6905 Z1 Revised Evaluation Criteria.docx
DOCX document 27 KB Posted
- Solicitation number
- 6905 Z1
- Issued by
- Saline County, Nebraska
About this file
This document is a revised evaluation criteria for Request for Proposal (RFP) Number 6905 Z1 issued by the State of Nebraska, Department of Administrative Services, Materiel Division, State Purchasing Bureau. The purpose of this RFP is to select a qualified contractor to provide KUON TV Tower Cross Member Replacement and Remediation at a competitive and reasonable cost. The mandatory requirements for proposal submissions include the Request for Proposal for Contractual Services form, Corporate Overview, Technical Approach, and Cost Proposal. The evaluation criteria consist of Corporate Overview (35 points), Technical Approach (45 points), and Cost Proposal (20 points), with a total of 100 points possible without oral interviews. The Cost Proposal points will be awarded based on the lowest cost submitted receiving the maximum points, and all other proposals being scored proportionately.
The pricing terms, set-asides, incumbents, current environment, funding requirements, and sources are not explicitly stated in the document. However, it is noted that the resulting contract may not be an exclusive contract, and the State reserves the right to contract for the same or similar services from other sources in the future.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 6905 Allstate Response.pdf | ||
| 118643 O5 RFP.doc | DOC document | |
| 6905 Z1 Addendum Four Revised Schedule of Events.pdf | ||
| 6905 Z1 Addendum Two Q&A.pdf | ||
| 6905 Z1 Addendum One Revised Schedule of Events.pdf | ||
| 6905 Z1 Exhibit A Inspection Report.pdf | ||
| 6905 Z1 Revised Cost Proposal.xlsx | XLSX spreadsheet | |
| 118643 O5 RFP.pdf | ||
| 6905 Precision Response.pdf | ||
| 6905 Z1 Attachment A - Technical Requirements.docx | DOCX document | |
| 6905 Z1 RFP Respondents List.pdf | ||
| 6905 Z1 Addendum Three Revised RFP Webinar Link.pdf | ||
| 6905 Z1 Final Evaluation Document.pdf | ||
| 6905 Z1 RFP Intent to Award.pdf | ||
| 6905 National Tower Response.pdf | ||
| 118643 O5 RFP.pdf | ||
| 6905 Z1 Cost Proposal.xlsx | XLSX spreadsheet | |
| 6905 Z1 Attachment A - Technical Requirements.docx | DOCX document | |
| 6905 Z1 Evaluation Criteria.docx | DOCX document | |
| 6905 Z1 Exhibit A Inspection Report.pdf | ||
| 118643 O5 RFP.doc | DOC document |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REVISED EVALUATION CRITERIA
RFP NUMBER 6905 Z1
KUON TV Tower Cross Member Replacement and Remediation Opening Date: July 22, 2024
Mandatory Requirements The proposals will first be examined to determine if all mandatory requirements listed below have been addressed to warrant further evaluation. Proposals not meeting mandatory requirements will be excluded from further evaluation. The mandatory requirement items are as follows:
Request for Proposal For Contractual Services form, signed in ink, Corporate Overview, Technical Approach; and Cost Proposal.
Evaluation Criteria All responses to this Request for Proposal, which fulfill all mandatory requirements, will be evaluated. Each category will have a maximum possible point potential. Areas that will be addressed and scored during the evaluation include:
| Evaluation Criteria |
| Possible Points |
| Part 1 Corporate Overview |
| 35 |
Part 2 Technical Approach (Project & Business Requirements)
| Part 3 Cost Proposal Points |
| 20 |
| Total Points without Oral Interviews |
| 100 |
Part 4 – Cost Proposal Points Cost points should be calculated as follows:
0. Establish lowest cost submitted – lowest cost submitted receives the maximum points.
0. To assign points to all others, the following formula should be followed:
Lowest Cost Submitted Cost Submitted x Maximum Possible Cost Points = Cost Points to Award (see samples below)
Formula
Sample
Sample
Sample
Lowest Cost Submitted
$100,000
$100,000
$100,000
Cost Submitted
$100,000
$200,000
$150,000 x Maximum Possible Cost Points
= Points To Award
26.7