Technical Questions Tracking Sheet - EHRM Design Hines Training and Admin Space Support Phase 1 - 7.1.2021.pdf
PDF 154 KB Posted
- Attached to
- EHRM Infrastructure Demo - Phase I - Hines, IL Federal contract opportunity
- Solicitation number
- 36C77621B0011
About this file
This document contains a technical questions tracking sheet for a solicitation to provide infrastructure demolition services at the Hines VA Medical Center in Hines, Illinois. The solicitation number is 36C77621B0011 and is set aside as a competitive opportunity for Service-Disabled Veteran-Owned Small Businesses. The contractor will demolish portions of the existing building as required by the drawings and specifications, with a contract value between $200,000 and $500,000. The tracking sheet includes questions and answers on infection control requirements, floor thicknesses, ceiling types, and the need for structural engineering support during demolition. A structural engineer must review any significant alterations to structural elements and inspect the work upon completion but does not need to be on site full time.
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL QUESTIONS
AND RESPONSE TRACKING SHEET
RFI CONTRACTOR QUESTIONS VA RESPONSES TO QUESTIONS
1 What is the Infection Control level for this work? 6/30/2021: Please See ICRA EHRM Infrastructure Phase 1 attachment. JR-VA COR
2 Please confirm concrete floor thickness at each floor. Will floor scanning be required at each floor penetration?
07/01/2021: Floors 1 through 15 are 5 1/2" thick. Penthouse floor is 5" thick. The penthouse slab is normally reinforced so scanning is not expected for the doweling. JR-VA COR
3 Please confirm ceiling type of each floor near construction area. 07/01/2021: Bidders should assume all ceilings in the area of work are gypsum board or plaster ceilings. There may be one or two acoustical tile ceilings but those are easier to demolish.
JR-VA COR
4 Engage a professional engineer to survey condition of building to determine whether removing any element might result in structural deficiency or unplanned collapse of any portion of structure or adjacent structures during selective demolition operations”. Does prime contractor owe a professional engineer to be on site full time while demolition is being completed? Please provide a scope of work for engineer requirements?
6/30/2021: A structural engineer shall be consulted when structural elements are proposed to be altered and provide written guidance. The engineer does not need to present during the modification but must inspect any significant work after completion. JR-VA COR