6-Pratts Dam Road Construction Schedule.pdf

PDF 102 KB Posted

Attached to
Pratts Dam Road Bank Stabilization Project
Solicitation number
US.235576
Issued by
Chester County, Pennsylvania

About this file

This document is a pre-bid construction schedule for the Pratts Dam Road Creek Embankment Reconstruction Project in West Brandywine Township, Chester County, Pennsylvania. The project involves the replacement of existing retaining walls with soldier pile retaining walls, construction of a second soldier pile retaining wall, placement of rock protection along both walls, drainage improvements, full depth pavement resurfacing, safety feature upgrades, and associated work. The construction schedule spans from November 19, 2026, through May 30, 2029, comprising 41 distinct tasks with durations ranging from 1 to 222 days. Work is organized into two primary phases: Phase 1 focuses on Wall 1 reconstruction from August 2027 through July 2028, while Phase 2 addresses Wall 2 from July 2028 through December 2028. The schedule includes utility relocations with lead times for Verizon pole relocation (6 weeks) and PECO facilities relocation (16 weeks), mobilization activities, erosion and sediment control measures, winter shutdown from January through March 2029, and final construction inspection and closeout activities. All work is planned on a 5-day work week basis with 8-hour days, excluding U.S. holidays.

The schedule reflects a complex, multi-phase project requiring coordination of significant infrastructure work including caisson drilling, steel post installation, concrete lagging panel installation, temporary shoring, pavement excavation and milling, and asphalt binder and wearing surface installation. The project incorporates environmental controls throughout, with erosion and sediment control measures and pumped water filter bags required during both wall construction phases. Notable milestone tasks include detour notification and installation at project commencement, grading and topsoil placement following each wall phase, and final pavement markings and guide rail installation near project completion. The schedule demonstrates careful sequencing to manage constructability constraints, site access, and environmental compliance across the 30-month project duration.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pratts Dam Road Creek Embankment Reconstruction Project West Brandywine Township, Chester County

Pre-Bid Construction Schedule

10/5/2026 Tiffany McClure

Drawn by: Planner - Chart Properties Dwg No. 00001 Revision No. A Notes: Comment - Chart Properties

Project Ref. \\extfs\Projects\10190_PA_WestBrandyTwp_Pratts\200_Disciplines\224_Roadway\Construction_Schedule\Pratts Dam Construction Schedule.pp Planned by Asta Powerproject

Line Unique Task

ID

Name Duration Start Finish Total float Calendar

2027 20282026 2029

December January February March April May June July August September October November December January February March April May June July August September October November December January February March April MayNov

23 30 7 14 21 28 4 11 18 25 1 8 15 22 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 5 12 19 26 2 9 16 23 30 7 14 21 28

520 521 522 523 524 525 526 527 528 529 530 531 532 533 534 535 536 537 538 539 540 541 542 543 544 545 546 547 548 549 550 551 552 553 554 555 556 557 558 559 560 561 562 563 564 565 566 567 568 569 570 571 572 573 574 575 576 577 578 579 580 581 582 583 584 585 586 587 588 589 590 591 592 593 594 595 596 597 598 599 600 601 602 603 604 605 606 607 608 609 610 611 612 613 614 615 616 617 618 619 620 621 622 623 624 625 626 627 628 629 630 631 632 633 634 635 636 637 638 639 640 641 642 643 644 645 646 647 648 649 650 651 652

Let Date

NTP

Verizon Pole Relocation - 6 week lead time

PECO Facilities Relocation - 16 week lead time

Detour Notification and Install Detour

Mobilization

Delineate Limits Of Disturbance

Clear & Grub Trees And Vegetation as Needed

Install Rock Construction Entrance

Phase 1 - Wall 1

Install Erosion and Sediment Control Measures for Wall 1 up to Station 212+50.00. Install Pumped Water Filter Bags As Needed

Install Temporary Shoring to Stabilize the Existing Wall.

