About this file

This is a General Bid Tabulation document for a PFAS Water Treatment Project in Pennsylvania involving the furnishing, construction, and installation of Ion Exchange resin filtration systems across ten well sites (Well Nos. 1, 3, 5, 7, 9, 14, 15, 37, 43/44, and 45). The project encompasses general construction of treatment buildings and building additions, chlorination equipment and instrumentation, demolition of existing facility infrastructure, site improvements including driveway upgrades, stormwater management, erosion and sedimentation controls, and site restoration. Additional work includes electrical construction with upgrades to electrical service supply, circuit breakers, transfer switches, transformers, motor starters, conduit and wiring, lighting, and instrumentation; mechanical construction (HVAC) with supply and installation of ceiling fans, louvers, heaters, dehumidifiers, and ductwork; and plumbing construction with supply and installation of water, sanitary sewer, storm sewer, floor drains, and associated piping. A pre-bid site meeting and site visits were scheduled for October 15, 2026, with bidders required to inspect sites prior to submission. All bids must include lump sum or unit prices for consideration by the Authority at their option.

The project is partially funded through the Military Installation Remediation and Infrastructure Authority (MIRIA) grant, requiring contract compliance with grant requirements, and partially funded through an agreement with the United States Navy. This funding structure necessitates adherence to both MIRIA and Navy agreement terms and conditions throughout project execution.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ARRO Consulting, Inc.

WARMINSTER MUNICIPAL AUTHORITY, BUCKS COUNTY

PFAS WATER TREATMENT PROJECT WELL NOS. 1, 3, 5, 7, 9, 14, 15, 37, 43/44, 45

Ref. #26-4A, -B, -C, -D

Unit Price Total Unit Price Total

Demolition including Existing Site Demolition as shown on the plans; and Existing Wellhouse Modifications, which include Abandonment of Existing Chlorine Facilities.

LS 1 $59,000.00 $59,000.00 $140,000.00 $140,000.00

Construction of Filter Treatment Building – 30’ wide, 42’ long, Split-Faced Block Building, including Concrete Footings and Floor Slab, Prefabricated Roof Truss System, Building Interior and Exterior Finishes, FRP Doors and Overhead Doors, Complete in every respect, as shown on the plans.

LS 1 $777,000.00 $777,000.00 $1,150,000.00 $1,150,000.00

Resin Filter Installation - Installation of two (2) Pre-Purchased IX Resin Filter Vessels and Skid Assembly, including Delivery, Handling, and Coordination, for a complete system installed as shown on the plans.

LS 1 $15,000.00 $15,000.00 $50,000.00 $50,000.00

Site Work – All Site Work including Grading, Paving, Site Fence, Unimproved (lawn) Area Restoration, Stormwater Management BMP(s), and Erosion and Sedimentation Control.

LS 1 $141,000.00 $141,000.00 $100,000.00 $100,000.00

Furnish and Install Process Equipment and Instrumentation including, Electromagnetic Flowmeters and System Pressure Transmitter, Chlorination Equipment including, but not limited to, Chlorination Booster Pumps, Cylinder Scales, Chlorine Leak Detection, complete.

LS 1 $87,500.00 $87,500.00 $100,000.00 $100,000.00

$1,079,500.00 $1,540,000.00

Demolition including Existing Site Demolition as shown on the plans; and Existing wellhouse modifications, to include Abandonment of Existing Chlorine Facilities.

LS 1 $58,000.00 $58,000.00 $140,000.00 $140,000.00

Construction of Filter Treatment Building Addition – 30’ wide, 42’ long, Split-Faced Block Building, including Concrete Footings and Floor Slab, Prefabricated Roof Truss System, Building Interior and Exterior Finishes, FRP Doors and Overhead Doors, Complete in every respect, as shown on the plans.

LS 1 $761,000.00 $761,000.00 $1,150,000.00 $1,150,000.00

Resin Filter Installation - Installation of two (2) Pre-Purchased IX Resin Filter Vessels and Skid Assembly, including Delivery, Handling, and Coordination, for a complete system installed as shown on the plans.

