659-24-901 Salisbury Masonry Specs CD.docx

DOCX document 999 KB Posted

Attached to
Y1DZ--Repair Masonry / Structural Issues | 659-24-901
Solicitation number
36C24626B0034
Issued by

About this file

This is a specification document for masonry repair and structural remediation work at the W.G. (Bill) Hefner Veterans Affairs Medical Center in Salisbury, North Carolina. The project (659-24-901) involves comprehensive exterior masonry maintenance and repair across seven campus buildings (Buildings 5, 6, 7, 11, 13, 19, and 21), with work to be performed in phases according to building groupings. The scope includes brick repointing, masonry accessory replacements, lintel repairs, expansion joint replacement, brick cleaning, sealant replacement, regrouting, precast and slate repair, repainting, removal and replacement of wall-mounted items, and building cleaning. All work occurs outside occupied buildings, requiring adherence to safety and infection control measures during construction.

The contract is structured with a base bid item covering 270 days of work, followed by four deduct alternates that progressively reduce scope through modified repointing requirements and building exclusions, with timelines ranging from 255 to 220 days. Buildings 7, 11, 19, and 21 receive full repointing under the base bid, while Buildings 5, 6, and 13 receive limited repointing and other specified items. All buildings include cleaning, painting, and refurbishment as indicated in the drawings and specifications. The solicitation number is 36C24626B0034, and the work is being procured by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 6.

View the file

Other files

File Type Posted
36C24626B0034 0002.docx DOCX document
RFI masonry project - RESPONSE 08102026.docx DOCX document
36C24626B0034 0001.docx DOCX document
RFI masonry project - RESPONSE 08062026.docx DOCX document
36C24626B0034_2.docx DOCX document
659-24-901 Drawings PDF Combined CD.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Specifications For: Salisbury VAMC Repair Masonry Structural Issues Combined Specifications (Divisions 00-48) At: WG “Bill” Hefner VA Medical Center Salisbury VAMC

Project No.: 659-24-901

Issue Final Construction Documents November 03, 2025

Property of US Department of Veterans Affairs

DEPARTMENT OF VETERANS AFFAIRS

Repair Masonry Structural Issues

TABLE OF CONTENTS

Section 00 01 10

SECTION NO
DIVISION AND SECTION TITLES
DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 13
Seals Page
00 01 15
List of Drawing Sheets
05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00
General Requirements
11-21
01 32 16.15
Project Schedules Small Projects – Design/Bid/Build
01-24
01 33 23
Shop Drawings, Product Data, and Samples
11-23
01 35 26
Safety Requirements
05-24
01 42 19
Reference Standards
11-20
01 45 00
Quality Control
02-21
01 45 29
Testing Laboratory Services
11-18
01 57 19
Temporary Environmental Controls
01-21
01 74 19
Construction Waste Management
04-22

DIVISION 02 – EXISTING CONDITIONS

02 41 00
Demolition
08-17

DIVISION 03 – CONCRETE - NOT USED

DIVISION 04 – MASONRY

04 01 00
Maintenance of Masonry
01-21
04 05 13
Masonry Mortaring
10-17
04 20 00
Unit Masonry
08-17
04 72 00
Cast Stone Masonry
01-21

DIVISION 05 – METALS

05 50 00
Metal Fabrications
08-18

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES – NOT USED

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13
Thermal Insulation
01-21
07 24 00
Exterior Insulation and Finish Systems
01-21
07 60 00
Flashing and Sheet Metal
01-21
07 92 00
Joint Sealants
04-22
07 95 13
Expansion Joint Cover Assemblies
01-21

