitute the following:

The utilities within the project limits have not been located or mapped for this project.

Various utilities exist under and above the road. Power, water lines, and cable exist within the County right-of-way.

Consult the following utility contacts before performing work that may affect their facilities:

POWER & CABLE TELEPHONE

Bonneville Power 272 High Country Road Palisades, ID 83428

Silver Star Communications Rob Heiner Office: 208-354-3300

Phone: 208-483-3391 Mr. Heiner: 307-883-6690 Email: rheiner@silverstar.net

E-13 DIVISION 100

Project: BONVIL 2016(1), Snake River Road and Bear Creek Road

CAMPGROUND WATER POWER AND WATER

Colby Jacobson, National Forest Service

(PRIVATE LINES)

Phone: 208-881-2686 (Refer to the next paragraph below) Email: colbyjjacobson@fs.fed.us

Contact the Idaho Dig Line (811, or 1-800-342-1585) not less than 3 business days before the start of any excavation on this project.

Protect utilities from construction operations. Utilities will not be relocated. In the event of conflict, protect the utilities while working in the area and notify utility contacts of the extent of conflict and protection measures taken.

107.03A Public Notice. (Added Subsection).

Publish notices of the road work in local newspapers and on local radio stations. Include a description of the work, expected delays, and periods when the road is open to traffic without delays. Issue the notice at least 5 days before beginning work on the project or beginning work after a winter suspension, and at least two times during the normal tourist season.

107.08 Sanitation, Health, and Safety. Add the following after the first paragraph:

Submit an accident prevention plan for implementing safety and health standards at the Preconstruction Conference. Use the Government furnished Form WFLHD-28, Guide Outline of Contractor's Accident Prevention Plan.

107.10 Environmental Protection. Amend as follows:

(c) Dirt, plant, and foreign material. Delete the first paragraph and substitute the following:

Remove dirt, plant, and foreign material from vehicles and equipment before entry into Caribou-Targhee National Forest. Prevent introduction of noxious weeds and non-native plant species into the work site. Follow applicable Federal land management agency requirements and state requirements. Maintain cleaning and inspection records. Clean hauling vehicles before their initial entry; subsequent entries will not require cleaning unless requested. Notify the CO a minimum of 48 hours before entry to allow for inspection.