LS 1 $13,000.00 $13,000.00 $50,000.00 $50,000.00

Site Work – All Site Work including Grading, Paving, Site Fence, Unimproved (lawn) Area Restoration, Stormwater Management BMP(s), and Erosion and Sedimentation Control.

LS 1 $130,000.00 $130,000.00 $100,000.00 $100,000.00

Furnish and Install Process Equipment and Instrumentation including, Electromagnetic Flowmeters and System Pressure Transmitter, Chlorination Equipment including, but not limited to, Chlorination Booster Pumps, Cylinder Scales, Chlorine Leak Detection, complete.

LS 1 $102,500.00 $102,500.00 $100,000.00 $100,000.00

$1,064,500.00 $1,540,000.00

Demolition including Existing Site Demolition as shown on the plans; and Existing wellhouse modifications, to include Abandonment of Existing Chlorine Facilities.

LS 1 $56,000.00 $56,000.00 $140,000.00 $140,000.00

Construction of Filter Treatment Building Addition – 30’ wide, 42’ long, Split-Faced Block Building, including Concrete Footings and Floor Slab, Prefabricated Roof Truss System, Building Interior and Exterior Finishes, FRP Doors and Overhead Doors, Complete in every respect, as shown on the plans.

LS 1 $761,000.00 $761,000.00 $1,150,000.00 $1,150,000.00

Resin Filter Installation - Installation of two (2) Pre-Purchased IX Resin Filter Vessels and Skid Assembly, including Delivery, Handling, and Coordination, for a complete system installed as shown on the plans.

LS 1 $13,000.00 $13,000.00 $50,000.00 $50,000.00

Site Work – All Site Work including Grading, Paving, Site Fence, Unimproved (lawn) Area Restoration, Stormwater Management BMP(s), and Erosion and Sedimentation Control.

LS 1 $103,000.00 $103,000.00 $100,000.00 $100,000.00

Furnish and Install Process Equipment and Instrumentation including, Electromagnetic Flowmeters and System Pressure Transmitter, Chlorination Equipment including, but not limited to, Chlorination Booster Pumps, Cylinder Scales, Chlorine Leak Detection, complete.

LS 1 $87,500.00 $87,500.00 $100,000.00 $100,000.00

$1,020,500.00 $1,540,000.00

WELL NO. 3 TOTALS

WELL NO. 5 TOTALS

(1) (2)

BASE BID - WELL NO. 5

DescriptionNo.

BASE BID - WELL NO. 3

WELL NO. 1 TOTALS

BASE BID - WELL NO. 1

Quantity Unit Of

Measure Jurich, Inc. Pact Two, LLC

GENERAL CONSTRUCTION - CONTRACT 26-4A

BID TABULATION

10/27/2026 Page 1 of 4 JE/C0004956.00 General Bid Tabulation.xlsx

PFAS WATER TREATMENT PROJECT WELL NOS. 1, 3, 5, 7, 9, 14, 15, 37, 43/44, 45

Ref. #26-4A, -B, -C, -D

(1) (2)

DescriptionNo. Quantity Unit Of

Measure Jurich, Inc. Pact Two, LLC

GENERAL CONSTRUCTION - CONTRACT 26-4A

BID TABULATION

Demolition including Existing Site Demolition as shown on the plans; and Existing wellhouse modifications, to include Abandonment of Existing Chlorine Facilities.

LS 1 $62,000.00 $62,000.00 $140,000.00 $140,000.00

Construction of Filter Treatment Building Addition – 30’ wide, 42’ long, Split-Faced Block Building, including Concrete Footings and Floor Slab, Prefabricated Roof Truss System, Building Interior and Exterior Finishes, FRP Doors and Overhead Doors, Complete in every respect, as shown on the plans.