DIVISION 08 – OPENINGS

06-01-24

00 01 10 - 1

SECTION NO
DIVISION AND SECTION TITLES
DATE
08 51 13
Aluminum Windows
01-21

DIVISION 09 – FINISHES

09 91 00
Painting
01-21

DIVISION 10 – SPECIALTIES - NOT USED

DIVISION 11 – EQUIPMENT - NOT USED

DIVISION 12 – FURNISHINGS - NOT USED

DIVISION 13 - SPECIAL CONSTRUCTION - NOT USED

DIVISION 14 – CONVEYING EQUIPEMENT - NOT USED

DIVISION 21 - FIRE SUPPRESSION - NOT USED

DIVISION 22 – PLUMBING - NOT USED

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC) - NOT USED

DIVISION 25 – INTEGRATED AUTOMATION - NOT USED

DIVISION 26 – ELECTRICAL - NOT USED

DIVISION 27 – COMMUNICATIONS - NOT USED

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY - NOT USED

DIVISION 31 – EARTHWORK - NOT USED

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 90 00
Planting
08-16

DIVISION 33 – UTILITIES - NOT USED

DIVISION 34 – TRANSPORTATION - NOT USED

DIVISION 48 – Electrical Power Generation - NOT USED

Section 00 01 13

PROJECT SEALS PAGE

PROJECT:

Repair Masonry Structural Issues W.G. Hefner VA Medical Center Salisbury, NC

RELEASE DATE:

Final Construction Documents: November 03, 2025

OWNER:

US Department of Veterans Affairs

ARCHITECT:

Jonathan Martin Carr, AIA, NCARB, CDT Harrell Design Group, PC 10720 Sikes Place Suite 100 Charlotte, NC 28277 704-814-1320

Digital Signature not valid without Certificate below seal.

Digital!�signod by JonathanM.Carr□

N:c�us, E�jcarr@har,relldg.com, Jonathan M. Carr 0-"t-JarrellDesign Grqi.ip, PC", CN..JonathanM.Carr Date:2025.10.30 14:38:47-04'00'

- - - E N D - - -

SECTION 00 01 15 LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

GI001COVER SHEET
GI002ARCHITECTURAL ABBREVIATIONS

ARCHITECTURAL

AS101 OVERALL ARCHITECTURAL SITE PLAN

AE102
SITE PLAN -
BUILDING
5
(DEDUCTIVE
BID

ALTERNATE)

AE103
SITE PLAN -
BUILDING
6
(DEDUCTIVE
BID

ALTERNATE)

AE104
SITE PLAN -
BUILDING
7
(DEDUCTIVE
BID

ALTERNATE)

AE105
SITE PLAN -
BUILDING
11
AE106
SITE PLAN -
BUILDING
13
(DEDUCTIVE
BID

ALTERNATE)

AE107
SITE PLAN -
BUILDING
19
(DEDUCTIVE
BID

ALTERNATE)

AE108
SITE PLAN -
BUILDING
21
AE203BUILDING 5 - ELEVATIONS (DEDUCTIVE BID ALTERNATE)
AE204BUILDING 5 - ELEVATIONS (DEDUCTIVE BID ALTERNATE)
AE204aBUILDING 5 - PHOTOS (DEDUCTIVE BID ALTERNATE)
AE205BUILDING 6 - ELEVATIONS (DEDUCTIVE BID ALTERNATE)
AE206BUILDING 6 - ELEVATIONS (DEDUCTIVE BID ALTERNATE)
AE207BUILDING 6 - ELEVATIONS (DEDUCTIVE BID ALTERNATE)

05-01-20

00 01 15 - 1

AE208BUILDING 6 - ELEVATIONS (DEDUCTIVE BID ALTERNATE)
AE209BUILDING 6 - ELEVATIONS (DEDUCTIVE BID ALTERNATE)
AE209aBUILDING 6 - PHOTOS (DEDUCTIVE BID ALTERNATE)
AE209bBUILDING 6 - PHOTOS (DEDUCTIVE BID ALTERNATE)
AE210BUILDING 7 - ELEVATIONS (DEDUCTIVE BID ALTERNATE)
AE210aBUILDING 7 – ELEVATIONS AND PHOTOS (DEDUCTIVE BID ALTERNATE)
AE211
BUILDING
11
- ELEVATIONS
AE212
BUILDING
11
- ELEVATIONS
AE213
BUILDING
11
- ELEVATIONS
AE213a
BUILDING
11
PHOTOS
AE213b
BUILDING
11
PHOTOS
AE214
BUILDING
13
- ELEVATIONS (DEDUCTIVE
BID

