This is a Post-Abatement Verification Statement issued by Environmental Testing & Consulting, Inc. for the State of Michigan regarding hazardous materials abatement at 668 W Hollywood, Detroit, Michigan 48203. The document confirms completion of abatement and removal services for regulated asbestos-containing materials and other hazardous materials identified at the property. The post-abatement inspection was conducted on January 15, 2026, with the original report dated November 26, 2024 and a revised report date of February 4, 2021. Inspector Randy Keathley certified that all safely accessible regulated materials have been abated or removed, and the site has passed visual inspection and is cleared for demolition. Abated quantities included 925 linear feet of exterior caulk, 8,725 square feet of plaster, 100 square feet of additional plaster, 2 square feet of stack cement, 5 square feet of heat shield, 2 natural gas meters, 1 security system, 1 refrigerator/freezer/blast chiller unit, and multiple paint cans and smoke detectors.
Materials remaining on site total 199 square feet of plaster and roofing material, which remain due to unsafe conditions and inaccessible areas where structural compromise poses collapse risk. The abatement contractor MWV Environmental Services, Inc., supervised by Juliette T. Brooks (Accreditation Number A59120), is responsible for removal and transport in accordance with applicable federal regulations. The document recommends that demolition activities treat all remaining debris as asbestos-containing waste material per 40 CFR 61.145(c)(iii) and 61.150, and comply with worker protection requirements under 29 CFR 1926.1101. Date-and-time-stamped photographs documenting material conditions are attached as supporting documentation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Environmental Testing & Consulting, Inc.
RFP #:
POST-ABATEMENT VERIFICATION STATEMENT
E-mail Address:
Phone #
Expiration Date:
State of Michigan ID #:
Company Name:
Inspector Name:
E-mail Address:
Phone #
Expiration Date:
State of Michigan ID #:
Randy.Keathley@2etc.com
734-955-6600
10.4.2024E
MWV Environmental Services, Inc
Katrenia B. Moncrief
01/15/2026
668 W Hollywood 01006701.
Randy Keathley Abatement Contractor:
Parcel ID #:Site Address:
A-41896
05/04/2026
(586) 203-7281
03/17/2026
A-50532
Environmental Testing & Consulting, Inc.
If yes, which areas are now inaccessible at the time of the post-abatement inspection?
Point of Contact:
EA 5, FS 3,12
Kat.mwvenv@yahoo.com
If a structure is in IMMINENT DANGER OF COLLAPSE, the Inspector must hold the inspection of the site and immediately inform the designated point(s)-of-contact for the assigned demolition contractor and the Owner as directed.
The Inspector must attach documentation (including, but not limited to, Alternate Control Methods and date- and time-stamped pictures) from the assigned abatement/demolition contractor that identifies any inaccessible materials.
Original Report Date:
Revised Report Date(s):
11/26/2024 Post-Abatement Inspection Date:
Are there inaccessible areas of the site that are different from those areas identified in the most current Report for the site? Yes revised 2/4/2021
Post-Abatement Verification Statement
668 W Hollywood, Detroit, MI 48203
Exterior Caulk - On Brick Siding &
Trim,Windows,Transitions,Seams, Rooflines
EA 1-4 925 LF
NEW SUSPECT OR PRESUMED ASBESTOS-CONTAINING MATERIALS5
See PO Letter
2 SF
FS 4-21
25 SF25 SFEA 5Roofing Material - Flashing
FS 12
Plaster - Skim & Base Coat
Ceilings on Brick/Block- Fireplace
Chimney
8864 SF
Material Description Material Location
5 SF
Heat Shield - Millboard under 6x6, neat chimney
Stack Cement - Chimney at
Mechanical Exhausts-Gray
FS 3
REGULATED ASBESTOS-CONTAINING MATERIALS1
Remaining
Quantity3
TABLE I
Report
Quantity2
FS 5
TABLE II
Abated
Quantity7Material Description Material Location
Plaster - Skim & Base Coat
Ceilings on Lath
135 SF
Estimated
Quantity6
Inaccessible/Unsafe to
Abate Quantity4 Notes
Inaccessible/Unsafe to
Abate Quantity4 Notes
35 SF
139 SF
See PO Letter
See PO Letter revised 2/4/2021
Post-Abatement Verification Statement
Inspector Signature Date
1/15/2026
NEW HAZARDOUS/REGULATED MATERIALS & UNIVERSAL WASTES5
Abated
Quantity7
Inaccessible/Unsafe to
Abate Quantity4 Notes
NATURAL GAS METER
TABLE IV
HAZARDOUS/REGULATED MATERIALS & UNIVERSAL WASTES1
FS 10
FS 18
FS 21
PAINTS - 1 pint
EA 5
FS 1
FRIDGE, FREEZER, BLAST
CHILLERS
Paint - 1- gal can
SECURITY SYSTEMS
Material Description Material Location Notes Inaccessible/Unsafe to
Abate Quantity4
Report
Quantity2
I, Randy Keathley, hereby certify that all information contained herein is complete and accurate to the best of my knowledge.
