This document is an Addendum Two to Request for Proposal (RFP) Number 6837 Z1 issued by the Nebraska State Purchasing Bureau (SPB) for the purpose of selecting a qualified Bidder or Bidders to provide high-speed transport services for participants of Network Nebraska. The addendum addresses questions and answers related to the RFP, including clarification on the location of service sites, contractor documents that may be incorporated into the contract, and the ownership of information and data/deliverables. The RFP is due to be opened on January 3, 2024, at 2:00 P.M. Central Time, and the State has declined to extend the due date.
The addendum confirms that any subcontractors used by the contractor to provide service under the contract must be included in the bidder's proposal and approved by the State. The RFP does not appear to have any set-aside requirements, and the current incumbent is not specified. The funding sources and amounts for this contract opportunity are also not provided in the addendum or the related contract opportunity description.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM TWO
QUESTIONS and ANSWERS
Date: December 7, 2023
To: All Bidders
From: Dianna Gilliland/Kelly Thomas, Procurement Contract Officers
AS Materiel State Purchasing Bureau (SPB)
RE: Addendum for Request for Proposal Number 6837 Z1 to be opened January 3, 2024, at 2:00 P.M. Central Time
Questions and Answers
Following are the questions submitted and answers provided for the above-mentioned Request for Proposal. The questions and answers are to be considered as part of the Request for Proposal. It is the Bidder’s responsibility to check the State Purchasing Bureau website for all addenda or amendments.
Questio n
Number
RFP
Section
Reference
RFP
Page
Number
Question State Response
1. Appendix C Can you confirm the address listed in Appendix C for site 9?
I don’t see a street address listed, and am unable to pull Lat/Long coordinates.
Ministerial errors for the location of sites 7 & 8 have been corrected, site 9 has been removed. Refer to Appendix C – Revised.
2. Section II(F) 11 The third paragraph of Section II(F) of the Request for Proposal for Contractual Services document, titled “Project Requirements” states, “The contractors may submit with their technical proposal any E-Rate, tax exemption, USF affidavit, user agreement, service level agreement, or similar documents that the contractor wants incorporated into the Contract.”
Will the Nebraska consider including a contractor’s Acceptable Use Policy, Privacy Policy, and/or Service Level Agreement?
The identified language was a ministerial error.
RFP Section V.II., paragraph 3, Sentence 1 is hereby deleted and replaced with the following:
The contractors may submit with their technical proposal any E-Rate, tax exemption, USF affidavit, or similar documents that the contractor wants incorporated into the Contract.
3. Section I (C) 5 Given the scope of the RFP, and number of service locations, as well as the intervening holiday and New Year’s season, will Nebraska extend the due date for bids by one month?
No.
4. Section III(O) 22 The second paragraph of Section III(O) of the Master Agreement Revision #5, titled “Ownership of Information and Data/Deliverables” states, “The State shall own and hold exclusive title to any
Yes.
deliverable developed as a result of this contract. Contractor shall have no ownership interest or title, and shall not patent, license, or copyright, duplicate, transfer, sell, or exchange, the design, specifications, concept, or deliverable.”
In the ordinary course of business for any of our customers, we use the same technologies, equipment, designs, specifications, and concepts to deliver our services as we will for Nebraska.
Please confirm that the intent of this section from the Master Agreement is to only address the scenario in which contractor is asked to create unique and custom deliverables that are developed specifically for Nebraska pursuant to a custom statement of work, and it does not apply to technology, equipment, designs, specifications and concepts used by contractor in the ordinary course of its business for any customer.
5. Section III(I) 20 In Master Agreement Revision #5, the seventh paragraph of Section III(I) titled “Independent Contractor/Obligations” states, “If the Contractor intends to utilize any subcontractor, the subcontractor's level of effort, tasks, and time allocation should be clearly defined in the bidder’s proposal. The Contractor shall agree that it will not utilize any subcontractors not specifically included in its proposal in the performance of the contract without the prior written authorization of the State.”
There is a similar provision in the Request for Proposal for Contractual Services document at the end of Section II(L)(2) (titled “Contractor”). Do the references to subcontractors in these provisions refer to any subcontractors that contractor may use (such as subcontractors for trenching, boring, etc.), or does it only apply to subcontractors who are engaged to perform a portion of the telecom service itself (i.e., last mile providers/Type II providers)?
Any subcontractor used by the contractor to provide service under the contract.
This addendum will become part of the Request for Proposal and should be acknowledged with the Request for Proposal response.