679-22-8010-04corrected

38 KB Posted

Attached to
RFP Chromebook Charging Carts
Solicitation number
679-22-8010-04
Issued by
Jefferson County, Georgia

About this file

This is a Request for Proposal (RFP) issued by Jasper County Charter System (JCCS) in Monticello, Georgia, for the procurement of 85 Chromebook charging carts. The district is seeking the EarthWalk Saver Series model SS30.4, a pre-wired USB-C Power Delivery charging cart with vertical storage capacity for up to 30 devices with screens up to 14 inches. The cart features a compact 22"W x 22"D x 36.5"H design, 5-inch swivel casters with locking brakes, and includes a 600-watt USB-C power system with 30 pre-wired USB-C 3.0 charging cables. Proposals must be submitted by 4:00 PM EST on June 16, 2022, to Cara Bockholt, Director of Instructional Technology (cbockholt@jasper.k12.ga.us) and Anne Harrison, Director of Finance (aharrison@jasper.k12.ga.us). Questions regarding site visits must be directed to cbockholt@jasper.k12.ga.us, and no phone calls will be accepted. Late proposals will be considered void and unacceptable.

Quotes must include the 85 charging carts, EarthWalk Cart Art custom-designed graphic panels with installation, shipping with lift gate and pallet jack service, and white glove delivery to centralized locations in each of four district buildings. Delivery and installation charges must be listed as separate line items, and pricing for the specified equipment cannot be contingent upon purchase of additional items. Evaluation criteria prioritize cost of services and products as the highest weighted factor, followed by product quality, bidder qualifications and experience, vendor proximity to JCCS, and district experience with the vendor. Vendors must provide a minimum of three references from similar projects, including customer names, addresses, contact names, and telephone/fax numbers. The district reserves the right to negotiate with selected vendors and requires contract execution within 60 days of award. JCCS reserves the right to reject any and all bids, reduce or cancel the RFP if district funding is reduced or not approved, and will not accept standard indemnification, non-Georgia governing law, or provisions binding the district to unknown terms and conditions.

Text of this file

Jasper County Charter System 1411 College Street Monticello, GA 31064

2022 RFP Chromebook Charging Carts

Kenny Garland Superintendent

Cara Bockholt Director of Instructional Technology cbockholt@jasper.k12.ga.us

Dan Kelley Director of Network Operations dkelley@jasper.k12.ga.us

Proposals and bids must be delivered no later than 4:00 PM EST on June 16, 2022 to:

Cara Bockholt, Director of Instructional Technology, cbockholt@jasper.k12.ga.us

AND

Anne Harrison, Director of Finance, aharrison@jasper.k12.ga.us

Please note that all proposals must be received by the stated deadline. Late proposals shall be considered void and unacceptable. Proposals should not be considered delivered until the vendor receives a confirmation e-mail from one of the contacts listed above.

Questions or requests to schedule a site visit should be sent to cbockholt@jasper.k12.ga.us NO phone calls will be accepted.

If district funding is reduced, not available, or not approved for any reason, JCCS reserves the right to defer, reduce, or cancel this RFP.

JCCS RESERVES THE RIGHT TO REJECT ANY AND ALL BIDS AND PROPOSALS AND TO

AWARD IN PART OR IN TOTAL WHICHEVER IS DEEMED TO BE IN THE BEST INTEREST OF

THE SCHOOL DISTRICT.

SECTION 1—GENERAL INFORMATION

1.1 – General Information

The Jasper County Charter System (JCCS) is seeking 85 Chromebook charging carts.

1.2 – Intent of the RFP

It is the intent of this Request for Proposal (RFP) to provide bidders with sufficient information to prepare a proposal for the purchase of Chromebook charging carts.