In my professional opinion, all safely accessible regulated asbestos-containing materials or other hazardous/regulated materials HAVE been abated or removed from this site. This site has PASSED the visual inspection and IS cleared for demolition.
Material Description Material Location Estimated
Quantity6
SMOKE DETECTORS
EA 1
TABLE III
Remaining
Quantity3 revised 2/4/2021
Post-Abatement Verification Statement
KEY / GUIDANCE ON COMPLETING THE POST-ABATEMENT VERIFICATION STATEMENT
3. The estimated quantities of accessible regulated asbestos–containing or other hazardous/regulated materials that were identified in the report for this site but have NOT been abated or removed prior to this inspection. These materials are grounds for failing the site. The Inspector should attach a date-and time-stamped picture of the remaining materials.
4. The estimated quantities of regulated asbestos-containing or other hazardous/regulated materials on this site that cannot be abated due to safety/accessibility concerns. The material(s)/quantities included under this column were identified in the report for this site or during the post-abatement inspection but cannot be abated/removed prior to demolition due to safety/accessibility concerns. Inaccessible areas or materials that are unsafe to abate/remove/inspect are NOT grounds for failing the site.
5. These tables lists ALL suspect or presumed asbestos-containing materials or other hazardous/regulated materials that were identified during the post-abatement inspection of this site.
7. The estimated quantities of accessible suspect or presumed asbestos-containing materials or other hazardous/regulated materials that were identified during the post-abatement inspection and were immediately abated/removed by the abatement contractor.
6. The estimated quantities of suspect or presumed asbestos-containing or other hazardous/regulated materials that were identified on site during the post-abatement inspection. These materials were NOT identified or listed in the most current report for this site. Suspect or presumed materials must be sampled and analyzed or abated in accordance with the applicable Scope of Services. If the abatement contractor elects to sample and analyze the suspect material, then the assigned due diligence contractor must prepare and submit a revised report as directed by the Owner. If the results determine that the material is NOT a regulated asbestos-containing material, then the post-abatement inspector may pass the site. If the results determine that the material is a regulated asbestos-containing material, then the post-abatement inspector must fail the site and await a subsequent request for a post-abatement inspection.
2. The estimated quantities of regulated asbestos-containing or other hazardous/regulated materials that were listed in the most current report for this site.
1. These tables lists ALL regulated asbestos-containing materials or other hazardous/regulated materials that were identified in the most current report for this site.
revised 2/4/2021
Post-Abatement Verification Statement
668 W. Hollywood, Detroit, MI. 48203
Material Description Quantity
Removed/Abated
Exterior Caulk 925 LF
Stack Cement 2 SF
Heat Shield 5 SF
Plaster 8,725 SF
Plaster 100 SF
Natural Gas Meters 2
Security System 1
Paint 1
Fridge, Freezer, Blast Chiler 1
Smoke Detector 1
Paint 1
Material Description Material Location Quantity Remaining Notes/Description*
Plaster FS 12 139 SF Excluded
Plaster FS 3 35 SF Unsafe
Roofing Material EA 5 25 SF Unsafe
FS 3
Detroit, MI 48228
The following materials and quantities were abated/removed and transported from the site in accordance with all applicable laws, regulations, and rules:
TABLE 1 – MATERIALS REMOVED/ABATED
Material Location
EA 1-4
MWV Environmental Services, Inc.
18407 Weaver St.
Detroit, MI 48228
MWV Environmental Services, 18407 Weaver St.
FS 21
FS 18
FS 10
FS 5
FS 4-21
FS 12
EA 1
FS 1
EA 5
TABLE 2 – MATERIALS REMAINING
668 W. Hollywood, Detroit, MI. 48203
The following materials and quantities will remain on site due to compromised structural members that pose a risk of unplanned collapse or other unsafe condition:
Juliette T. Brooks A59120
Name Contractor/Supervisor Accreditation Number
1/9/2026
Signature Date
ATT [1] ATT [2]
ATT [2]
ATT [3]
Note:
668 W. Hollywood, Detroit, MI. 48203
*See attached date- and time-stamped photos that document the change in condition from the time of the Engineering
Survey.
☒ Furthermore, certain areas of the site were inaccessible for inspection at the time of the Engineering Survey. Therefore, we cannot verify the absence of asbestos-containing materials in those areas.
For the reasons identified above, we recommend that the demolition treat all debris as asbestos-containing waste material in accordance with 40 CFR 61.145(c)(iii) and 40 CFR 61.150, and we recommend that the demolition follow all applicable worker protection requirements. This includes but is not limited to the applicable regulations found in 29 CFR 1926.1101.
I certify that all information contained herein is true, complete, and accurate to the best of my knowledge and belief.