ALTERNATE)

AE215
BUILDING 13 - ELEVATIONS (DEDUCTIVE
BID

ALTERNATE)

AE215a
BUILDING 13 - PHOTOS (DEDUCTIVE BID
ALTERNATE)
AE216
BUILDING 19 - ELEVATIONS (DEDUCTIVE
BID

ALTERNATE)

AE216a
BUILDING 19 - PHOTOS (DEDUCTIVE BID
ALTERNATE)
AE217
BUILDING 21 - ELEVATIONS
AE218
BUILDING 21 - ELEVATIONS
AE219
BUILDING 21 - ELEVATIONS
AE220
BUILDING 21 - ELEVATIONS
AE221
BUILDING 21 - ELEVATIONS
AE222
BUILDING 21 - ELEVATIONS
AE222a
BUILDING 21 - PHOTOS
AE222b
BUILDING 21 - PHOTOS
AE501
DETAILS
AE502
PRECAST REPOINTING DETAILS
AE503
PRECAST REPOINTING DETAILS
AE504
PRECAST REPOINTING DETAILS
AE505
DETAILS

SECTION 01 00 00 GENERAL REQUIREMENTS

GENERAL

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

Contractor shall completely prepare site for building operations, including removal of existing masonry and mortar, and furnish labor and materials to perform work for VA project 659-24-901, Replace Masonry Structural Issues, which includes masonry maintenance and repair to the exterior walls for seven (7) campus buildings (Buildings 5, 6, 7, 11, 13, 19, and 21), with phased construction according to building groupings. Work includes brick repointing, masonry accessory replacements, lintel repairs, repainting, removal and replacement of existing wall-mounted items, expansion joint replacement, brick cleaning, sealant replacement, regrouting, precast and slate repair, and certain other work activities. All work occurs outside of occupied buildings. Therefore, safety and infection control measures are required during construction. The project includes deduct alternates, as required by drawings and specifications.

A. Visits to the site by Bidders may be made only by appointment with the Medical Center Engineering Officer. The General Contracting firm that is awarded the project must provide proof to VA that their company representatives performed site visit(s) during bidding.

B. Offices of Harrell Design Group, PC, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

C. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.

11-01-21

01 00 00 - 10

D. All employees of the General Contractor and Subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

1.3 STATEMENT OF BID ITEM(S)

A. BID ITEM I, GENERAL CONSTRUCTION, BASE BID: the Contractor shall provide all necessary tools, labor, materials, equipment, permits, license and supervision for masonry joint repair on the exterior of Buildings 5, 6, 7, 11, 13, 19, and 21. Buildings 7, 11, 19 and 21 receive full repointing. Buildings 5, 6 and 13 receive limited repointing. and certain other items. All buildings receive building cleaning (including non-masonry wall areas), painting, and certain other refurbishments, as indicated by drawings and specifications.

B. BID ITEM 2, ALTERNATE NO.1: BASE BID, except delete full repointing on Building 19 and, instead, provide limited repointing on Building 19.

C. BID ITEM 3, ALTERNATE NO.2: BASE BID AND ACCEPTANCE OF ALTERNATE 1,

except delete full repointing on Building 7 and, instead, perform limited repointing on Building 7.

D. BID ITEM 4, ALTERNATE NO.3: BASE BID AND ACCEPTANCE OF ALTERNATE 1 AND

ALTERNATE 2, except delete all work associated with Building 13.

E. BID ITEM 5, ALTERNATE NO.4: BASE BID AND ACCEPTANCE OF ALTERNATE 1,

ALTERNATE 2 and ALTERNATE 3, except delete all work associated with Building 5.

F. BID ITEM 6, ALTERNATE NO.5: BASE BID AND ACCEPTANCE OF ALTERNATE 1,

ALTERNATE 2, ALTERNATE 3, AND ALTERNATE 4, except delete limited repointing on Building 6 and, instead, provide reparative-only masonry work on Building 6.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.

4. VA reserves the right to close or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting Officer’s representative (COR) for the purpose of security inspections of every area of project including toolboxes and parked machines and take any emergency action.