1.3 – Evaluation Criteria

Selection will be based upon technical quality, project management, costs of goods and services, and system features. The evaluation criteria will consider but are not limited to the following factors:

1. Product quality/appropriateness/compatibility/performance consistent with the specs in the RFP

2. Bidder's qualifications/experience

3. Cost of Services and Products (Highest Weighted Factor)

4. Proximity of bidder to JCCS

5. Districts experience with vendor

JCCS reserves the right to seek clarification of any or all bidders in order to assist in the evaluation process. Additional considerations within those listed above may also include:

1. All specification terms and conditions as outlined in the RFP are complied with and met.

2. Suitability of proposed solution with respect to the district’s needs and objectives.

3. Bidder participation and responsibility clearly defined.

4. JCCS’s participation and responsibilities clearly defined.

5. Hardware and peripheral product quality and content including, but not limited to, durability, performance, integration, serviceability, warranty, maintenance, meets or exceeds industry standards, and fulfillment of criteria specified in this RFP.

6. Bidder's service and support hours are clearly defined.

7. Price of proposal including, but not limited to, individual system pricing, upgrades/downgrades pricing.

8. installation support, warranty support, training, and any other relevant options with associated pricing.

9. Experience and/or references of the company submitting proposals.

10. Installation procedures clearly defined if applicable.

1.4 – Contract Negotiation

JCCS reserves the right to negotiate with any company/supplier submitting a response to alter, clarify, or further enhance the company's proposals and/or any contract arising out of the acceptance of the response. In the evaluation of the proposal, the pricing submitted will be considered the best and final pricing.

In the event that a contract is required to complete any purchase, a maximum of 60 days will be allowed to finalize and execute the contract. Failure to execute an agreement within this time frame, for any reason, constitutes sufficient cause for voiding the award. Failure to comply with other requirements within the set time constitutes failure to execute the agreement. If the successful Proposer refuses or fails to execute the agreement, JCCS may award the agreement to the next qualified Proposer. If there is no next qualified Proposer, a new RFP may be initiated.

In addition, many standard clauses typically found in commercial contracts cannot be accepted by the District. These include the following:

● Indemnification and/or hold harmless clauses

● Governing law or venue in any state other than Georgia

● Any provision requiring the District to be bound by terms and conditions that are unknown at the time of signing the agreement

SECTION 2 – SUBMITTAL REQUIREMENTS

2.1 – General

The proposal must include all necessary hardware, software, installation, configuration, and cabling needed to complete a full installation.

Warranty terms on the hardware must be clearly defined.

Any delivery and installation charges must be clearly defined as separate line items.

Vendors may include upgrades, services, or other items in their proposal. However, the pricing of the equipment stated in the RFP must not be contingent on the purchase of any additional items quoted. These products or services must be listed as separate line items from the requested equipment.

2.2 – Company Experience and/or References

JCCS reserves the right to fully investigate the qualifications of any bidder(s) based on references supplied and publicly available information.

Vendors are required to supply a minimum of three referrals on projects of similar nature and/or magnitude. The referrals must include: customer name, address, contact names, and telephone/fax numbers.

2.3 – Confidential Material

Any material that is to be considered as confidential in nature must be clearly marked as such and will be treated as confidential by JCCS to the extent allowable by law.

2.4 – Supplemental/Supporting Materials

Please include descriptive literature/brochures, if available, for products submitted in the proposal.

SECTION 3 –SPECIFICATIONS

Reference Model:

EarthWalk Saver Series model SS30.4

● Pre-wired USBC-PD charging cart

● Vertical storage, up to 30 user cart for devices up to 14“ screen size

● Space saving 22”w X 22“d X 36.5”h design.

● Device Storage Slots 15“d X

● 11”h X 1.27“w

● 5” swivel casters w/ two locking brakes

● Includes 600watt USBC-PD power system w/ (30) pre-wired USBC 3.0 charging cables

The district seeks 85 of this model

The quote should include:

EarthWalk Cart Art Custom designed graphic panel for SS.4 , with installation Shipping and handling to include a lift gate and palate jack White glove service to deliver the specified number of carts to a centralized location in each of the four buildings

Other files

File Type Posted
Award Information —

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .