65DPS-S3744 - Cost Proposal.docx
DOCX document 14 KB Posted
- Attached to
- Rehabilitation of Fire Investigation Burn Cells
- Solicitation number
- 65DPS-S3744
- Issued by
- Churchill County, Nevada
About this file
This is a Cost Proposal form for RFP 65DPS-S3744 concerning the Rehabilitation of Fire Investigation Burn Cells, submitted to a state agency (indicated by the "65DPS" designation). The project involves demolition and reconstruction of fire investigation burn cells, with vendors required to submit a detailed cost breakdown. The proposal requests separate line items for the cost per demolition and project cost, as well as a contingency or reserve amount calculated as a percentage of the demolition and reconstruction project cost.
The payment structure is divided into two equal installments, with half of the contract value paid prior to the commencement of demolition work and the remaining half paid upon completion and inspection of the project. The total contract amount is not to exceed $322,768.53. Vendors must provide their company name and itemized costs within the specified format, with the contingency reserve serving as a buffer for unforeseen expenses during the rehabilitation project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment BB-1 Stand-alone Units.pdf | ||
| 65DPS-S3744 - Request-for-Proposals~1.docx | DOCX document | |
| 65DPS-S3744 - Insurance Schedule - RFP.docx | DOCX document | |
| Quote Instructions.pdf | ||
| Attachment CC SFMD Materials List.pdf | ||
| Attachment BB Trailer photos.pdf | ||
| 65DPS-S3744-Vendor-Information-Response.pdf | ||
| 65DPS-S3744-Reference-Questionnaire.docx | DOCX document | |
| Attachment DD-1 Damage Report.pdf | ||
| Standard-form-contract~4.docx | DOCX document | |
| Attachment DD Damage Report.pdf | ||
| Terms-and-conditions-for-services~5.pdf | ||
| Certification-regarding-lobbying~5.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COST PROPOSAL – RFP 65DPS-S3744
Rehabilitation of Fire Investigation Burn Cells
Vendor Name: _______________________________________________________
Cost per demolition and project cost $_________________
Contingency/reserve (per demolition and reconstruction project cost) $__________________
Half of the payment will be paid prior to the start of demolition and the remainder upon completion and inspection of the project.
Two payments per demolition and reconstruction of project:
TOTAL CONTRACT NOT TO EXCEED: $322,768.53