Q&A_5-9-18.pdf
PDF 72 KB Posted
- Solicitation number
- 69056718B000008
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BidSum.pdf | ||
| Q&A_5-16-18.pdf | ||
| Q&A_5-15-18.pdf | ||
| A001.pdf | ||
| Plan_Set_-_OR_WASCO_102(1)_FINAL.pdf | ||
| Plan_Request_for_Internet.docx | DOCX document | |
| IFB_OR_Wamic_Market.pdf | ||
| PROJECT_DESCRIPTION_OR_Wasco_102(1).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OR WASCO 102(1)
Wamic Market Road and Ramsey Creek Overlay
# General Technical Question Answer Date
1 X
How do you intend to replace the existing steel posts that are attached to the box culvert? No drawings are referenced or provided. These posts are not like the ones shown on the drawings at sheet D.4 of the plans.
Guardrail replacement at the Ramsey Creek box culvert will be clarified in a forthcoming Amendment.
5/9/18
2 X
I also noticed the existing guardrail is only 150 LF per side not 250 LF? In order to provide an accurate bid for this project we need some clarification.
Thank you for the information. Measure and payment for the actual quantity removed will be according to Subsections 109.02, 203.07, and 203.08.
5/9/18