6905 Z1 Evaluation Criteria.docx
DOCX document 27 KB Posted
- Solicitation number
- 6905 Z1
- Issued by
- Saline County, Nebraska
About this file
This document is a Request for Proposal (RFP) issued by the State of Nebraska, Department of Administrative Services (DAS), Materiel Division, State Purchasing Bureau (SPB), for the purpose of selecting a qualified Contractor to provide KUON TV Tower Cross Member Replacement and Remediation at a Competitive and Reasonable Cost. The RFP outlines the mandatory requirements that proposals must meet, as well as the evaluation criteria that will be used to assess the responses. The evaluation criteria include Corporate Overview, Technical Approach, and Cost Proposal, with a total of 100 possible points. The Cost Proposal points will be calculated based on a formula that awards the maximum points to the lowest cost submitted.
The RFP provides details on the specific project, which involves the replacement and remediation of the KUON TV Tower Cross Members. The contract resulting from this RFP may not be an exclusive contract, as the State reserves the right to contract for the same or similar services from other sources in the future.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 6905 Allstate Response.pdf | ||
| 6905 Z1 Revised Evaluation Criteria.docx | DOCX document | |
| 118643 O5 RFP.doc | DOC document | |
| 6905 Z1 Addendum Four Revised Schedule of Events.pdf | ||
| 6905 Z1 Addendum Two Q&A.pdf | ||
| 6905 Z1 Addendum One Revised Schedule of Events.pdf | ||
| 6905 Z1 Exhibit A Inspection Report.pdf | ||
| 6905 Z1 Revised Cost Proposal.xlsx | XLSX spreadsheet | |
| 118643 O5 RFP.pdf | ||
| 6905 Precision Response.pdf | ||
| 6905 Z1 Attachment A - Technical Requirements.docx | DOCX document | |
| 6905 Z1 RFP Respondents List.pdf | ||
| 6905 Z1 Addendum Three Revised RFP Webinar Link.pdf | ||
| 6905 Z1 Final Evaluation Document.pdf | ||
| 6905 Z1 RFP Intent to Award.pdf | ||
| 6905 National Tower Response.pdf | ||
| 118643 O5 RFP.pdf | ||
| 6905 Z1 Cost Proposal.xlsx | XLSX spreadsheet | |
| 6905 Z1 Attachment A - Technical Requirements.docx | DOCX document | |
| 6905 Z1 Exhibit A Inspection Report.pdf | ||
| 118643 O5 RFP.doc | DOC document |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EVALUATION CRITERIA
RFP NUMBER 6905 Z1
KUON TV Tower Cross Member Replacement and Remediation Opening Date: July 11, 2024
Mandatory Requirements The proposals will first be examined to determine if all mandatory requirements listed below have been addressed to warrant further evaluation. Proposals not meeting mandatory requirements will be excluded from further evaluation. The mandatory requirement items are as follows:
Request for Proposal For Contractual Services form, signed in ink, Corporate Overview, Technical Approach; and Cost Proposal.
Evaluation Criteria All responses to this Request for Proposal, which fulfill all mandatory requirements, will be evaluated. Each category will have a maximum possible point potential. Areas that will be addressed and scored during the evaluation include:
| Evaluation Criteria |
| Possible Points |
| Part 1 Corporate Overview |
| 15 |
Part 2 Technical Approach (Project & Business Requirements)
| Part 3 Cost Proposal Points |
| 45 |
| Total Points without Oral Interviews |
| 100 |
Part 4 – Cost Proposal Points Cost points should be calculated as follows:
0. Establish lowest cost submitted – lowest cost submitted receives the maximum points.
0. To assign points to all others, the following formula should be followed:
Lowest Cost Submitted Cost Submitted x Maximum Possible Cost Points = Cost Points to Award (see samples below)
Formula
Sample
Sample
Sample
Lowest Cost Submitted
$100,000
$100,000
$100,000
Cost Submitted
$100,000
$200,000
$150,000 x Maximum Possible Cost Points
= Points To Award
26.7
File details come from the government source that posted it. Updated .