D. Document Control:

1. Before starting any work, the General Contractor/Subcontractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”. Secure such information in separate containers and limit access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using Engineering Document Management Software (EDMS).

Security, access and maintenance of all project drawings, both scanned and electronic, shall be performed and tracked through the EDMS system.

“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. An unlimited number of permits shall be issued for General Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical Center Facility Manager. Only Contractor’s key personnel may park at building sites. Contractor must propose the key personnel to VA, for VA prior approval. All other Contractor and Subcontractor vehicles must be parked in designated campus parking areas away from the building sites.

1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. Working space and space available for storing materials shall be as shown on the drawings and as modified by COR prior to construction.

E. Workers are subject to rules of Medical Center applicable to their conduct.

F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.

G. Execute work to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction areas outside buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two workdays. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

H. Phasing:

1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include but not be limited to the items above plus an hourly work schedule that suits VA needs. For areas impacting patient care, Contractor will work outside normal hospital business hours, unless coordinated with VA-COR.

Normal Business Hours are 7:00 AM to 5:00 PM.

2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. VA will review and modify the Contractor’s phasing plan. VA reserves the option to choose which phase starts first. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange phasing to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, COR and Contractor, as follows:

Phase I: Perform concurrent work on four (4) west campus buildings, including:

a. Building 21. Building 21’s work straddles Phases I and II.

b. Building 11.

c. Building 13.

d. Building 19.

Phase II: Perform concurrent work on three (3) east campus buildings and one

(1) west campus building, including:

a. Building 21. Building 21’s work straddles Phases I and II.

b. Building 6.

c. Building 7.

d. Building 5.

I. All buildings will be occupied during performance of work

1. The Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. The Contractor shall permit access to Department of Veterans Affairs personnel and patients through construction areas which serve as routes of access to such affected areas and equipment. These routes, whether access or egress, shall be isolated from the construction area by temporary scaffolding and have walking surfaces, lighting etc. to facilitate safe patient and staff access. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction period.

J. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction and staging areas indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). For staging areas, bottom of fences shall extend to 25mm (one inch) above grade. For construction areas, bottom of fences shall have matching tube stands with reinforced welds, rust resistance, and flared bases. Remove the fences when directed by COR.

K. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall plan for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.

L. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to ensure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR.

2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent services to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

M. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

N. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

O. Coordination of Construction: The building activities shall take precedence over construction activities. The Contractor must cooperate and coordinate with the COR, in arranging construction schedule to cause the least possible interference with building activities.

1. The Contractor is required to discontinue work sufficiently in advance of Easter Sunday, Mother's Day, Father's Day, Memorial Day, Veteran's Day and/or Federal holidays, to permit him to clean up all areas of operation adjacent to existing buildings before these dates.

2. Cleaning up shall include the removal of all equipment, tools, materials and debris and leaving the areas in a clean, neat condition.

3. The Contractor is required to mow the grass areas inside the Contractor’s fenced areas and trailer location(s) on a periodic basis. Grass cannot be allowed to grow longer than 4 inches. Mow the grass to a height of 2 to 2-1/2 inches high.

4. Upon completion of the phase, remove all temporary fencing, materials, debris, trailers, tools, and clean area to its pre-construction state. Then install seeding in accordance with section 32 90 00, PLANTING. All phase work must be completed, including cleanup and seeding, prior to starting the next phase.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of building exteriors and interiors in which work occurs and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:

1. Existing condition and types of masonry walls, windows, lintels, and other surfaces not required to be altered throughout affected areas of buildings.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical conduit, mechanical equipment, landscaping, and trees required to be protected during construction.

3. Note any discrepancies between drawings and existing conditions at site.

4. Designate areas for working space, materials storage and routes of access to buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled, and equipment moved and/or relocated.

3. Protection of interior of existing structures always, from damage, dust and weather inclemency.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accrued from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to reinstallation and reuse. Store such items as directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS (FAR 52.236-9) A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed, and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and

"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge Elimination System (NPDES) permit is required for this project. The Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:

1. Designating areas for equipment maintenance and repair.

2. Providing waste receptacles at convenient locations and provide regular collection of wastes.

3. Locating equipment wash down areas on site and provide appropriate control of wash-water.

4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and

5. Providing adequately maintained sanitary facilities.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver complete and undamaged work. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed because of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).