LS 1 $761,000.00 $761,000.00 $1,150,000.00 $1,150,000.00

Resin Filter Installation - Installation of two (2) Pre-Purchased IX Resin Filter Vessels and Skid Assembly, including Delivery, Handling, and Coordination, for a complete system installed as shown on the plans.

LS 1 $13,000.00 $13,000.00 $50,000.00 $50,000.00

Site Work – All Site Work including Grading, Paving, Site Fence, Unimproved (lawn) Area Restoration, Stormwater Management BMP(s), and Erosion and Sedimentation Control.

LS 1 $125,000.00 $125,000.00 $100,000.00 $100,000.00

Furnish and Install Process Equipment and Instrumentation including, Electromagnetic Flowmeters and System Pressure Transmitter, Chlorination Equipment including, but not limited to, Chlorination Booster Pumps, Cylinder Scales, Chlorine Leak Detection, complete.

LS 1 $87,500.00 $87,500.00 $100,000.00 $100,000.00

$1,048,500.00 $1,540,000.00

Demolition including Existing Site Demolition as shown on the plans; and Existing wellhouse modifications, to include Abandonment of Existing Chlorine Facilities.

LS 1 $58,000.00 $58,000.00 $140,000.00 $140,000.00

Construction of Filter Treatment Building Addition – 30’ wide, 42’ long, Split-Faced Block Building, including Concrete Footings and Floor Slab, Prefabricated Roof Truss System, Building Interior and Exterior Finishes, FRP Doors and Overhead Doors, Complete in every respect, as shown on the plans.

LS 1 $761,000.00 $761,000.00 $1,150,000.00 $1,150,000.00

Resin Filter Installation - Installation of two (2) Pre-Purchased IX Resin Filter Vessels and Skid Assembly, including Delivery, Handling, and Coordination, for a complete system installed as shown on the plans.

LS 1 $13,000.00 $13,000.00 $50,000.00 $50,000.00

Site Work – All Site Work including Grading, Paving, Site Fence, Unimproved (lawn) Area Restoration, Stormwater Management BMP(s), and Erosion and Sedimentation Control.

LS 1 $124,000.00 $124,000.00 $100,000.00 $100,000.00

Furnish and Install Process Equipment and Instrumentation including, Electromagnetic Flowmeters and System Pressure Transmitter, Chlorination Equipment including, but not limited to, Chlorination Booster Pumps, Cylinder Scales, Chlorine Leak Detection, complete.

LS 1 $87,500.00 $87,500.00 $100,000.00 $100,000.00

$1,043,500.00 $1,540,000.00

Demolition including Existing Site Demolition as shown on the plans; and Existing wellhouse modifications, to include Abandonment of Existing Chlorine Facilities.

LS 1 $58,000.00 $58,000.00 $140,000.00 $140,000.00

Construction of Filter Treatment Building Addition – 30’ wide, 42’ long, Split-Faced Block Building, including Concrete Footings and Floor Slab, Prefabricated Roof Truss System, Building Interior and Exterior Finishes, FRP Doors and Overhead Doors, Complete in every respect, as shown on the plans.

LS 1 $761,000.00 $761,000.00 $1,150,000.00 $1,150,000.00

Resin Filter Installation - Installation of two (2) Pre-Purchased IX Resin Filter Vessels and Skid Assembly, including Delivery, Handling, and Coordination, for a complete system installed as shown on the plans.

LS 1 $13,000.00 $13,000.00 $50,000.00 $50,000.00

Site Work – All Site Work including Grading, Paving, Site Fence, Unimproved (lawn) Area Restoration, Stormwater Management BMP(s), and Erosion and Sedimentation Control.

LS 1 $155,000.00 $155,000.00 $100,000.00 $100,000.00

Furnish and Install Process Equipment and Instrumentation including, Electromagnetic Flowmeters and System Pressure Transmitter, Chlorination Equipment including, but not limited to, Chlorination Booster Pumps, Cylinder Scales, Chlorine Leak Detection, complete.

