This document contains an Infection Control Risk Assessment (ICRA) and details of a related federal contract opportunity. The ICRA outlines construction activity types and corresponding infection control risk groups for an EHRM Infrastructure Upgrades Phase 1 project at the Hines VA Medical Center in Hines, Illinois. Contractors must follow safety protocols corresponding to the project class determined by the construction activity type and risk group matrix. The federal contract opportunity is a competitive Service-Disabled Veteran-Owned Small Business set-aside solicitation for furnishing labor, materials and performing work as required by drawings and specifications for the EHRM Construction Project at the Hines VA Medical Center for between $200,000 to $500,000 in accordance with VAAR 836.204. Responses are due by the date specified in the solicitation.
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Infection Control Risk Assessment for Construction / Renovation Projects Project Name: EHRM Infrastructure Upgrades Phase 1 Project or Work-Order Number: 578-21-700
Project Manager or COR: John Robertson Extension: 22605
Building Number: 200 Floor(s)/Room(s): C2216, 4112, 564, 672, 772, 858, 953, 1072, 1161, 1272, 1372, 1472, 1572, 1600
Start date: 3/12/21 Projected completion date: 7/9/21
Construction Activity Infection Control Risk Group
☐ TYPE A: DUST LEVEL Low
Non-invasive activity, low noise, no vibration.
☒ GROUP 1: LOW
Office areas, FMS areas, all non-patient care areas.
☒ TYPE B: DUST LEVEL: Moderate to High
Small scale, short duration, low-moderate noise, low-moderate vibration.
☐ GROUP 2: MEDIUM
All other patient care areas including general medicine floors, ultrasound, Rehab, Occupational Therapy.
☐ TYPE C: DUST LEVEL Moderate to High
Requires more than one work shift (independent of working days) to complete, low-moderate noise, moderate–high vibration
☐ GROUP 3: MEDIUM/HIGH
ED, Radiology/MRI, admissions, food service areas, laboratories.
☐ TYPE D: DUST LEVEL High
Major demolition and construction activities. Requires consecutive work shifts, moderate-high noise, moderate-high vibration
☐ GROUP 4: HIGHEST
Operating rooms, SPS, ICU’s, Outpatient areas, oncology, anesthesia, post anesthetic recovery, all endoscope areas, Pharmacy, Renal Dialysis
Project Class Determination Matrix
Construction Activity Type
Risk Group
Type
“A”
Type
“B”
Type
“C”
Type
“D”
Group 1 I II II III
Group 2 I II III IV
Group 3 I III III IV
Group 4 III IV IV IV Contractors Actions by Project Class
All personnel will have Emergency Preparedness training/posting/ID card.
CLASS
I
1. Execute work to minimize air-borne dust dispersed into atmosphere from construction operations.
2. Immediately replace any ceiling tile displaced for visual inspection.
3. Contain construction waste before transport in tightly covered containers.
4. Clean work area upon completion of task including wiping surfaces with disinfectant.
5. Contact EMS for appropriate preparation for return to operation(s).
CLASS
II
In addition to above:
6. Post the signed ICRA at the entrance.
7. Isolate work area from patients/staff. Use appropriate temporary barriers and more permanent containment methods (i.e., seal holes in walls, tape gaps in doors, etc.)
8. Water mist work surfaces to control dust while cutting.
9. Block off and seal supply air vents. Place filter over return/exhaust vents.
10. Place dust mat or wipe feet at entrance/exit of work area.
11. Wet mop and/or vacuum w/HEPA filtered vacuum before leaving work areas.
CLASS
III
In addition to above:
12. Install barriers to create a negative pressure ante room and/or workroom.
13. Maintain negative air pressure in work area at all times until completion utilizing HEPA-equipped air filtration units.
14. Vacuum personnel with HEPA vacuum before leaving. Or, Don-Doff coveralls each time leaving work site. All wear shoe covers changed each time exiting the area.
15. Vacuum the entire work area with HEPA vacuums or wet mop with disinfectant at the completion of project.
16. Do not remove barriers until completed project is inspected by Safety, IC-Team, EMS, and Area Manager.
17. Carefully remove barriers to minimize spread of dirt and debris. Contact EMS for final clean.
CLASS
IV
In addition to above:
18. Provide a disinfectant wipe down of any tool carts or waste transports prior to leaving the containment area.
19. Do not remove barriers until terminal clean is performed inside work zone and barriers are included in the cleaning process.
20. Perform 2nd terminal cleaning after removal of barriers. Contact EMS for final clean.
Signatures Date
Contractor’s Signature:
(Projects Only)
Project Planner or
Maintenance Worker Signature:
Supervisor Signature:
Infection Control:
VHAHINDoyleL Typewritten Text 1/25/21
| 2021-01-25T09:47:11-0600 | |
| JOHN H. ROBERTSON 3478266 |
| 2021-01-25T10:00:36-0600 | |
| LAWRENCE P DOYLE 233105 |