1.11 PHYSICAL DATA – SOIL CONDITIONS - NOT USED

1.12 PROFESSIONAL SURVEYING SERVICES

A. If the Contractor requires a survey for scaffolding or other reasons, the Contractor shall provide a registered professional land surveyor or registered civil engineer. These services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections. The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.

1.13 LAYOUT OF WORK – NOT USED

1.14 AS-BUILT DRAWINGS

A. The contractor shall maintain two full-size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.15 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.

2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

4. A list for each warranted equipment item, feature of construction or system indicating:

a. Name of item.

b. Model and serial numbers.

c. Location where installed.

d. Name and phone numbers of manufacturers and suppliers.

e. Name and phone numbers of manufacturers or suppliers.

f. Names, addresses and phone numbers of sources of spare parts.

g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

h. Starting point and duration of warranty period.

i. Summary of maintenance procedures required to continue the warranty in force.

j. Cross-reference to specific pertinent Operation and Maintenance manuals.

k. Organizations, names and phone numbers of people to call for warranty service.

l. Typical response time and repair time expected for various warranted equipment.

5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.

6. Procedure and status of tagging of all equipment covered by extended warranties.

7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

B. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period.

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.

3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.

C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty will be established/reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.

D. Contractor’s Response to Construction Warranty Service Requirements:

E. Following oral or written notification by the Contracting Officer, the Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.

1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.

2. Second Priority Code 2. Perform onsite inspection to evaluate situations, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.

3. Third Priority Code 3. All other work to be initiated within 3 workdays and work continuously to completion or relief.

4. The “Construction Warranty Service Priority List” is as follows:

a) Code 1-Life Safety Systems

· Fire suppression systems.

· Fire alarm system(s).

b) Code 1-Air Conditioning Systems

· Air conditioning leak in part of the building, if causing damage.

· Air conditioning system not cooling properly.

c) Code 1 Doors

· Overhead doors not operational, causing a security, fire or safety problem.

2) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.

d) Code 3-Doors

· Overhead doors not operational.

· Interior/exterior personnel doors or hardware not functioning properly.

e) Code 1-Electrical

· Power failure (entire area or any building operational after 1600 hours).

· Security lights.

· Smoke detectors.

f) Code 2-Electrical

· Power failure (no power to a room or part of building). Receptacle and lights not operational (in a room or part of building).

g) Code 3-Electrical

· Exterior lights not operational.

h) Code 1-Gas

· Leaks and pipeline breaks.

i) Code 1-Heat

· Power failure affecting heat.

j) Code 1-Plumbing

· Hot water heater failure.

2) Leaking water supply pipes

k) Code 2-Plumbing

· Flush valves not operating properly

· Fixture drain, supply line or any water pipe leaking.

· Toilet leaking at base.

l) Code 3- Plumbing

· Leaky faucets.

m) Code 3-Interior

· Floors damaged.

· Paint chipping or peeling.

· Casework damaged.

n) Code 1-Roof Leaks

· Damage to property is occurring.

o) Code 2-Water (Exterior)

· No water to facility.

p) Code 2-Water (Hot)

· No hot water in portion of building listed.

q) Code 3

· All work not listed above.

Warranty Tags: At the time of installation, tag each warranted item with a durable oil and water-resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.

Warranty Tags

Type of product/material

Model number

Serial number

Contract number

Warranty period from/to

Inspector’s signature

Construction Contractor

Address

Telephone number

Warranty Contact

Address

Telephone number

Warranty response time priority code

1.16 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

1.17 COR’S FIELD OFFICE – NOT USED

1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT – NOT USED

1.19 TEMPORARY USE OF EXISTING ELEVATORS

A. Contractors are prohibited to use existing elevators. Outside type hoists shall be used by Contractor for transporting materials and equipment.

1.20 TEMPORARY USE OF NEW ELEVATORS – NOT USED

1.21 TEMPORARY TOILETS

A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodation with suitable sewer and water connections; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.

