This document is an amendment to a solicitation for the replacement of the galley roof on Building 446 at Naval Submarine Base New London in Groton, CT. The amendment answers several Requests for Information (RFIs) submitted by offerors, including the location of the laydown area, the need to reinstall existing roof pads, the availability of water for testing, and the potential for additional roof replacement beyond the initial 300 square feet. The amendment also extends the proposal due date to June 27, 2024, at 12:00 PM EST. The overall requirement is limited to the 6 contractors under the Multiple Award Construction Contract (MACC) ML-C00073, and the scope includes the replacement of 300 square feet of roofing, cleaning and re-adhering the existing EPDM roof, conducting thermal scans to identify any wet areas, and installing a new fluid-applied membrane over the existing surfaces.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0002.pdf | ||
| (M) Guide to Taxes.pdf | ||
| (N) Sales Tax Exemption Form 2016-R-0149.pdf | ||
| (C) Drawings.pdf | ||
| (G) General Requirements.pdf | ||
| (K) ECMS.pdf | ||
| (D) NEPA.pdf | ||
| (F) Price Proposal Form Updated.doc | DOC document | |
| (A) MACC RFP.docx | DOCX document | |
| (J) RFI Form.pdf | ||
| (O) CERT-141.pdf | ||
| (I) Map to B135.pdf | ||
| (E) CT Wage Determination.pdf | ||
| (H) Base Map.pdf | ||
| (L) FAR 52.204-24.pdf | ||
| (B) Specifications.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
N40085
Shawn A. Drake
The purpose of this amendment is to answer RFIs and extend proposal due date.
Proposal due date extended to 27 June 2024, 12:00 PM EST
See continuation page.
NAVFACSYSCOM MID-ATLANTIC
PWD NEW LONDON
BOX 400 BLDG 135
NAVAL SUBMARINE BASE NEW LONDON
GROTON, CT 06349-5026
See Item 6
ACQR6055646
ACQR#6055646
1 2
06/21/2024
06/20/2024
6/21/2024
ACQR#6055646
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
RFI001 QUESTION #1: Where is the lay down location for materials and equipment at B446?
ANSWER: Location for laydown area will be in the parking area behind the building.
RFI001 QUESTION #2: There are existing roof grip/pads that are to be removed from the existing roof.
Do these pads need to be reinstalled, or be replaced after the new roofing material is installed?
ANSWER: The roof pads will NOT be reinstalled.
RFI001 Question #3: Do we need to provide our own water for the water/leak test?
ANSWER: The building only has a garden hose size fixture for water supply. If this is adequate for conducting the water/leak test, it may be used. If not, water will need to be supplied.
RFI002 Question #1: During the site visit, it became evident that more than 300 square feet of roofing may need to be replaced. Would the government consider adding a bid option to the Price Proposal Form to quantify roof replacement price per SF that may be required above and beyond the 300 square feet replaced in the base bid?
ANSWER: Will be provided in amendment 0002.