LS 1 $87,500.00 $87,500.00 $100,000.00 $100,000.00

$1,074,500.00 $1,540,000.00WELL NO. 14 TOTALS

WELL NO. 7 TOTALS

BASE BID - WELL NO. 9

WELL NO. 9 TOTALS

BASE BID - WELL NO. 7

BASE BID - WELL NO. 14

10/27/2026 Page 2 of 4 JE/C0004956.00 General Bid Tabulation.xlsx

PFAS WATER TREATMENT PROJECT WELL NOS. 1, 3, 5, 7, 9, 14, 15, 37, 43/44, 45

Ref. #26-4A, -B, -C, -D

(1) (2)

DescriptionNo. Quantity Unit Of

Measure Jurich, Inc. Pact Two, LLC

GENERAL CONSTRUCTION - CONTRACT 26-4A

BID TABULATION

Demolition including Existing Site Demolition as shown on the plans; and Existing wellhouse modifications, to include Abandonment of Existing Chlorine Facilities.

LS 1 $58,000.00 $58,000.00 $140,000.00 $140,000.00

Construction of Filter Treatment Building Addition – 30’ wide, 42’ long, Split-Faced Block Building, including Concrete Footings and Floor Slab, Prefabricated Roof Truss System, Building Interior and Exterior Finishes, FRP Doors and Overhead Doors, Complete in every respect, as shown on the plans.

LS 1 $761,000.00 $761,000.00 $1,150,000.00 $1,150,000.00

Resin Filter Installation - Installation of two (2) Pre-Purchased IX Resin Filter Vessels and Skid Assembly, including Delivery, Handling, and Coordination, for a complete system installed as shown on the plans.

LS 1 $13,000.00 $13,000.00 $50,000.00 $50,000.00

Site Work – All Site Work including Grading, Paving, Site Fence, Unimproved (lawn) Area Restoration, Stormwater Management BMP(s), and Erosion and Sedimentation Control.

LS 1 $148,000.00 $148,000.00 $100,000.00 $100,000.00

Furnish and Install Process Equipment and Instrumentation including, Electromagnetic Flowmeters and System Pressure Transmitter, Chlorination Equipment including, but not limited to, Chlorination Booster Pumps, Cylinder Scales, Chlorine Leak Detection, complete.

LS 1 $87,500.00 $87,500.00 $100,000.00 $100,000.00

$1,067,500.00 $1,540,000.00

Demolition including Existing Site and wellhouse demolition, complete in every respect, as shown on the plans.

LS 1 $55,000.00 $55,000.00 $140,000.00 $140,000.00

Construction of Filter Treatment Building – 30’ wide, 42’ long, Split-Faced Block Building, including Concrete Footings and Floor Slab, Prefabricated Roof Truss System, Building Interior and Exterior Finishes, FRP Doors and Overhead Doors, Complete in every respect, as shown on the plans.

LS 1 $761,000.00 $761,000.00 $1,150,000.00 $1,150,000.00

Resin Filter Installation - Installation of two (2) Pre-Purchased IX Resin Filter Vessels and Skid Assembly, including Delivery, Handling, and Coordination, for a complete system installed as shown on the plans.

LS 1 $13,000.00 $13,000.00 $50,000.00 $50,000.00

Site Work – All Site Work including Grading, Paving, Site Fence, Unimproved (lawn) Area Restoration, Stormwater Management BMP(s), and Erosion and Sedimentation Control.

LS 1 $106,000.00 $106,000.00 $100,000.00 $100,000.00

Furnish and Install Process Equipment and Instrumentation including, Electromagnetic Flowmeters and System Pressure Transmitter, Chlorination Equipment including, but not limited to, Chlorination Booster Pumps, Cylinder Scales, Chlorine Leak Detection, complete.

LS 1 $87,500.00 $87,500.00 $100,000.00 $100,000.00

$1,022,500.00 $1,540,000.00

Demolition including Existing Site Demolition as shown on the plans; and Existing wellhouse modifications, to include Abandonment of Existing Chlorine Facilities.