1.22 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.

B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.

C. Contractor shall install meters at Contractor's expense and furnish the Medical Center a monthly record of the Contractor's usage of electricity as hereinafter specified.

D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials like mortar.

E. Electricity (for Construction and Testing): Furnish all temporary electric services.

1. Obtain electricity by connecting to the Medical Center distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.

F. Water (for Construction and Testing): Furnish temporary water service.

1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the Contractor.

2. Maintain connections, pipes, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other waste will be cause for revocation (at COR discretion) of use of water from Medical Center's system.

1.23 NEW TELEPHONE EQUIPMENT – NOT USED

1.24 TESTS

A. As per specification section 01 45 29 Testing Laboratory Services, testing services are retained by the General Contractor.

B. The Contractor shall provide a testing plan. The plan will provide a schedule and a written sequence of what will be tested, and how. This document will be submitted for approval prior to commencing work. The Contractor shall document the results of the approved plan and submit for approval with the as-built documentation.

1.25 INSTRUCTIONS – NOT USED

1.26 GOVERNMENT-FURNISHED PROPERTY – NOT USED

1.27 RELOCATED ITEMS – NOT USED

1.28 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT – NOT USED

1.29 CONSTRUCTION SIGN

A. Provide a Construction Sign as directed by the COR. All wood members shall be of framing lumber. Cover sign frame with 0.7 mm (24 gage) galvanized sheet steel nailed securely around edges and on all bearings. Provide three 100 by 100 mm (4 inch by 4 inch) posts (or equivalent round posts) set 1200 mm (four feet) into ground. Set bottom of sign level at 900 mm (three feet) above ground and secure to posts with through bolts. Make posts full height of sign. Brace posts with 50 x 100 mm (two by four inch) material as directed.

B. Paint all surfaces of sign and posts with two coats of white gloss paint. Border and letters shall be of black gloss paint, except project title which shall be blue gloss paint.

C. Maintain sign and remove it when directed by the COR.

D. Detail Drawing of construction sign showing required legend and other characteristics of sign is made a part of this specification and shown on the drawings.

1.30 SAFETY SIGN

A. Provide a Safety Sign as directed by COR. Face of sign shall be 19 mm (3/4 inch) thick exterior grade plywood. Provide two 100 mm by 100 mm (four by four inch) posts extending full height of sign and 900 mm (three feet) into ground. Set bottom of sign level at 1200 mm (four feet) above ground.

B. Paint all surfaces of Safety Sign and posts with one prime coat and two coats of white gloss paint. Letters and designs shall be painted with gloss paint of colors noted.

C. Maintain sign and remove it when directed by COR.

D. Drawing details in VA Signage Design Manual, Section 11 Specialty Signs (found on VA TIL) show required legend and other characteristics of sign is made a part of this specification and shown on the drawings.

E. Post the number of accident-free days daily.

1.31 PHOTOGRAPHIC DOCUMENTATION

A. During the construction period through completion, provide photographic documentation of construction progress and selected milestones including electronic indexing, navigation, storage and remote access to the documentation, as per these specifications. The commercial photographer or the subcontractor used for this work shall meet the following qualifications:

1. Demonstrable minimum experience of three (3) years in operation providing documentation and advanced indexing/navigation systems including a representative portfolio of construction projects of similar type, size, duration and complexity as the Project.

2. Demonstrable ability to service projects throughout North America, which shall be demonstrated by a representative portfolio of active projects of similar type, size, duration and complexity as the Project.

B. Photographic documentation elements:

1. Each digital image shall be taken with a professional grade camera with minimum size of 6 megapixels (MP) capable of producing 200x250mm (8 x 10 inch) prints with a minimum of 2272 x 1704 pixels and 400 x 500 mm (16 x 20 inch) prints with a minimum 2592 x 1944 pixels.

2. Indexing and navigation systems shall utilize actual AUTOCAD construction drawings, making such drawings interactive on an on-line interface. For all documentation referenced herein, indexing and navigation must be organized by both time (date-stamped) and location throughout the project.

3. Documentation shall…