Drill Caissons

Install Steel Posts

Backfill the Front Face of Wall 1 with Rock, Class R-4, Grouted as Indicated on the Plans

Install Timber Lagging

Install Precast Concrete Lagging Panels. Remove and Install Proposed Drainage for Wall 1 as the Panels are Being Installed.

Install Inlet Filter Bags Immediately.

Remove the Existing Wall 1 and Backfill in Accordance with the Structure Plans.

Grade Areas Affected by the Construction of Wall 1 to the Proposed Contours. Place Topsoil, Erosion Control Blanket, and Seed as Required

Excavate Existing Pavement up to Station 212+50.00. Install Up to Proposed Base Course to the Proposed Elevations and Cross Slopes. Install Temporary Barrier Immediately.

Phase 2 - Wall 2

Install Erosion and Sediment Control Measures for Wall 2. Install Pumped Water Filter Bags As Needed

Install Temporary Shoring to Stabilize the Existing Wall

Dril Caissons

Install Steel Posts

Backfill the Front Face of Wall 2 with Rock, Class R-4, Grouted as Indicated on the Plans

Install Timber Lagging

Install Precast Concrete Lagging Panels

Remove Wall 2 and Backfill in Accordance with the Structure Plans

Grade Areas Affected by the Construction of Wall 2 to the Proposed Contours. Place Topsoil, Erosion Control Blanket, and Seed as Required

Winter Shutdown

Excavate Existing Pavement from Station 212+50.00 to the End of the Full Depth Section. Install Up to Proposed Base Course to the Proposed Elevations and Cross Slopes.

Mill Pratts Dam Road as Indicated on the Plans

Install Proposed Binder and Wearing Surface Throughout the Project Limits

Remove Temporary Barrier. Install Proposed Guide Rail Immediately.

Install Proposed Pavement Markings

Final Grade All Disturbed Areas. Place Topsoil, Erosion Control Blanket, and Seed as Required

Final Construction Inspection

Remove Erosion And Sediment Controls

Remove Detour

Project Complete

86d

1d

30d

80d

15d

3d

2d

7d

1d

222d

2d

150d

150d

150d

150d

150d

150d

150d

10d

25d

218d

2d

60d

60d

60d

60d

60d

60d

60d

5d

48d

10d

2d

5d

15d

2d

5d

1d

1d

1d

1d

11/19/2026

3/19/2027

3/22/2027

3/22/2027

7/12/2027

8/2/2027

8/5/2027

8/9/2027

8/18/2027

8/19/2027

8/19/2027

8/23/2027

9/6/2027

9/20/2027

10/4/2027

10/18/2027

11/1/2027

11/15/2027

6/12/2028

6/26/2028

7/31/2028

7/31/2028

8/2/2028

8/16/2028

8/30/2028

9/13/2028

9/27/2028

10/11/2028

10/25/2028

1/17/2029

1/24/2029

4/2/2029

4/16/2029

4/18/2029

4/25/2029

5/16/2029

5/18/2029

5/25/2029

5/28/2029

5/29/2029

5/30/2029

3/18/2027

3/19/2027

4/30/2027

7/9/2027

7/30/2027

8/4/2027

8/6/2027

8/17/2027

8/18/2027

6/23/2028

8/20/2027

3/17/2028

3/31/2028

4/14/2028

4/28/2028

5/12/2028

5/26/2028

6/9/2028

6/23/2028

7/28/2028

5/30/2029

8/1/2028

10/24/2028

11/7/2028

11/21/2028

12/5/2028

12/19/2028

1/2/2029

1/16/2029

1/23/2029

3/30/2029

4/13/2029

4/17/2029

4/24/2029

5/15/2029

5/17/2029

5/24/2029

5/25/2029

5/28/2029

5/29/2029

5/30/2029

65d

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work

Week, US

Holidays

8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work

Week, US

Holidays

8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

5 Day Work Week, US Holidays 8hrs/day

File details come from the government source that posted it. Updated .