LS 1 $58,000.00 $58,000.00 $140,000.00 $140,000.00

Construction of Filter Treatment Building Addition – 30’ wide, 42’ long, Split-Faced Block Building, including Concrete Footings and Floor Slab, Prefabricated Roof Truss System, Building Interior and Exterior Finishes, FRP Doors and Overhead Doors, Complete in every respect, as shown on the plans.

LS 1 $761,000.00 $761,000.00 $1,150,000.00 $1,150,000.00

Resin Filter Installation - Installation of two (2) Pre-Purchased IX Resin Filter Vessels and Skid Assembly, including Delivery, Handling, and Coordination, for a complete system installed as shown on the plans.

LS 1 $13,000.00 $13,000.00 $50,000.00 $50,000.00

Site Work – All Site Work including Grading, Paving, Site Fence, Unimproved (lawn) Area Restoration, Stormwater Management BMP(s), and Erosion and Sedimentation Control.

LS 1 $115,000.00 $115,000.00 $100,000.00 $100,000.00

Furnish and Install Process Equipment and Instrumentation including, Electromagnetic Flowmeters and System Pressure Transmitter, Chlorination Equipment including, but not limited to, Chlorination Booster Pumps, Cylinder Scales, Chlorine Leak Detection, complete.

LS 1 $87,500.00 $87,500.00 $100,000.00 $100,000.00

$1,034,500.00 $1,540,000.00

BASE BID - WELL NO. 15

WELL NO. 15 TOTALS

BASE BID - WELL NO. 37

WELL NO. 37 TOTALS

BASE BID - WELL NO. 43/44

WELL NO. 43/44 TOTALS

10/27/2026 Page 3 of 4 JE/C0004956.00 General Bid Tabulation.xlsx

PFAS WATER TREATMENT PROJECT WELL NOS. 1, 3, 5, 7, 9, 14, 15, 37, 43/44, 45

Ref. #26-4A, -B, -C, -D

(1) (2)

DescriptionNo. Quantity Unit Of

Measure Jurich, Inc. Pact Two, LLC

GENERAL CONSTRUCTION - CONTRACT 26-4A

BID TABULATION

Demolition including Existing Site Demolition as shown on the plans; and Existing wellhouse modifications, to include Abandonment of Existing Chlorine Facilities.

LS 1 $58,000.00 $58,000.00 $140,000.00 $140,000.00

Construction of Filter Treatment Building Addition – 30’ wide, 42’ long, Split-Faced Block Building, including Concrete Footings and Floor Slab, Prefabricated Roof Truss System, Building Interior and Exterior Finishes, FRP Doors and Overhead Doors, Complete in every respect, as shown on the plans.

LS 1 $761,000.00 $761,000.00 $1,150,000.00 $1,150,000.00

Resin Filter Installation - Installation of two (2) Pre-Purchased IX Resin Filter Vessels and Skid Assembly, including Delivery, Handling, and Coordination, for a complete system installed as shown on the plans.

LS 1 $13,000.00 $13,000.00 $50,000.00 $50,000.00

Site Work – All Site Work including Grading, Paving, Site Fence, Unimproved (lawn) Area Restoration, Stormwater Management BMP(s), and Erosion and Sedimentation Control.

LS 1 $120,000.00 $120,000.00 $100,000.00 $100,000.00

Furnish and Install Process Equipment and Instrumentation including, Electromagnetic Flowmeters and System Pressure Transmitter, Chlorination Equipment including, but not limited to, Chlorination Booster Pumps, Cylinder Scales, Chlorine Leak Detection, complete.

LS 1 $87,500.00 $87,500.00 $100,000.00 $100,000.00

$1,039,500.00 $1,540,000.00

$10,495,000.00 $15,400,000.00BASE BID

AWARD SCENARIOS

WELL NO. 45 TOTALS

BASE BID - WELL NO. 45

10/27/2026 Page 4 of 4 JE/C0004956.00 General Bid Tabulation.xlsx